ELECTRICITY ACT 1994 - SECT 20P
20P Exemption for connection of generating plant not supplying electricity to transmission grid or supply network
Section 87 does not apply to the connection of a stand-by generating plant to
a transmission grid or supply network if--
(a) the connection is only when
the operation of the plant is tested; and
(b) electricity is not supplied by
the plant into the grid or network.