ECONOMIC DEVELOPMENT ACT 2012 - SECT 56 Development scheme required

ECONOMIC DEVELOPMENT ACT 2012 - SECT 56

Development scheme required

56 Development scheme required

(1) As soon as practicable after the priority development area is declared, MEDQ must make a development scheme, under this division, for the entire priority development area.
(2) However, MEDQ may make more than 1 development scheme, under this division, for the priority development area if—
(a) more than 1 interim land use plan was made under section 38 for the priority development area; and
(b) each development scheme is made for 1 or more parts of the priority development area in which development is regulated by a single interim land use plan; and
(c) together, the development schemes provide for the entire priority development area.
(3) A development scheme is a statutory instrument.
(4) To remove any doubt, it is declared that the development schemes mentioned in subsection (2) may be made at different times.