62 Evidence of cost

(1) This section applies if--

(a) a regulated contract provides for a prime cost item or provisional sum; and
(b) the building contractor receives a supporting document for the item or sum.

(2) The building contractor must give a copy of the supporting document to the building owner before, or when, seeking payment under the contract of--

(a) if the contract provides for progress payments--the related progress payment; or
(b) if the contract does not provide for progress payments--the amount of the contract price.

Maximum penalty--20 penalty units.

(3) In this section--

supporting document, for a prime cost item or provisional sum included in a regulated contract, means an invoice, receipt or other document showing the cost to the building contractor of the item, or relating to the sum.