ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 66 Seeking general terms of approval

ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 66

Seeking general terms of approval

66 Seeking general terms of approval

(cf clause 52A of EP[#38]A Regulation 1994)

(1) After it receives a development application for integrated development, the consent authority--
(a) must forward a copy of the application (together with all accompanying documentation) to the approval body whose approval is required, and
(b) must notify the approval body in writing of the basis on which its approval is required and of the date of receipt of the development application, and
(c) if known at that time, must notify the approval body in writing of the dates of the relevant submission period if the application is to be publicly notified under Schedule 1 to the Act.
(2) The application must be forwarded to the relevant approval body within 14 days after the application is lodged.