Queensland Consolidated Acts(1) The applicant for a proposed mining claim must, within the later of the following periods to end, take the actions mentioned in subsection (2)--
(a) 5 business days after the certificate is given to the applicant;
(b) if the mining registrar at any time decides a longer period--the longer period.
(2) For subsection (1), the actions are--
(a) post a copy of the certificate of public notice on the datum post of land the subject of the proposed mining claim (relevant land); and
(b) durably engrave or mark the number of the proposed mining claim on the datum post; and
(c) give a copy of the certificate, the application for the mining claim and any additional document about the application given by the applicant to the mining registrar to--
(i) each owner of relevant land or any other land necessary for access to relevant land; and
(ii) the relevant local government.
(3) The applicant must ensure the copy of the certificate posted on the datum post remains so posted until the end of the last objection day for the application.