Australian Capital Territory Bills Explanatory Statements
[Index]
[Search]
[Download]
[Bill]
[Help]
PLANNING AND DEVELOPMENT AMENDMENT BILL 2009
2009
THE LEGISLATIVE ASSEMBLY FOR THE
AUSTRALIAN CAPITAL
TERRITORY
PLANNING AND DEVELOPMENT
AMENDMENT BILL 2009
EXPLANATORY
STATEMENT
Presented
by
Mr Andrew Barr
MLA
Minister for
Planning
This Explanatory Statement relates to the Planning
and Development Amendment Bill 2009 (the Bill) as introduced into the
Legislative Assembly.
Background
The purpose of the Bill is to amend the Planning
and Development Act 2007 (the Act) and the Planning and Development
Regulation 2008 (the regulation).
The Act
commenced on 31 March 2008 and introduced, amongst other things, leading
practice for the assessment of development applications; provided clarity and
consistency in the management of leasehold land; and strengthened compliance
mechanisms. Through monitoring during the initial implementation phase, and in
consultation with Government, Agencies, industry and the community, a number of
Act modifications were made in order to respond to issues identified. Further
fine tuning has also occurred in some areas following operational review of the
particular sections of the Act.
The Act
modifications were made through the regulation making power in section 429 of
the Act. Section 431 of the Act requires section 429 and regulations made
under section 429 to cease two years after the commencement of the Act (i.e. two
years after 31 March 2008). Section 429 and the regulations under this section
are not saved by section 88 of the Legislation Act 2001 (because of the
exception in section 88(2) of the Legislation
Act).
The Bill is composed, of those
modifications to the Act, that it is considered should be made permanent. Not
all modifications made are required to be made permanent however. This is
because they were transitional and are no longer required.
The modifications covered the following
general
areas:
o lease
variations in designated areas and conversion of Commonwealth leases of National
land to territory leases upon revocation of National Land
status;
o development
assessment processes including transitional
provisions;
o use
as
development;
o granting
of leases and payment;
and
o extension
of time to commence or complete building and
development.
The table below sets out the
section of the Act that is amended, details of the amending regulation and the
clause of this Bill that amends the Act so as to entrench the
modification.
|
Item
|
Act Section
|
Clause in Bill
|
Latest Amendment
|
|
Application of assessment tracks to development
proposals
§ PCO - Technical,
clarity (refer s114(2), clause 5)
|
113 (2)
|
4
|
Refer to clause 5
|
|
Application of assessment tracks to development
proposals
§ Technical,
clarity
|
114 (2) refer 113
(3)
|
5
|
No: 04, S/L2008/41 Sept 2008, clause 14, 20.1 new
section 429AA
|
|
Development proposal for lease variation in designated
area
§ Defines
‘merit’ track as applicable assessment track
|
131A
|
6
|
No: 04, S/L2008/41 Sept 2008, clause 14, 20.1 new
section 131A
|
|
Applications to amend development
approvals
§ Technical refer new
section 198C
|
197 (1)
|
7
|
No: 03, S/L2008/33 Aug 2008, clause 21, 5.1 section
429A
|
|
Deciding applications to amend development
approvals
§ Technical refer new
section 198B
|
198 (4)
|
8
|
No: 03, S/L2008/33 Aug 2008, clause 21, 5.1 section
429B
|
|
Exception to referral requirement under s198 (1)
(b)
§ Technical,
consistency
|
198A
|
9
|
No: 03, S/L2008/33 Aug 2008, 21, 5.1 section 429C new
section 198A
|
|
Exception to notification requirement under s198 (1)
(b)
§ Waiver
notification
|
198B
|
9
|
No: 03, S/L2008/33 Aug 2008, clause 21, 5.1 section 429C
new section 198B
|
|
When development approvals do not require
amendment
§ Deemed
compliance
|
198C
|
9
|
No: 03, S/L2008/33 Aug 2008, clause 21, 5.1 section 429C
new section 198C
|
|
Development other than use lawful when
begun
§ Clarity
|
203 (1) (c)
|
10
|
No: 03, S/L2008/33 Aug 2008, clause 21, 5.1 section
429D
|
|
Use as development lawful when begun
§ Clarity
|
204 (1) (c)
|
11
|
No: 03, S/L2008/33 Aug 2008, clause 21, 5.1 section
429E
|
|
Payment for leases
Previous
amendments: No: 04, S/L2008/41, clause 15, Scrutiny
02/2009. No: 06 S/L2009/18, clause 4, Scrutiny
08/2009.
