BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2009 - SECT 25 Respondent must pay adjudicated amount

BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2009 - SECT 25

Respondent must pay adjudicated amount

If an adjudicator decides that a respondent must pay an adjudicated amount to a claimant, the respondent must pay the amount to the claimant on or before—

        (a)     the day 5 business days after the day the adjudicator's decision is given to the respondent; or

        (b)     if the adjudicator decides a later day under section 24  (1) (b)—the later day.