Australian Capital Territory Bills Explanatory Statements
[Index]
[Search]
[Download]
[Bill]
[Help]
BUILDING AND CONSTRUCTION INDUSTRY (SECURITY OF PAYMENT) BILL 2009
2009THE
LEGISLATIVE ASSEMBLY FOR THEAUSTRALIAN CAPITAL
TERRITORYBUILDING AND CONSTRUCTION
INDUSTRY (SECURITY OF PAYMENT) BILL 2009EXPLANATORY
STATEMENT
Presented by
Mr John Hargraves
MLA
Minister for Industrial Relations
Building and Construction Industry (Security of Payment) Bill
2009
Overview
Objectives
of the Legislation
The objective of the
legislation is to entitle certain persons who carry out construction work (or
who supply related goods or services) to a timely payment for the work they
carry out and the goods and services they
supply.
This will be achieved through
establishing a procedure for securing progress payments to which a person
becomes entitled under this
Bill.
Reasons for the objectives and
how they will be achieved
Security of
payment has been an issue in the building and construction industry over many
decades. Several taskforces and the 2003 Cole Royal Commission into the
Building and Construction Industry flagged security of payment as a significant
industry matter and cited strong anecdotal evidence across all jurisdictions to
support the notion that security of payment problems are widespread
within the
industry.
The
building and construction industry is particularly vulnerable to security of
payment issues because it typically operates under a hierarchical chain of
contracts with inherent imbalances in bargaining power. The failure of any one
party in the contractual chain to honour its obligations can cause a domino
effect on other parties resulting in restricted cash flow, and in some cases,
insolvency.
The Bill establishes a system
of rapid adjudication for the interim resolution of payment on disputes
involving building and construction work
contracts.
Rapid adjudication will be
conducted by an independent adjudicator with relevant expertise. If the decision
of the adjudicator is in whole, or in part, in favour of the applicant, the
respondent is required to pay a specified amount directed by the adjudicator to
the applicant. Decisions by the adjudicator are enforceable as a judgement
debt.
Rapid adjudication does not
extinguish a party’s ordinary contractual rights to obtain a final
resolution of a payment dispute by a court or tribunal of competent
jurisdiction.
The adjudication process
will cover all forms of construction contracts other than contracts for the
carrying out of domestic building work where an ordinary "resident owner" is a
party to the contract.
Administrative
arrangements
Private providers will conduct the
adjudication on a user pays basis. The ACT Planning and Land Authority and will
act as the Minister’s delegate for authorising and monitoring adjudicators
and authorised nominating authorities (the organisations that appoint
adjudicators).
Consultation
Extensive consultation was undertaken with
industry stakeholders over an 18 month period.
This included a series of meetings with relevant stakeholders and the
release of a discussion paper to key employee and employer groups from the
industry so that all organisation were given the opportunity to comment on the
development of the legislative model.
Building and Construction Industry
(Security of Payment) Bill 2009
Detail on clauses
Clause 1 – Name of Act
This is a technical clause that names the Act. The name of the Act is the
Building and Construction Industry (Security of Payment) Act
2009.
The Act commences on 1 July 2010.
This clause establishes that the dictionary at the end of the Building and
Construction Industry (Security of Payment) Bill 2009 (the Bill) is part
of the Bill.
This clause establishes that notes in the Bill are explanatory and not part
of the Bill.
Clause 5 - Offences against
Act—application of Criminal Code etc
This clause establishes that other legislation applies in relation to
offences against this Bill.
Clause 6 – Objects of Act
This sets out the object of this Bill is to ensure that a person is
entitled to receive, and is able to recover, progress payments if the
person:
(a) undertakes to carry out construction work under certain construction
contracts; or
(b) undertakes to supply related goods and services under certain
construction contracts.
In particular, this Bill:
(a) grants an entitlement to a progress payment for construction work,
whether or not a construction contract provides for progress payments;
and
(b) establishes a recovery procedure for construction work progress
payments.