§ Payment
in-kind
|
246 (2) (c) &
(d)
246 (3) (b) &
(c)
246, 3A
|
12
13
14
|
No: 09, S/L2009/38, July 2009, clause13, New sections
429EAA and 429EAB
|
|
Payment for adjoining concessional
leases
§ Technical, payment
regime
|
246A
|
15
|
No: 06, S/L2009/18, May 2009, clause 5, 20.9 New
sections 461B
|
|
Grant of further leases
§ Payment
|
254 (1) (e)
|
16
|
No: 04 S/L2008/41 Sept 2008, clause 15, 20.1 new
section 429EB
|
|
Grant of further leases includes authorised
use
§ Clarity
|
255 (4)
|
17
|
No: 04, S/L2008/41 Sept 2008, clause 15, 20.1 new
section 429EC
|
|
Determination of amount payable for further leases-rural
land
§ Allows payment by
instalments
|
280
|
18
|
No: 04, S/L2008/41 Sept 2008, clause 15, 20.1 new
section 429ED
|
|
Application for extension of time to commence or
complete building and development
Previous
amendments: No: 01, S/L2008/08, Scrutiny 54/2008,
No: 03, S/L2008/33, Scrutiny 58/2008, No: 04, S/L2008/41, Scrutiny
02/2009
§ Clarity, Government
policy
|
298A (3), (4) & (5)
|
19
|
No: 08, S/L2009/35, June 2009, clause 21, Section
298A
|
|
Extension of time to commence or complete building and
development
§ Removes limit on
extensions allowed
|
298B (5) & (6)
|
20
|
No: 04, S/L2008/41, Sept 2008, clause 17, New section
429G
|
|
Conversion of Commonwealth leases – revocation of
National Land status
§ Technical,
omission
|
312A
|
21
|
No: 03, S/L2008/33, Aug 2008, clause 23, 459B New
section 312A
|
|
Transitional – Expiry - excluded provisions (from
2010 ending)
|
431 (2) (a) & (b)
|
22
|
No: 02, S/L 2008/27 June 2008, clause 4,
5.1A
|
|
Transitional – applications (DA) lodged before
commencement day
§ Technical,
process
|
442 (1)
|
23
|
No: 01, S/L2008/08 March 2008, clause 5, 5.2
substitute
|
|
Transitional – applications (DA) lodged before
commencement day
§ Technical,
process
|
442 (4)
|
24
|
No: 01, S/L2008/08 March 2008, clause 5, 5.3 New section
442 (4)
|
|
Transitional – DA lodged on or after commencement
– EDP
§ Technical,
process
|
442C
|
25
|
No: 02, S/L2008/27 June 2008, clause 5, 5.3A new
section
|
|
Transitional – approvals under repealed
Act
§ Technical,
process
|
444
|
26
|
No: 01, S/L2008/08 March 2008, clause 5,
5.4
|
|
Transitional – commencement of DA under repealed
Act
§ Technical,
process
|
444A
|
26
|
No: 02, S/L2008/27 June 2008, clause 6, 5.4A New section
444A
|
|
Transitional – approval in force with uncommenced
extension
§ Technical,
process
|
445 (2) (a)
|
27
|
No: 01, S/L2008/08 March 2008, clause 5,
5.5
|
|
Power to make lease and development
conditions
§ Technical,
process
|
446
|
28
|
No: 02, S/L2008/27 June 2008, clause 7,
5.5A
|
|
Transitional – application for development
approval if lease and development condition
§ Technical,
process
|
446A
|
28
|
No: 02, S/L2008/27 June 2008, clause 7,
5.5A
|
|
Transitional – extended meaning of development
approval – s199
§ Technical,
process
|
447
|
29
|
No: 01, S/L2008/08 March 2008, clause 5,
5.6
|
|
Transitional – applications for certain grants
before commencement day
§ Technical,
process
|
458
|
30
|
No: 04, S/L2008/41 Sept 2008, clause 18,
20.6A
|
|
Transitional—applications for certain grants
decided after 6 months
§ Technical,
process
|
459
|
31
|
Original Act provision
|
|
Transitional – contracts before commencement day
to grant leases
§ Technical,
process
|
459A
|
32
|
No: 03, S/L2008/33 Aug 2008, clause 22, 5.7 new section
459A
|
|
Payment for leases to community organisations
§ Technical, payment
regime
|
461A
|
33
|
No: 06, S/L2009/18, May 2009, clause 5, 20.9 New
sections 461A
|
The majority of the provisions are a literal
translation of the provision as it appeared in the regulation (that made the
modification). However there are some minor wording variations. This is
because drafting styles change; different drafters adopt different ways of
delivering the same outcome and in some instances the Parliamentary
Counsel’s Office have clarified previous drafting. These variations may
appear as simple as using a different format to set-out the same words as in
clause 8; or terminology as in clause 7 where the word ‘application’
is changed to ‘proposal’ which better reflects the stage that the
proposed development is at in the assessment process; or the inclusion of a new
sub-section, within the existing provision, that articulates the intent of the
provision and removes doubt about the intended outcome. This drafting style is
used consistently within the Act to assist persons, including industry and
community members, to understand the intent of the provision. However, despite
these minor drafting inconsistencies there is no change in the policy or
application of the provisions.
Because of the
nature of the Bill, that is, a translation of an already existing provision, the
explanation of the amendments contained in this explanatory statement need to be
read with this in mind. For instance where the explanatory statement states
‘new section’ as it does at clause 6 this does not mean that the
provision is in fact new. Rather it means that the provision is new to the Act
but has in fact been in operation since the relevant regulation containing the
provision was notified. For this example clause 6 was introduced through
Planning and Development Amendment Regulation 2008 No: 4, S/L 2008/41 and
has been in operation since September 2008.
