76 Roads authorities to notify TfNSW of proposal to carry out major road work

(1) A roads authority may not carry out road work on a public road (being work that has an estimated cost of more than $2,000,000 or such other amount as may be prescribed by the regulations) unless it has forwarded particulars of the proposed work to TfNSW at least 28 days before the commencement of the work.
(2) If it appears that the proposed work may affect the development, or further development, of a main road, tollway or transitway, TfNSW may, within that period of 28 days, require the roads authority--
(a) to give effect to specified amendments or alterations in the construction of the work, or
(b) to defer construction of the work for a specified period.