Queensland Consolidated Acts(1) The building contractor under a regulated contract must, as required under this section, give the building owner a copy of the appropriate contract information statement for the contract.
Maximum penalty--20 penalty units.
(2) Subsection (1) does not apply to a building contractor if the building contractor gave a copy of the statement to the building owner before the contract was entered into.
(3) The statement must be given to the building owner--
(a) when the contract is entered into; or
(b) as soon as practicable (but within 5 business days) after the contract is entered into.
(4) The statement may be given to the building owner separate from, or attached to, the contract.