Each amending regulation has had an
explanatory statement prepared which is available on the ACT Legislation
Register. The regulation is republished each time it is amended and all
versions of the regulation (and the amending regulation) are available also on
the ACT Legislation Register. The Planning and Development Regulation 2008,
Schedule 5 list modifications to the Act made up-until June 2008 and has
been renumbered to Schedule 20 in republications post July
2008.
Because the proposed Bill seeks to
translate these Act modifications, as permanent amendments to the Act, schedule
20 needs to reflect these changes. The effect of this amendment will mean that
there will be no provisions listed in schedule 20, subsequently it will be
redundant. The Bill therefore amends the Planning and Development Regulation
2008 to remove these provisions.
Outline of
Provisions
Part 1 Preliminary
Clause 1 Name of
Act
Names the Act as the Planning and Development
Amendment Act 2009.
Clause 2
Commencement
Provides
the commencement provisions, noting that this Act will commence 7 days after its
notification day. The naming and commencement provisions automatically commence
on the notification day (see Legislation Act , s75(1)).
Part 2 Planning and Development Act
2007
Clause 3 Legislation
amended—pt 2
Declares that it is the Planning and Development Act
2007 that is being amended.
Clause 4 Relationship between
development proposals and development applications New section 113
(3)
Inserts a new clause 113(3) to clarify subsection (2) is
subject to section 123 (Impact track applicability). This amendment ensures
consistency in the Act, through reference to s123. Section 123 requires a
development application to be assessed in the impact track in the specified
circumstances. Therefore, the development tables are not the sole determinant of
the required assessment track. The amendment makes this
clear.
Clause 5 Application of
assessment tracks to development proposals Section 114 (2)
Omits subsection 114 (2) as this provision is
encompassed by section 113 (2). The modification of section 113 in clause 4
ensures the omitted section 114 (2) remains in force.
The original intention of 114 (2) was to
specify that a development application for a development proposal must be
assessed in the assessment track determined by the Act development table. The
provision also inserted a new subsection (3) and stated that the section is
subject to section 123 of the Act.
This
amendment ensured consistency in the Act, through reference to s123. Section 123
requires a development application to be assessed be in the impact track in the
specified circumstances. Therefore the development tables are not the sole
determinant of the required assessment track. The original amendment made this
clear.
The original intentions of this
amendment are now provided for in section 113.
Clause 6 New section
131A
Provides that div
7.2.5 of the Act should be read as if new section 131A were inserted. New
section 131A determines how a development proposal for approval of a lease
variation in a designated area must be assessed and dealt with under the Act.
The interrelationship of territory land and designation under Commonwealth law
is a complex matter. A designated area is defined in the Dictionary to the Act
– see the Australian Capital Territory
(Planning and Land Management Act 1988 (Cwlth) (PALM), section 4 -
Designated Area means an area of land specified in the National Capital
Plan under section 10 of PALM. The Territory has exempted effectively all
development in a designated area from requiring any territory approvals,
requiring only lease variations to be subject to approval processes. The Act is
amended to apply merit track provisions to the processing of an application of a
development proposal for a lease variation in a designated area. The amendment
also excludes any reference to the territory plan in determining such
applications, as Commonwealth law provides that the territory plan does not
apply to designated areas.
Clauses 7, 8 and
9
The intention of these clauses is to overcome
delays caused by minor contraventions of development approvals (DAs) by
inserting a range of provisions that will remove the need to seek further
development approvals or amendment to an existing development approval. The
provisions prescribe the tolerances within which development under a DA may
lawfully contravene the DA without the need for another DA or a DA
amendment.
Historically, there have been
significant levels of minor contravention of DAs, for example, the height of
floors are not constructed to the exact millimetre dimensions stated in the DA,
sometimes varying by +/- 300mm or more. Also, many people building their home
often visit the site during construction and discover that construction could
benefit from minor variations, such as altering windows or door or making
certain rooms larger, etc.
Under the Land
(Planning and Environment) Act 1991 (the repealed Act), such contraventions
and variations were readily regularised by way of a regularising DA amendment
after the fact. Such amendments, depending on their nature, were approved
relatively quickly. Any significant delay in obtaining the relevant DA amendment
can result in delayed lawful occupation of completed buildings which adds to
development holding costs.
Sectors of the ACT
construction industry expressed concern with increased delays during
implementation of the Planning and Development Act 2007 and new territory
plan. These sectors expressed the view that a tolerance on allowable changes to
construction under a DA would benefit all stakeholders, including home-owners
without significant detriment.
Clause 9 also
permits minor DA amendments to be assessed and processed quickly without further
public consultation on the development or further referral to a government
agency for advice. The ability to proceed without these steps is tightly
circumscribed and is consistent with the approach already taken in the Act with
amendments to development applications
Clause 7 Applications to amend development approvals
Section 197(1)
Substitutes a new section
197(1) in the Act which adds paragraph (c) to the section. The additional
paragraph (c) is necessary because of the insertion of new section 198C into the
Act by this Bill. New section 197(1) provides that the section applies
if:
(a) the planning and land authority has
given development approval for a development proposal;
and
(b) the development proposal changes so that it
is not covered by the development approval;
and
(c) section 198C (When development approvals do
not require amendment) does not apply to the changed development
proposal.
The effect of section 197(1)(c) and
section 198C is summarised below (see clause 9).
