• Specific Year
    Any

ROADS ACT 1993 - SECT 221 Roads authority to supply TfNSW with plans and specifications

ROADS ACT 1993 - SECT 221

Roads authority to supply TfNSW with plans and specifications

221 Roads authority to supply TfNSW with plans and specifications

(1) Before carrying out any work for which it proposes to require a roads authority to pay the whole or any part of the cost, TfNSW--
(a) must provide the roads authority with plans and specifications of the work, and
(b) must serve notice on the roads authority of its proposal and of its estimate of the cost of the work.
(2) If, within 90 days after service of the notice, the roads authority makes written submissions to TfNSW in relation to the matters specified in the notice, TfNSW must give the roads authority written notice of TfNSW's decision in relation to the submissions--
(a) if the roads authority has indicated that it wishes to be heard and to call evidence in relation to the matter, within 28 days after hearing the roads authority, or
(b) in any other case, within 28 days after receiving the submissions.