For this Part, an outstanding acquittals plan:
- (a)
- must list all activities
in relation to the construction and operation of the launch facility and
operation of the launch vehicles for which an approval or other authorisation
of any kind is required by or under any other Australian law; and
- (b)
- must, for each activity listed under paragraph (a), describe the
arrangements for obtaining the approval or authorisation or each approval or
authorisation, including the time frame within which the approval or
authorisation must be obtained; and
(c) must contain a schedule that, in relation to each particular matter
referred to in a plan mentioned in paragraph 2.04 (2) (a) or
(c) or, if applicable, paragraph 2.04 (2) (b) or subparagraph
2.04 (2) (e) (ii) that is to be verified, validated or
acquitted in a way referred to or described in the plan:
- (i)
- lists the
matter to be verified, validated or acquitted; and
- (ii)
- describes the arrangements for obtaining the verification, validation or
acquittal, including the time frame within which it must be obtained.