BUILDING AND CONSTRUCTION INDUSTRY PAYMENTS ACT 2004 - SECT 17

17 Payment claims

(1) A person mentioned in section 12 who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment (the respondent).

(2) A payment claim--

(a) must identify the construction work or related goods and services to which the progress payment relates; and
(b) must state the amount of the progress payment that the claimant claims to be payable (the claimed amount); and
(c) must state that it is made under this Act.

(3) The claimed amount may include any amount--

(a) that the respondent is liable to pay the claimant under section 33(3); or
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.

(4) A payment claim may be served only within the later of--

(a) the period worked out under the construction contract; or
(b) the period of 12 months after the construction work to which the claim relates was last carried out or the related goods and services to which the claim relates were last supplied.

(5) A claimant can not serve more than 1 payment claim in relation to each reference date under the construction contract.

(6) However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim.