318ZH Deciding progressive certification application

The administering authority must decide to give or refuse the progressive certification—

(a) if the administering authority requests further information under section 318ZG (1) —within 40 business days after the further information is received by the authority; or
(b) otherwise—within 40 business days after the application is received.