Part 2 Important
concepts
Division 2.1 Meaning of terms
Clause 7 Meaning of construction work
This clause defines the expression construction work for the
purposes of the Bill. The definition of construction work also includes building
work within the meaning of the Building Act 2004.
Clause 8 Meaning of related goods and services
This clause defines the expression
related goods and services
for the purposes of the
Bill.
Division 2.2 Application of
Act
Clause 9 Application of
Act
This clause provides for the application of the Bill to all construction
contracts, whether written or oral, or partly written and partly oral.
Certain classes of contract are excluded from the Bill, as are certain
classes of contractual provisions.
Other classes of construction contract can be excluded from the Bill by
regulations under the Bill.
Part 3 Rights to progress payments
Clause 10 Rights to progress payments
This clause provides that on and from each reference date, a person who has
undertaken to carry out construction work, or to supply related goods and
services, becomes entitled to a progress payment.
A reference date is a date ascertained in accordance with the
terms of the construction contract as a date for making a claim for a progress
payment or as a date by reference to which the amount of a progress payment is
to be calculated or, if the contract contains no such terms, the last date of
the named month in which the construction work commenced, or the related goods
and services were first supplied, under the contract.
Clause 11 Amount of progress payment
This clause provides for the amount of a progress payment to be ascertained
in accordance with the terms of the construction contract or, if the contract
contains no such terms, according to the value of construction work carried out,
or related goods and services supplied, under the contract.
Clause 12 Valuation of construction work and related goods and
services
This clause provides for the manner in which the value of construction work
carried out, or related goods and services supplied, under a construction
contract is to be valued.
Clause 13 Due date for payment
This clause provides that a progress payment becomes due and payable in
accordance with the terms of the construction contract or, if the contract
contains no such terms, 10 business days after a progress claim is made in
relation to that payment under Part 4 of the Bill.
Clause 14 Effect of pay when paid provision
This clause provides
that a “pay when paid” provision of a contract has no effect in
relation to construction work carried out, or related goods and services
supplied, under a construction contract. A “pay when paid” provision
is a provision that makes one person’s payment dependent on another
person’s payment or dependent on the operation of
another contract.
Part 4 Procedure for recovering progress
payments
Division 4.1 Payment claims and payment schedules
Clause 15 Payment claims
This clause enables a person who is entitled to a progress payment under
proposed section 10 (1) (the claimant) to serve a payment claim on
the person who is liable to make the payment (the respondent). The
claim will set out the amount to which the claimant claims
entitlement.
Clause 16 Payment schedules
This clause enables the respondent to reply to the claim by providing a
payment schedule to the claimant. The schedule will set out how much the
respondent proposes to pay the claimant and when.
Clause 17 Consequences of not paying claimant-no payment
schedule
This clause provides that a claimant will be able to recover the whole
amount of his or her claim as a debt, and to suspend carrying out construction
work, or supplying related goods and services, if the respondent fails to
provide a payment schedule within the time allowed under clause 16
(4).
Clause 18 Consequences of not paying claimant in accordance with payment
schedule
This clause provides that a claimant will be able to recover the amount set
out in the respondent’s payment schedule, and to suspend carrying out
construction work, or supplying related goods and services, where the respondent
provides the payment schedule within the time allowed under clause 16 but fails
to pay that amount by the due date referred to in clause 13.
Division 4.2 Adjudication of disputes
Clause 19 Adjudication applications
This clause enables a claimant to apply to an authorised nominating
authority for adjudication of the amount of a progress payment payable in the
event that the amount set out in the respondent’s payment schedule is less
than the amount set out in the claimant’s payment claim. The application
will have to be made within 5 days after the claimant receives the payment
schedule, and will be able to be made to an authority authorised to nominate
adjudicators for the purposes of the Bill.
