NATIONAL MEASUREMENT REGULATIONS 1999 - REG 38 Decision not to certify, or delay in certifying, measuring instruments

NATIONAL MEASUREMENT REGULATIONS 1999 - REG 38

Decision not to certify, or delay in certifying, measuring instruments

  (1)   If the certifying authority decides not to certify a measuring instrument, the authority must give written notice of the reasons for its decision to the applicant as soon as practicable.

  (2)   If the authority has not granted an application or given notice to the applicant under subregulation   (1) within 3 months after receiving the application, the authority must, at the request of the applicant, give written notice to the applicant of the reasons for the delay.