5 Operation of corrosion protection systems requires approval

(1) A person must not operate a corrosion protection system to which this Regulation applies unless the system is the subject of an approval.
Maximum penalty: 200 penalty units, in the case of a body corporate, or 50 penalty units in any other case.
(2) A person must not operate a corrosion protection system to which this Regulation applies otherwise than in accordance with the conditions of an approval to which the system is subject.
Maximum penalty: 200 penalty units, in the case of a body corporate, or 50 penalty units in any other case.
(3) This clause does not apply to a person operating a corrosion protection system:
(a) for the purpose of testing it, but only for not more than a total of 24 hours after completion of:
(i) the installation or extension of the system, or
(ii) any maintenance or repairs carried out on the system, or
(b) with the written consent of the Director-General.