Clause 8 Deciding
applications to amend development approvals Section 198(4)
Substitutes a new section 198(4) in the Act. New section
198(4) is necessary because of the insertion of new section 198B by this Bill
(see clause 9). New section 198(4) continues to provide that if public
notification of a proposed development is required then only the application for
the amendment need be publicly notified. The only change to s198(4) is to state
that s198(4) is not relevant if the requirement for public notification is
removed by the operation of new section 198B.
Clause 9 New sections 198A to
198C
Inserts new sections 198A, 198B and 198C in the
Act.
Section 198A Exception to referral
requirement under s198(1)(b)
New section 198A
specifies that, despite section 198(1)(b), the authority need not refer an
application to amend a development approval to an entity if satisfied that the
amendment does not affect any part of the development approval in relation to
which the entity made a comment. This provision is consistent with the approach
taken in section 145(4) with respect to changes to development applications.
Section 198B Exception to notification
requirement under s198(1)(b)
New section 198B specifies that, despite section
198(1)(b), the planning and land authority (the authority) need not publicly
notify an application for the amendment of a development approval if satisfied
that:
(a) no-one other than the applicant will be adversely
affected by the amendment; and
(b) the environmental impact caused by the amendment
will do no more than minimally increase the environmental impact for the
development.
New section 198B is consistent
with the approach taken in existing section 146(3) with respect to changes to
development applications.
Section 198C When
development approvals do not require amendment
New section 198C specifies that the section applies
if:
(1) (a) the authority has given development approval for
a development application; and
(b) the development is changed so that it is not covered
by the approval; and
(c) a circumstance prescribed by regulation under
subsection (3) applies.
(2) the changed development proposal is taken to be in
accordance with the development approval
(3) A regulation may prescribe circumstances for
subsection (1)(c ).
Under new section 198C(3),
a regulation may prescribe the circumstances in which a development in
accordance with the changed development is taken to be in accordance with the
development approval.
New section 198C applies
in the situation where a development is authorised by a development approval but
the actual development as built (or part built) turns out to exceed some of the
dimension parameters in the development approval. If the built form exceeds the
approval parameters but is still within the tolerance range specified in the
regulation under 198C(3), the building is deemed to still comply with the
requirements of the development approval and a new or amended approval is not
required. Similarly, if the building includes a new feature outside the terms of
the development approval (such as a new door or window) and the new feature is
authorised under 198C(3), then again the building is deemed to comply with the
approval.
For example, if the building is a
class 1 building (e.g. a house) and the internal arrangement of the house's
walls, ceilings, kitchen and bathroom fit outs are varied so they are outside
the terms of the development approval, the building is deemed to comply with the
approval if the variation is authorised under 198C. The provision effectively
permits the regulation to exempt specified matters from requiring a development
approval amendment in the same way as the existing regulations exempt specified
matters from requiring development
approval.
Amended section 197, section 198 and
new section 198C are intended to work as follows. Section 198C must be
considered to determine whether an amendment to a development approval is
necessary. If an amendment is necessary then amended section 197 gives the
proponent the ability to apply for an amendment. Section 198 sets out the
process for deciding such an application.
Clause 10 Development other
than use lawful when begun Section 203 (1) (c)
Adds the words “because of an amendment of this
Act” to the end of section 203(1)(c). The addition of these words
clarifies that the provision only applies if the Act changes but not if the
development, of itself, changes so that it is no longer exempt development. As
the provision stands, it could perhaps be interpreted as making lawful a
development that started out being an exempt development under schedule 1 of the
regulation but, because of a change to the nature of the development during
construction, it stops being exempt. This was not the intention of the provision
and the modification clarifies the intent.
Clause 11 Use as development
lawful when begun Section 204 (1) (c)
The new section 204(1)(c) adds the words “because
of an amendment of the development table or regulation” to the end of
s204(1)(c). The addition of these words clarifies that the provision only
applies if a development table or regulation changes but not if the development,
of itself, changes so that it is no longer exempt development. As the provision
stands, it could perhaps be interpreted as making lawful a development that
started out being an exempt development under schedule 1 but, because of a
change to the nature of the development during construction, it stops being
exempt. This was not the intention of the provision and the modification
clarifies the intent.
Clause 12 Payment for leases
Section 246 (2) (c) and (d)
Substitutes new sections 246 (2) (c) & (d) in the
Act. New section 246(2)(c) omits the specific reference to “rural
leases” because it is not necessary because of the operation of amended
s254 and s280 of the Act (see clauses 16 and 18 of this Bill). The amendments
allow a further grant of a rural lease to be made where an undertaking to pay
rent and/or for payment by instalments is
made.
New section 246(2)(d) extends the
operation of the former charging policies under the repealed Act (section 169).
Section 246 (1) of the Act states that the authority may not grant a lease for
less than market value. Section 246 (2) states that subsection (1) does not
apply in particular circumstances, that is, there are specific conditions under
which the authority may grant a lease for less than market value. A lease to
which the new section 461A (inserted by Clause 33 of this Bill) or new section
246A (inserted by clause 15 of this Bill) applies are leases which the authority
may grant for less than market value.
