ENVIRONMENTAL PLANNING AND ASSESSMENT ACT 1979 - SECT 75R

Application of other provisions of Act

75R Application of other provisions of Act

(1) Part 4 and Part 5 do not, except as provided by this Part, apply to or in respect of an approved project (including the declaration of the project as a project to which this Part applies and any approval or other requirement under this Part for the project).
(2) Part 3 and State environmental planning policies apply to:
(a) the declaration of a project as a project to which this Part applies or as a critical infrastructure project, and
(b) the carrying out of a project, but (in the case of a critical infrastructure project) only to the extent that the provisions of such a policy expressly provide that they apply to and in respect of the particular project.
(3) Environmental planning instruments (other than State environmental planning policies) do not apply to or in respect of an approved project.
Note: See sections 75J (3) and 75O (3) in relation to the application of such instruments when an application for approval of a project or a concept plan is being considered.
(3A) The Minister may, by order published on the NSW legislation website, amend an environmental planning instrument to authorise the carrying out of any of the following development (or to remove or modify any provisions of the instrument that purport to prohibit or restrict the carrying out of any of the following development):
(a) development that is an approved project,
(b) development that is a project for which a concept plan has been approved (whether or not approval for carrying out the project or any part of the project is subject to this Part).
(4) Divisions 6 and 6A of Part 4 apply to projects (and the giving of approval for the carrying out of projects under this Part) in the same way as they apply to development and the granting of consent to the carrying out of development under Part 4, subject to any necessary modifications and any modifications prescribed by the regulations. However, a condition cannot be imposed under section 94, 94A, 94EF or 94F unless that section would have applied if this Part did not apply to the project and a development consent were granted.
(5) Division 2A of Part 6 applies to a critical infrastructure project only to the extent that the regulations so provide.