401 Procedure if administering authority prepares site management plan

(1) This section applies if the administering authority prepares a site management plan for relevant land under section 391 (3) .
(2) The administering authority must, within 5 business days after preparing the site management plan—
(a) record the details of the plan in the relevant land register in which particulars of the land are recorded; and
(b) give the land’s owner and the relevant local government—
(i) written notice that the plan has been prepared; and
(ii) a copy of the site management plan, including the site suitability statement that accompanies the plan.
(3) The notice must state—
(a) the reasons why the administering authority prepared the site management plan; and
(b) the review or appeal details.