186O Installation of fire sprinkler systems in facilities with 1 March 2016 as
nominated completion date
(a) before 1 September 2013, provide an implementation plan to the
Implementation Committee, and
(b) before 1 March 2014 (and every 1 September
and 1 March after that date unless the fire sprinkler system has been
installed), provide a progress report to the Implementation Committee.
(2) An
implementation plan is to--
(a) specify details of the proposed installation
of the fire sprinkler system (including any approvals required for the
installation), and
(b) describe any work completed for the purposes of the
installation, and
(c) provide an estimate of the date by which the
installation will be completed, and
(d) specify the capital investment value
of installing the fire sprinkler system, and
(4) In this clause,
"approval" means an approval under the Act and includes a development consent,
a complying development certificate or any other certificate under Part 6 of
the Act.