221 Roads authority to supply TfNSW with plans and specifications
(1) Before carrying out any work for which it proposes to require a roads
authority to pay the whole or any part of the cost, TfNSW--
(a) must provide
the roads authority with plans and specifications of the work, and
(b) must
serve notice on the roads authority of its proposal and of its estimate of the
cost of the work.
(2) If, within 90 days after service of the notice, the
roads authority makes written submissions to TfNSW in relation to the matters
specified in the notice, TfNSW must give the roads authority written notice of
TfNSW's decision in relation to the submissions--
(a) if the roads authority
has indicated that it wishes to be heard and to call evidence in relation to
the matter, within 28 days after hearing the roads authority, or
(b) in any
other case, within 28 days after receiving the submissions.