Clause 13 Section 246(3) (b) and
(c)
Substitutes new paragraphs (b) and (c) in
section 246(3). Under section 246 the planning and land authority must not grant
a lease other than for payment of an amount that is not less than the market
value of the lease. New paragraphs (b) and (c) of s246(3) clarify when an entity
is taken to have paid not less than the market value for a lease. The present
s246(3) makes it clear that payment for a lease can include a combination of
money and infrastructure or works. However, the infrastructure or works must be
provided on the sale lease and not another lease. New paragraphs (b) and (c)
expand section 246(3). Under amended s246(3), an entity pays an amount that is
not less than the market value of a lease if:
“(a) the entity pays less than the market value of
the lease (the monetary component); and
(b) the entity provides another component (a non
monetary component) comprising:
(i) infrastructure or other work in relation to the
lease or another lease; or
(ii) 1 or more of the following under a deed or
agreement with the Territory or Territory authority:
(A) goods;
(B) services;
(C) works; and
(c) the total value of the monetary component and the
non monetary component is not less than the market value of the
lease.”
Clause 14 New section 246
(3A)
Inserts section 246(3A) in the Act for
similar reasons to those mentioned above in Clause 13. Under section 246(2)(e),
s246(1) does not apply to the grant of a lease prescribed by regulation for
which the amount prescribed by regulation has been paid. New section 246(3A)
makes it clear that the amount prescribed by regulation can be comprised of a
monetary component and a non monetary component as described in new
s246(3A)(b).
Clause 15 New section
246A
New section 246A specifies the conditions
under which a person may apply for the grant of a new lease where the new lease
adjoins another lease granted to the person. The granted lease must be a
concessional lease. Payment for the new lease may be calculated in the same way
the granted concessional lease was calculated. If, for example, payment for the
granted concessional lease was calculated under repealed Act provisions, payment
for the new lease may also be calculated using the repealed Land Act
provisions.
Clause 16 Grant of further leases
Section 254 (1) (e)
Amends section 254 of the Act to provide for rural
leases that are rental leases. New subsection 254 (1) (e) provides that the
section applies if the amount determined under section 280 of the Act for a
rental rural lease has been paid or for a rural lease, that is not a rental
lease, that any amounts, determined under section 280, allowed to be paid by
instalments has been paid.
Clause 17 Grant of further lease
includes authorised use New section 255 (4)
Amends section 255 of the Act to insert new subsection
255 (4) which provides that a further lease may include provisions that are
different to those in the original lease. This is a ‘to remove any
doubt’ provision. However, the further lease must retain all existing
authorisations of use of the land under the lease as required by section 255
(2). The provision includes an example that suggests that a restriction on the
number of dwellings permitted on the lease may be included in the further lease
where no restriction had been in the original lease. The example provided is not
exhaustive and may extend, but does not limit, the
provision.
Clause 18 Section
280
Amends section 280 of the Act so that the section
reflects the amendments made under clauses 12 and 16 of this Bill and provides
that the amount payable for a further rural lease may be paid in
instalments.
Clause 19 Application for
extension of time to commence or complete building and development Section 298A
(3) to (5)
Substitutes new sections 298A(3) to (5) in the Act.
Planning and Development Amendment Regulation 2008 (No 4) - SL2008-41
modified the requirements in the Act and amended the regulation in relation to
applications for extensions of time to commence or complete development
provisions in a lease to provide for a reduced fee regime; removal of a maximum
extension period; to make provision for hardship; and allowed for delays in
obtaining statutory approvals to be taken into account.
In December 2008 the planning and land
authority published a Guide to fees for extending building and development
provisions, which provided a detailed explanation on the intended
application of section 298A of the Act and Division 5.7.2 of the regulation. In
practice, industry expressed concerns that the regulation did not necessarily
provide for the scaling of fees over time in the manner
intended.
The amendments made by this Bill
(made through amendment regulation SL 2009/35) make it clear that the fee for an
extension of time is scaled over time (lower fee for the first 12 months
extension and a higher fee for second extension, etc) and that this scaling
applies whether an extension of time is sought in one or multiple applications.
The amendments are as
follows:
Sub-section (3)(b) makes it clear that in
defining the required fee that this is to be worked out using the
formula specified for each year, or part year, of the period of extension of
time sought. A clear worked example of how the required fees should be
calculated is also provided.
Sub-section (4)
inserts clarification about how earlier extensions of time which have been
approved are taken into account in working out the required fee, in
particular:
“(4)(a)(i) and (ii) require the period of
extension be taken to include each earlier period of extension granted, other
than extensions for which the required fee was waived under s131 of the
Financial Management Act 1996, or an earlier extension prescribed by
regulation; and
(4)(b)(i) and (ii) require the fee is to be reduced by
the amount of fee paid for each earlier extension and by any amount waived for
an earlier extension under the Financial Management
Act.”
Note: the removal of
extensions granted where the fee is waived under section 131 of the Financial
Management Act 1996 from the calculation of fees for future extensions of
time is a new element to the Act but is consistent with the approach taken to
zero fee extensions of time already set under ss205, 206, and 207 of the
regulation.
