ELECTRICITY SUPPLY (SAFETY AND NETWORK MANAGEMENT) REGULATION 2008 - REG 8
Network operators may be required to lodge plan
8 Network operators may be required to lodge plan
(1) A network operator must, if notified in writing to do so by the
Director-General, lodge a network management plan with the Director-General,
within such period as may be specified in the notice. Maximum penalty: 100
penalty units (in the case of a corporation) and 25 penalty units (in any
other case).
(2) The network management plan is to consist of the following:
(a) chapter 1 dealing with network safety and reliability,
(b) chapter 2
dealing with customer installation safety,
(c) chapter 3 dealing with public
electrical safety awareness,
(d) chapter 4 dealing with bush fire risk
management.
(3) A network operator that is a distribution network service
provider does not comply with a requirement under subclause (1) in respect of
a network management plan unless the plan complies with any requirements
imposed on the network operator by any relevant conditions of the network
operator’s distribution network service provider’s licence.
(4) A network
operator must implement the plan it lodges under this clause. Maximum penalty:
100 penalty units (in the case of a corporation) and 25 penalty units (in any
other case).
(5) The Director-General, when exercising functions under this
clause, is to have regard to the following: (a) the size, nature and
complexity of the network operator’s transmission or distribution system,
(b) any inadequacy in the planning, design, construction, operation or
maintenance of that system that has given rise to, or may give rise to, a
failure to provide an adequate, reliable or safe supply of electricity of
appropriate quality.