ENVIRONMENTAL PROTECTION ACT 1994 - SECT 401
Procedure if administering authority prepares site management plan
ENVIRONMENTAL PROTECTION ACT 1994 - SECT 401
Procedure if administering authority prepares site management plan
401 Procedure if administering authority prepares site management plan
(1) This section applies if the administering authority prepares a site
management plan for relevant land under section 391 (3) .
(2) The
administering authority must, within 5 business days after preparing the site
management plan— (a) record the details of the plan in the relevant land
register in which particulars of the land are recorded; and
(b) give the
land’s owner and the relevant local government— (i) written notice that
the plan has been prepared; and
(ii) a copy of the site management plan,
including the site suitability statement that accompanies the plan.
(3) The
notice must state— (a) the reasons why the administering authority prepared
the site management plan; and
(b) the review or appeal details.