41 Deciding variation application

(1) If the building work is being or is to be carried out by or for someone other than the State, the chief executive must consult with the assessment manager about the variation application before deciding it.
(2) The chief executive may consult with any other person about the variation application before deciding it.
(3) After considering the variation application, the chief executive must decide to vary or refuse to vary how the provision applies to the building work.
(4) The chief executive must decide the variation application within 20 business days after the application is made.