Queensland Consolidated Acts(1) If the council's procurement plan states any significant procurement activities, the council must make a plan (a significant procurement activity plan) for each of the activities before it starts.
(2) A significant procurement activity plan must state--
(a) its objectives, and how they will be achieved; and
(b) any alternative ways of achieving the objectives, and why the alternative ways were not adopted; and
(c) a risk analysis of the market from which the relevant goods or services are to be procured.
(3) The objectives must be consistent with the council's procurement plan.
(4) The council may amend a significant procurement activity plan at any time before the end of the financial year to which it relates.