Sub-section (5) more clearly
defines the variables used in the formula for calculating the required fee under
(3)(b) – this formula remains unchanged. Sub-section (5) states
that:
“A is the figure, being not more
than 5, as prescribed by regulation (i.e. as listed in column 3 of the Tables
203 and 204 in the regulation) for the relevant year of the period of extension
(definition reworded);
B is the amount of land rates payable
under the Rates Act 2004 in the financial year of the application
(definition unchanged);
D is the lesser
of
(a) 365 [if extension is for a whole year];
and
(b) The number of days for which the extension
is sought in the relevant
year.”
Sub-section (5) also inserts the
definition of period of extension (s298A) in the Act –which
was previously in the regulation.
Clause 20 Extension of time to
commence or complete building and development Section 298B (5) and
(6)
Omits sections 298B(5) and (6). This means that there is
no upper limit on the number of extensions that can be granted provided the
required fee is paid.
Clause 21 New section
312A
Section 291 of the repealed Act provided
for the conversion of Commonwealth leases. This section was applied in
circumstances where under section 27(1) of the Australian Capital Territory
(Planning and Land Management) Act 1988 (Cwlth), (PALM), a declaration
classifying land as National Land had been rescinded, revoked, amended or
varied. Consequently, land that had been National Land ceased to be National
Land.
PALM, section 27, states that the
Minister may declare land to be National Land only where it is, or is intended
to be, used by or on behalf of the Commonwealth. In this section, the Minister
may rescind, revoke, amend or vary land that is National Land. Furthermore,
section 28 of PALM states that at any time when any land in the Territory is not
National Land, that land is Territory Land for the purposes of PALM. In the
event that National Land becomes Territory Land, section 291 of the repealed Act
allowed for a lease that was in force immediately before the declaration to be
taken as having been granted under the repealed Act. In this way, the continuity
of these leases and their continued management under Territory legislation was
assured.
The Act does not have a provision
similar to section 291 of the repealed Act. The new section 312A corrects this
omission.
Clause 22 Expiry – ch 15
Section 431 (2) (a) and (b)
Modifies the Act by inserting new sections 431(2) (a),
(b) and (c) to reflect changes in headings.
Clause 23
Transitional—applications lodged before commencement day Section 442
(1)
Substitutes a new section 442(1). The amendment expands
section 442 to include an application for an amendment of an approval under the
repealed Act. Under new section 442(1), the section applies, if
before the commencement day of the Act:
(1) a person applied for an approval under the repealed
Act, section 226 (Application to undertake development); or
(2) an amendment of an approval under the repealed Act,
section 247 (Minor amendments); and
(3) immediately before commencement day, the authority
had not finally decided the application.
Clause 24 New section 442
(4)
Inserts new section 442(4) which specifies the meaning
of “finally decided” and “reconsideration
period” for the section. An application for approval under
the repealed Act is “finally decided”
if:
(a) the period for making an application under the
repealed Act, section 246 for reconsideration of the authority’s decision
on the application for approval has ended and no application for reconsideration
has been made; or
(b) If an application for reconsideration of the
authority’s decision on the application for approval is made within the
reconsideration period – the authority has made a decision on the
application for reconsideration under the repealed Act, section 246(1)(b); or
the authority is taken to have confirmed the original decision under the
repealed Act, section
246B.
“Reconsideration period”
means the period within which an application must be made under the repealed
Act, section 246(3).
Under sections 442 (2) and
(3), the repealed Act continues to apply in relation to the application despite
its repeal and if the application is approved, the approval is taken to be a
development approval under this Act.
Clause 25 New section
442C
Inserts new section 442C which sets out the transitional
position for development applications for approval of an estate development plan
(EDP) where processes were begun before the commencement of the Act but the
application is lodged after commencement of the Act .The intention is that the
repealed Act and old territory Plan apply to the assessment of all development
applications for EDP’s that were submitted to the authority for comment
prior to the commencement date of the Act.
This section applies to a development
application that relates to an Estate Development Plan (EDP) that is lodged on
or not later than 6 months after commencement day of the Act and the EDP was
given to the authority before commencement day for consideration. The
development application may be made and decided in accordance with the repealed
Act as if that Act had not been repealed.
If
the development application is approved, the approval is taken to be under the
Act and unless extended under the Act, continues in force until the time when it
would have ended under the repealed Act. The development application is taken to
be a merit track proposal for section 198(2) (Deciding applications to amend
development approvals) of the Act.
Under
section 5(4), the repealed Act applies in relation to any application for
reconsideration, or of review, of the decision on a development application to
which this section applies.
Section 5(5) sets
out what the authority must consider in deciding whether a document is an EDP.
The authority must consider whether the document is identified, by itself or
another document, as an EDP; the document appears to be a document to which
government publication Guidelines for Estate Development Plans- Greenfields Land
Subdivision-September 2007 applies; and whether the document includes plans or a
proposal for the subdivision of land and related infrastructure
development.
Section 5 (6) states that an EDP
(the final plan) is taken to have been given to the authority for consideration
if the EDP (the initial plan) was given to the authority and the final plan is
identifiable as a revised version of the initial plan.
Clause 26 Section
444
Section 444
Substitutes a new section 444. New section 444(1)
specifies that the section applies not only when a person has an approval
immediately before the commencement day of the Act but also when the authority
gives an approval under the repealed Act after the commencement of the Act.
