Queensland Consolidated Acts(1) This section applies if--
(a) the building contractor under a regulated contract reasonably believes--
(i) the carrying out of the subject work will be delayed; and
(ii) that there is, or will be, a specific reason for the delay attributable to specific circumstances the building contractor reasonably believes exist, or will exist; and
(b) it is not possible for the building contractor to adequately estimate the period of likely delay.
(2) The building contractor must ensure the contract states--
(a) the reason for the likely delay; and
(b) that it is not possible for the building contractor to adequately estimate the period of likely delay; and
(c) the general effect the delay is likely to have on the carrying out of the subject work.
Maximum penalty--40 penalty units.
(3) Subsection (1) does not apply for a delay caused by--
(a) inclement weather; or
(b) the occurrence of non-working days.