SOCIAL SECURITY (ADMINISTRATION) ACT 1999 - SECT 27AA Time limit for claims for Disaster Recovery Allowance

SOCIAL SECURITY (ADMINISTRATION) ACT 1999 - SECT 27AA

Time limit for claims for Disaster Recovery Allowance

  (1)   A claim for a Disaster Recovery Allowance relating to a Part   2.23B major disaster must be lodged within 6 months after the determination of the disaster under section   36A of the 1991 Act.

  (2)   However, the claim may be lodged more than 6 months after the determination if the Secretary is satisfied that:

  (a)   there are special circumstances applying to the person's claim that justify a late lodgement; and

  (b)   the claim is lodged within a reasonable period having regard to those circumstances.