Under section 444 (2) the approval:
(a) is taken to be a development approval under the
Act;
(b) unless extended under the Act, continues in force
until the time when it would have ended under the repealed Act;
and
(c) for the Act, section 198 (2) (Deciding applications
to amend development approvals) is taken to relate to a proposal in the merit
track.
Pursuant to new section 444 (3), if the
application to which the approval relates was not required to be publicly
notified under the repealed Act, an application under the Act for the amendment
of the approval need not be notified under the Act.
Section
444A
This clause also inserts new section 444A.
This section applies to development approvals under section 442, 442B, 442C, 443
or 444 of the Act unless the development approval commenced before commencement
day. The development approval in relation to these types of approvals commences,
or is taken to have commenced, when the development approval would have
commenced under the repealed Act, if the repealed Act had not been
repealed.
Section 444A corrects an omission
from the transitional provisions of the Act. The transitional provisions in the
Act indicated when a development approval ends under the transitional
arrangements but did not indicate when the approval commences. New section 444A
makes it clear that the approval commences in accordance with the repealed Act
and not the Act.
Clause 27
Transitional—approvals in force with uncommenced extension Section 445 (2)
(a)
Substitutes a new section 445 (2) (a) in the Act. When
an approval has been given under the repealed Act and an extension of the
approval has been granted but has not commenced on commencement day of the Act,
the approval is taken to be a development approval under the Act and ends at the
end of the period for which the approval was extended under the repealed Act
before commencement day.
Clause 28 Sections 446 and
446A
Substitutes new sections 446 and
446A.
These provisions relate to "lease and
development conditions". The repealed Act and the old Territory Plan permitted
the creation of "lease and development conditions" to apply local specific rules
to the relevant area. Under the repealed Act, lease and development conditions
played a role in informing the market prior to release of land. The conditions
were prepared prior to release of land and contained information to assist the
prospective buyers. The lease and development conditions were able to vary the
Territory Plan through local, specific planning and development conditions,
planning control plans, set backs, block details etc. The authority applied the
lease and development conditions to the assessment of subsequent individual
projects following the release of the land.
The
new provisions set out more clearly the transitional arrangements for these
matters and confirms their application in areas covered by relevant EDPs.
New section 446A permits the application of
lease and development conditions in geographical areas that were the subject of
a relevant EDP. The new section permits both the application of existing lease
and development conditions (that is, conditions made prior to the commencement
date) as well as the application of new lease and development conditions. New
section 446 gives the authority the power to make new lease and development
conditions for application as noted above.
New
section 446A makes it clear that the new Territory Plan can require lease and
development conditions (existing or new) to apply in the assessment of
development applications in geographical areas that were the subject of an EDP
submitted to the authority for comment prior to the commencement date (provided
that the relevant development application for the EDP has been granted). This
ability applies to all such geographical areas irrespective of whether the
development application for the EDP was lodged prior to or after the
commencement date. To be clear, such lease and development conditions do not
apply to the assessment of the EDP but apply to the assessment of subsequent
development applications for individual projects in the geographical area that
was covered by an already approved EDP.
These
arrangements are for transitional purposes only. The intention is for the lease
and development conditions to apply only in respect to land covered by EDPs
submitted prior to the commencement date. For the future, all planning rules
including local specific planning rules are to be incorporated, as necessary,
into the relevant codes of the new Territory
Plan.
New section
446
This section gives the authority the ability to
make new lease and development conditions in certain circumstances. The
authority may make such conditions in relation to the following geographical
areas, that is, land that:
• is covered by an EDP that is the subject
of a development approval given under new section 442C (that is, EDPs submitted
prior to the commencement date but the development application for the EDP was
not lodged until after this date; or
• is covered by an EDP that is the subject
of a development approval given under the provisions of the repealed Act in
relation to an "earlier application" whether the approval was given before or
after the commencement date (that is, EDPs submitted prior to the commencement
date and the development application for the EDP was also lodged prior to this
date).
On or after the commencement day, the
authority may make a lease and development condition in relation to the above
land, or part of the land.
Section 446(3) sets outs definitions for the
section.
“defined land” means land identified in the
old territory plan for the repealed Act, subdivision 2.3.4
"earlier application" means an application for
development approval if the application–
(a) was made under the repealed Act before the
commencement day; and
(b) relates to land that was defined land (which means
land identified in the old territory plan for the repealed Act subdivision
2.3.4); and
(c) is for approval to subdivide whether or not it is
also for approval of something else.
"earlier approval" means a development approval under
the repealed Act of an earlier application.
"lease and development condition" means a lease and
development condition that could have been made under the repealed Act, but for
its repeal.
"old territory plan" means the territory plan under the
repealed Act.
Section 446(4) states that
section 88 of the Legislation Act (Repeal does not end effect of transitional
laws, etc) does not apply.
New section
446A
This section provides for existing lease and development
conditions to be considered when assessing some development applications. The
section applies to a development application if the application
is:
“(i) not in the code track; or
(ii) for development on land to which a lease and
development condition -
a. under section 446 applies; or
b. made under the repealed Act applied immediately
before the commencement day.”
The
authority (or the Minister, if the Minister has exercised the power to "call
in") must consider the lease and development condition in making a decision
under section 162 (Deciding development applications) in relation to the
application if-
(a) the territory plan provides that the lease and
development condition may vary the plan; and
(b) the condition is relevant to assessing the
application and granting the approval.
