WATER AND SEWERAGE ACT 2000 - SECT 9

Amendment of approved plans

    (1)     The owner of premises to which a plan approved by a certifier relates may apply to a certifier for approval of an amendment of the plan.

    (2)     The certifier—

        (a)     must refuse the application if satisfied that the proposed amendment requires reconsideration of the plan approval; or

        (b)     may approve the amendment and amend the plan accordingly if—

              (i)     satisfied that reconsideration of the plan approval is not required; and

              (ii)     the requirements of section 8 (2), other than paragraph (a), have been complied with in relation to the amendment.

    (3)     A regulation may prescribe when the proposed amendment of a plan does, or does not, require reconsideration of the plan approval.

    (4)     A certifier who approves an amendment must keep all documents relating to the amendment for 12 months.

    (5)     In this section, a reference to a "plan approval" includes a reference to an approval that has been amended in accordance with this section.