Queensland Consolidated Acts(1) Subject to section 99, nothing in part 3 affects any right that a party to a construction contract--
(a) may have under the contract; or
(b) may have under part 2 in relation to the contract; or
(c) may have apart from this Act in relation to anything done or omitted to be done under the contract.
(2) Nothing done under or for part 3 affects any civil proceedings arising under a construction contract, whether under part 3 or otherwise, except as provided by subsection (3).
(3) In any proceedings before a court or tribunal in relation to any matter arising under a construction contract, the court or tribunal--
(a) must allow for any amount paid to a party to the contract under or for part 3 in any order or award it makes in those proceedings; and
(b) may make the orders it considers appropriate for the restitution of any amount so paid, and any other orders it considers appropriate, having regard to its decision in the proceedings.