Proceedings for breach of warranties
18E Proceedings for breach of warranties
(1) Proceedings for a breach of a statutory warranty must be commenced within
7 years after: (a) the completion of the work to which it relates, or
(b) if
the work is not completed: (i) the date for completion of the work specified
or determined in accordance with the contract, or
(ii) if there is no such
date, the date of the contract.
(2) The fact that a person entitled to the
benefit of a statutory warranty specified in paragraph (a), (b), (c), (e) or
(f) of section 18B has enforced the warranty in relation to a particular
deficiency in the work does not prevent the person from enforcing the same
warranty for a deficiency of a different kind in the work (
"the other deficiency") if: (a) the other deficiency was in existence when the
work to which the warranty relates was completed, and
(b) the person did not
know, and could not reasonably be expected to have known, of the existence of
the other deficiency when the warranty was previously enforced, and
(c) the
proceedings to enforce the warranty in relation to the other deficiency are
brought within the period referred to in subsection (1).