Clause 29 Section 447
Omits the transitional definition for the extended
meaning of development approval.
Clause 30 Section 458
Substitutes a new section 458. New section 458 provides
for where an applicant (potential lessee) has applied for a grant of a lease
under the repealed Act, section 161 (granting of leases), or section 163 (Leases
to community organisations) or section 164 (Special leases), and the lease is
not granted before commencement day. In this case the lease may be granted
either under the repealed Act or if agreed to by the applicant, the Act.
Importantly this applies irrespective of when the application was
‘decided’.
Previously, the relevant
transitional arrangements were determined by reference to the date of the
decision on the application. This approach is simplified so the transitional
arrangements are determined solely by the date of
application.
This means that a lease applied
for but not granted before 31 March 2008 may be granted under the repealed Act
or the Act. The potential lessee (the person) must agree in writing to a lease
being granted under the Act if that person applied for the grant before 31 March
2008.
Subsection 458 (3) provides that the
lease may be registered under the Land Titles Act 1925, as if the
repealed Act had not been repealed, and is taken to have been granted under this
Act.
New section 458 also removes the
requirement for deciding the application, for the grant of the lease, within 6
months of commencement day.
Clause 31 Section
459
Clause 31 deletes section 459 because the amendments to
section 458 (see Clause 30 of this Bill) no longer makes the distinction of
whether or not an application, for the grant of a lease, has been decided within
6 months or not of commencement day. Section 459 had provided for the grant of a
lease applied for before commencement day but not decided within 6 months of
commencement day.
Clause 32 New section 459A
Inserts a new section 459A. Previously, sections 458
and 459 of the Act set out transitional arrangements for the granting of a
lease. Under these sections, a lease may be granted under the repealed Act where
an application for a lease was made but not decided before the commencement of
the Act on 31 March 2008.
There was some doubt
as to whether these transitional provisions cover the scenario where a contract
for the sale of the lease was entered into before 31 March 2008 but the lease is
not granted until after this date. This is because it is arguable that in this
scenario the decision to grant the lease was made before 31 March, that is, when
the contract for sale was entered into and as such, existing sections 458 and
459 do not apply.
New section 459A removes
this doubt by inserting transitional provisions that authorise the granting of
leases in these cases. Under the new section 459A, the lease may be granted
under the repealed Act (i.e. in the old format with references to the repealed
Act etc) or, if the potential lessee agrees in writing, under the Act. Where a
lease is granted under the repealed Act using this provision, the lease (like
other leases granted under the repealed Act) is taken to have been granted under
the Act and it can still be registered at the Land Titles
Office.
This provision has retrospective
application in that it applies from 31 March 2008. For the amendment to apply to
all relevant leases, it needs to be operational from 31 March
2008.
Section 76 of the Legislation Act
2001 - Non–prejudicial provision may commence retrospectively -
prohibits statutory instruments from including retrospective provisions that are
prejudicial unless specifically authorised by the relevant Act. New section 459A
does not contravene this requirement because it is non –prejudicial. The
effect of new section 459A is to confirm that the:
• authority or land development agency is
able to meet obligations for the grant of leases under contracts for sale
entered into prior to 31 March 2008;
• the potential lessee has the right to elect to
have the lease granted in terms consistent with granting under the repealed Act
or in terms consistent with granting under the Act;
and
• relevant leases acquire the same status
and protections afforded other leases covered by the Act and can be registered
at the Land Titles Office (consistent with the underlying approach in existing
transitional provisions in Part 15.6 of the
Act).
These effects are not prejudicial but
operate to the benefit of the parties concerned.
Clause 33 New section 461A
Inserts new section 461A in the Act. New section 461A
specifies the payment conditions for a lease to a community organisation. In
this, a person may apply for the grant of a lease. If the application was made
under the repealed Act before it was repealed, the authority may grant the lease
under the repealed Act. The repealed Act section 163 allowed for leases to be
granted to community organisations. Clause 33 extends the operation of the
former charging policies under section 163 (2) of the repealed Act. The repealed
Act allowed the authority to grant a lease for less than market value by direct
grant (section 161 (1) (d)), to a community organisation (section 163), as a
special lease (section 164), as a further lease (section 171), as a further
rural lease (section 171A) or as a further lease for purposes other than
residential or rural (section 172). The new section 461A equates to the repealed
Act section 163(2).
Part 3 Planning and
Development Regulation 2008
Clause 34 Legislation
amended—pt 3
Declares that it is the Planning and Development
Regulation 2008 that is being amended.
Clause 35 Section
410
Omits section 410. Section 410 specifies that chapter
15 of the Act is modified by schedule 20 of the regulation. Because the Act
modifications contained in schedule 20 have now been inserted permanently into
the Act section 410 is no longer required.
Clause 36 Schedule
20
Omits Schedule 20.
Schedule 20, the schedule that listed Act modifications, is no longer required
because the modifications have now been inserted permanently into the Act by
this amendment Bill.
Clause 37 Dictionary,
definition of period of extension
The definition of period of extension is omitted
as it has been moved into s298 of the Act.
[Index]
[Search]
[Download]
[Bill]
[[Help]]