Clause 20 Eligibility-adjudicators
This clause requires an adjudicator to be an individual and to have such
qualifications, expertise and experience to perform adjudications and has
successfully completed a relevant training course. It also prohibits a person
from being an adjudicator in relation to a particular construction contract if
the person is a party to the contract, or the person is employed or represents a
building and construction industry organisation or in such circumstances as are
prescribed by the regulations.
Clause 21 Adjudicator for application
This clause provides that the appointment of an adjudicator is effected
when the adjudicator gives notice of his or her acceptance of the adjudication
application to the claimant and the respondent. The adjudicator must also at
the same time, with the notice of acceptance, give the respondent a copy of the
adjudication application.
Clause 22 Adjudication responses
This clause enables the respondent to lodge, in writing, with an
adjudicator the respondent’s response to the claimant’s adjudication
application.
Clause 23 Adjudication procedures
This clause sets out the manner in which, and the time within which, an
adjudicator is to determine an adjudication application.
Clause 24 Adjudicator’s decision
This clause provides that the adjudicator is to determine an adjudication
application by determining the amount of the progress payment to be paid and the
date on or before which it must be paid and the rate of interest on the
amount.
Clause 25 Respondent must pay adjudicated amount
This clause provides that if the adjudicator determines an amount that the
respondent must pay as a progress payment, the respondent must pay that amount
to the claimant on or before the relevant date.
Clause 26 Failure to pay adjudicated amount
This clause provides that if a respondent fails to
pay the whole or any part of an adjudicated amount, the claimant may request an
adjudication certificate from the authorised nominating authority and may serve
a notice on the respondent of the claimant’s intention to suspend carrying
out construction work or supplying related goods and services. The clause also
specifies the content requirements for an adjudication certificate and matters
that may be included in the certificate at the request of the
claimant.
Clause 27 Filing of adjudication certificate as judgement
debt
This clause enables an adjudication certificate to
be filed as a judgment debt that may be enforced in any court of competent
jurisdiction. If the respondent commences proceedings to have the judgment debt
set aside, the respondent is not entitled to bring any counter-claim against the
claimant, raise any defence or challenge the adjudicator’s determination
and is required to pay to the court as security the unpaid portion of the
adjudicated amount.
Clause 28 Claimant may make new application in certain
circumstances
This clause enables a claimant to make a new
adjudication application in the event that a previous application is not
accepted by an adjudicator within 4 business days after it is made or if an
adjudicator fails to determine the application within the time
allowed.
Division 4.3 Claimant’s right to suspend
construction work
Clause 29 Claimant may suspend
work
This clause entitles a claimant to suspend the carrying out of construction
work (or the supply of related goods and services) if at least 2 business days
have passed since notice of intention to do so has been given as referred to in
clause 17, 18 or 26. A claimant who suspends the carrying out of construction
work (or the supply of related goods and services) under the proposed section
will be immune from civil liability as during the period of
suspension.
Division 4.4 Authorised nominating authorities
and adjudicators
Clause 30 Maximum number of nominating
authorities
This clause allows the
Minister to decide the maximum number of people that
may
be authorised as a nominating
authority.
Clause 31 Application for nominating
authority
This clause enables the relevant Minister to authorise, or refuse to
authorise, persons as nominating authorities (to nominate adjudicators for the
purposes of the proposed Act) and to withdraw any authority so given. The
Minister’s decision to refuse an application is a reviewable
decision.
Clause 32 Nominating
authority-suitability
This clause
provides the factors the relevant Minister must consider in deciding whether an
applicant is a suitable nominating authority under clause 31.
Clause 33 Term of
authorisation
This clause provides that
an authorisation under this division is effective for 3 years starting on the
day the Minister gives the authorisation and that an authorised nominating
authority may apply for renewal of the authorisation.
Clause 34 Costs and expenses-authorised
nominating authority
This clause provides for the costs and
expenses payable to an authorised nominating authority in relation to the
adjudication of an adjudication application.
