BUILDING ACT 1975 - SECT 86

86 Requirements on approval of application

(1) If the private certifier approves the application, the certifier must--

(a) within 5 business days, give the local government a copy of each of the following documents, identified in the way stated in subsection (2)--
(i) the application;
(ii) the approval documents for the application; and
(b) give the local government the approved form for the documents mentioned in paragraph (a); and
(c) pay the fee fixed by the local government under the Local Government Act 1993, section 1071A(1)(e) for accepting the application and the approval documents.

Maximum penalty--40 penalty units.

(2) For subsection (1)(a), the documents must be identified by--

(a) marking each of them as documents that relate to the application and that have been approved by the private certifier; or
(b) giving them to the local government with another document that--
(i) identifies each of the documents; and
(ii) states their edition number, if any; and
(iii) states that they relate to the application and that they have been approved by the private certifier.
Note--
Under IPA, section 5.7.4, the local government must make the documents required to be given to it under this section available for public inspection and purchase.


[Index] [Table] [Search] [Search this Act] [Notes] [Noteup] [Previous] [Next] [Download] [Help]