ENVIRONMENTAL PLANNING AND ASSESSMENT ACT 1979 - SECT 75F
Environmental assessment requirements for approval
75F Environmental assessment requirements for approval
(1) The Minister may, after consultation with the Minister for the
Environment, publish guidelines in the Gazette with respect to environmental
assessment requirements for the purpose of the Minister approving projects
under this Part (including levels of assessment and the public authorities and
others to be consulted).
(2) When an application is made for the Minister’s
approval for a project, the Director-General is to prepare environmental
assessment requirements having regard to any such relevant guidelines in
respect of the project.
(3) The Director-General is to notify the proponent
of the environmental assessment requirements. The Director-General may modify
those requirements by further notice to the proponent.
(4) In preparing the
environmental assessment requirements, the Director-General is to consult
relevant public authorities and have regard to the need for the requirements
to assess any key issues raised by those public authorities.
(5) The
environmental assessment requirements may require an environmental assessment
to be prepared by or on behalf of the proponent in the form approved by the
Director-General.
(6) The Director-General may require the proponent to
include in an environmental assessment a statement of the commitments the
proponent is prepared to make for environmental management and mitigation
measures on the site.
(7) This section is subject to section 75P. Note:
Section 75P enables the Minister to determine environmental assessment
requirements for approval to carry out the project or any stage of the project
when giving approval to a concept plan for the project under Division 3.