BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2009 - SECT 13 Due date for payment
BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) ACT 2009 - SECT 13
Due date for payment(1) A progress payment under a construction contract is payable on the earlier of the following:
(a) 15 business days after a payment claim is given under part 4 in relation to the payment;
(b) the day when the payment becomes payable under the contract.
(2) Interest is payable on the unpaid amount of a progress payment that is payable under subsection (1) at the greater of the following:
(a) the rate of interest applying from time to time under the Court Procedures Rules 2006
, schedule 2, part 2.2 (Interest after judgment);
(b) the rate stated under the construction contract.
(3) If a progress payment is payable under subsection (1), the claimant is entitled to exercise a lien in relation to the unpaid amount over any unfixed plant or materials supplied by the claimant for use in connection with carrying out construction work for the respondent.
Note 1 Claimant— s ee s 15.
Note 2 Respondent— s ee s 15.
(4) Any lien or charge over the unfixed plant or materials existing before the date on which the progress payment becomes payable takes priority over a lien under subsection (3).
(5) Subsection (3) does not create any right against a third party who is the owner of the unfixed plant or materials.