Clause 35 Report-authorised nominating
authority
This clause provides that an
authorised nominating authority must provide a report to the relevant Minister,
on request, about its activities under the Act, or costs and expenses charged by
the authority for any service provided by the authority in relation to an
adjudication application made to the authority.
Clause 36 Costs and
expenses-adjudicator
This clause provides for the costs and
expenses payable to an adjudicator in relation to his or her adjudication of an
adjudication application. In particular, an adjudicator will not be entitled to
be paid any fees if he or she fails to determine such an application within the
time allowed under clause 21 (3).
Clause 37 Protection from
liability-adjudicators and authorised nominating authorities
This
clause ensures that no action will lie against an adjudicator or any other
person for anything done or omitted to be done by the adjudicator honestly and
without recklessness in the exercise of the adjudicator’s functions under
the Bill.
Division 4.5 General
Clause 38 Effect of part on civil
proceedings
This clause ensures that nothing done under this part
will affect any civil proceedings arising under a construction contract, except
that a court will be required to make appropriate set-offs and any orders
necessary to provide for the restitution of money paid as a consequence of its
decision in the proceedings.
Part 5 Notification and review of
decisions
Clause 39 Meaning of reviewable decision-pt 5
This clause provides the meaning of reviewable decision for
the purposes of this part.
Clause 40 Reviewable decision notice
This clause requires that if
a person makes a reviewable decision, the person must give a reviewable decision
notice to each entity mentioned in schedule 1,
column 4 in relation to the
decision, and under s 67A of the ACT Civil and Administrative Tribunal Act
2008, the person must also take reasonable steps to give a reviewable
decision notice to any other person whose interests are affected by the
decision.
Clause 41 Applications for review
This
clause provides that an entity mentioned in schedule 1, column 4 in relation to
the reviewable decision, or any other person whose interests are affected by the
decision, may apply to the ACT Civil and Administrative
Tribunal for review of a reviewable
decision.
Part 6 Miscellaneous
Clause 42 No contracting out
This clause avoids any provision of an agreement that purports to exclude,
modify or restrict the operation of the Bill.
Clause 43 Judicial review of adjudication decision
This clause provides for appeals on questions of law by parties to an
adjudication decision to the Supreme Court. The provision is modelled closely
on the appeal provision under section 38, part 5 of the Commercial
Arbitration Act 1986, save for one respect, in that the period in which an
adjudicator must make a new decision has been reduced to 10 business days after
the decision has been remitted. This reduction is consistent with the subject
matter of the Bill.
Clause 44 Determination of question of law by Supreme
Court
This clause provides that the Supreme Court has jurisdiction to determine
any question of law arising in an application to the court made by any of the
parties to adjudication. The provision is modelled closely on the appeal
provisions under section 39, part 5 of the Commercial Arbitration Act
1986.
Clause 45 Review of Act
This provision
requires the Minister to review the operation of the Act as soon
as
possible after 1 July 2015 and report on
the outcome of the review to the Legislative Assembly by 1 July
2016.
Clause 46 Determination of fees
This
clause provides that the Minister may, in writing, determine fees for this
Bill.
Clause 47 Approved forms
This clause
provides that the chief executive may, in writing, approve forms for this Act
and if approved, the forms must be used.
Clause 48 Regulation-making power
This
clause allows the Executive to make regulations for the purposes of this
Bill.
Part 7 Repeals and consequential
amendments
Clause 49 Legislation repealed
This clause repeals the
Contractors Debts Act
1897.
Clause 50 Legislation amended-sch 2
This clause provides that this Bill amends the
legislation mentioned in schedule 2.
Schedule 1 Reviewable decisions
This schedule lists the decisions and the respective provisions under the
Bill that are able to be reviewed.
Schedule 2 Consequential amendments
Part 2.1 Legislation Act 2001
This part provides the amendments to other Acts as a consequence of this
Bill.
Dictionary
The Dictionary defines terms used in the Bill.
[Index]
[Search]
[Download]
[Bill]
[[Help]]