ENVIRONMENTAL PLANNING AND ASSESSMENT ACT 1979 - SECT 75M
Application for approval of concept plan for project
75M Application for approval of concept plan for project
(1) The Minister may authorise or require the proponent to apply for approval
of a concept plan for a project.
(2) The application is to: (a) outline the
scope of the project and any development options, and
(b) set out any
proposal for the staged implementation of the project, and
(c) contain any
other matter required by the Director-General.
A detailed description of the
project is not required.
(3) The application is to be lodged with the
Director-General.
(3A) A single application may be made for approval of a
concept plan for a project and for approval to carry out any part or aspect of
the project. In that case, environmental assessment requirements, public
consultation and reports under this Division and Division 2 with respect to
the project may be combined.
(4) If an environmental planning instrument
requires the preparation of a development control plan before any particular
or kind of development is carried out on any land, the obligation may be
satisfied for a project by an application for approval and approval of a
concept plan in respect of the land concerned (but only if the Minister
authorises or requires an application for approval of the concept plan).