Development near proposed Rozelle Metro Station
88C Development near proposed Rozelle Metro Station
(1) This clause applies
to land shown as CBD Metro Station Extent on the rail corridors map and marked
“Rozelle” and land that is adjacent to that land.
(2) A consent authority
must: (a) give written notice of an application for consent to development on
land to which this clause applies to Sydney Metro within 7 days of receiving
the application, and
(b) before determining the application, take into
account any submissions made by Sydney Metro within 21 days after giving the
notice.
(3) The consent authority must provide Sydney Metro with a copy of
the determination of the application within 7 days after the determination is
made.
(4) This clause applies only in respect of a development application
that is lodged before 31 December 2010.