Northern Territory Consolidated RegulationsThe time within which a building certifier shall decide an application for a building permit is:
(a) if additional information is not required by the building certifier under section 58 of the Act – 20 days from the day that a completed application is made to the building certifier;
(b) if additional information is required by the building certifier under section 58 of the Act – 20 days from the day that all the additional information required by the building certifier is supplied to the building certifier.