BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2009 - SECT 25 Respondent must pay adjudicated amount
BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2009 - SECT 25
Respondent must pay adjudicated amountIf an adjudicator decides that a respondent must pay an adjudicated amount to a claimant, the respondent must pay the amount to the claimant on or before—
(a) the day 5 business days after the day the adjudicator's decision is given to the respondent; or
(b) if the adjudicator decides a later day under section 24 (1) (b)—the later day.