ENVIRONMENTAL PROTECTION ACT 1994 - SECT 285 PRCP schedule must be audited

ENVIRONMENTAL PROTECTION ACT 1994 - SECT 285

PRCP schedule must be audited

285 PRCP schedule must be audited

(1) The holder of a PRCP schedule must commission an audit of the schedule by a rehabilitation auditor for the following periods (each an
"audit period" )—
(a) the 3-year period starting on the day the schedule takes effect;
(b) each 3-year period starting on the day after the previous audit period ended.
(2) The holder must, within 4 months after the end of each audit period, give the administering authority—
(a) the rehabilitation auditor’s report (an
"audit report" ) about the audit that complies with section 286 ; and
(b) a declaration for the audit report stating the holder—
(i) has not knowingly given false or misleading information to the rehabilitation auditor; and
(ii) has given all relevant information to the rehabilitation auditor.
Penalty—
Maximum penalty—100 penalty units.
(3) The declaration mentioned in subsection (2) (b) must be made—
(a) if the holder is an individual—by the holder; or
(b) if the holder is a corporation—by an executive officer of the corporation.