ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 25 Additional information requested by relevant planning authority

ENVIRONMENTAL PLANNING AND ASSESSMENT REGULATION 2000 - REG 25

Additional information requested by relevant planning authority

25 Additional information requested by relevant planning authority

(1) If an environmental planning instrument requires or permits a development control plan to be prepared and submitted to the relevant planning authority, the planning authority may request the owners (as referred to in section 3.44 of the Act) who are submitting the plan to provide the planning authority with such additional information as the planning authority considers necessary for the purposes of making the plan.
(2) Any such request is to be in writing.
(3) The information that the relevant planning authority may request is limited to information relating to any relevant matter referred to in an environmental planning instrument.
(4) In accordance with section 3.44(6) of the Act, the 60-day period referred to in section 3.44(5) of the Act may be extended by the number of days from the day on which the request for the information was made until the day on which the information is provided or on which the owners refuse to supply the information (whichever is the sooner).
(5) If the owners refuse to supply the requested information, the development control plan is taken not to have been submitted to the relevant planning authority.