![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of Queensland - Court of Decisions |
Last Updated: 2 January 2008
SUPREME COURT OF QUEENSLAND
|
CITATION:
|
Cant Contracting P/L v Casella & Anor [2006] QCA 538
|
|
PARTIES:
|
CANT CONTRACTING PTY LTD
ACN 079 036 025 (plaintiff/respondent) v CON CASELLA (defendant/appellant) MICHELLE LYNDSAY CASELLA (defendant/appellant) |
|
FILE NO/S:
|
Appeal No 8063 of 2006
SC No 5925 of 2005 |
|
DIVISION:
|
Court of Appeal
|
|
PROCEEDING:
|
General Civil Appeal
|
|
ORIGINATING COURT:
|
Supreme Court at Brisbane
|
|
DELIVERED ON:
|
15 December 2006
|
|
DELIVERED AT:
|
Brisbane
|
|
HEARING DATE:
|
23 October 2006
|
|
JUDGES:
|
Williams and Jerrard JJA and Philip McMurdo J
Separate reasons for judgment of each member of the Court, each concurring as to the order made |
|
ORDER:
|
1. Appeal allowed |
|
BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION –
RECOVERY ON QUANTUM MERUIT – IN GENERAL – where
the respondent
agreed to construct poultry sheds for the appellants – substantial work
had been carried out before the Laidley
Shire Council issued a stop work order
– pursuant to the Building and Construction Industry Payment Act
2004 (Qld) the respondent sought progress payments by way of a payment claim
– the appellants did not serve a corresponding payment
schedule on the
respondent – summary judgment was awarded against the appellants –
where the appellants had filed a defence
and counter-claim against summary
judgment arguing that the respondent did not hold an appropriate licence at the
time construction
was carried out – whether the respondent was entitled to
summary judgment, regardless of the fact that he may not have held
an
appropriate construction licence in contravention of s 42(1) Queensland
Building Services Authority Act 1991 (Qld)
Building & Construction Industry Payment Act 2004 (Qld), s 3, s
7, s 8, s 13, s 17, s 18, s 19, s 26
Home Building Act 1989 (NSW), s 10, s 94 Queensland Building Services Authority Act 1991 (Qld), s 42 Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421,
distinguished
Lucas Stuart Pty Ltd v Council of the City of Sydney [2005] NSWSC 840; File No 50077 of 2005, 23 August 2005, distinguished |
|
|
COUNSEL:
|
J A Griffin QC, with T F Mylne, for the appellants
P L O’Shea SC, with M J F Burnett, for the respondent |
|
SOLICITORS:
|
Graham & Associates for the appellants
Holding Redlich for the respondent |
[1] WILLIAMS JA: On 1 September 2006 the respondent (the plaintiff in the
action) obtained summary judgment against the appellants
(the defendants in the
action) in the sum of $493,339.45 with interest and costs. The appellants have
appealed against that decision.
To appreciate the submissions on the hearing of
the appeal it is necessary to set out the history of dealings between the
parties.
[2] By contract made 1 November 2004 the respondent agreed to
construct five poultry sheds for the appellants at a cost of $211,143
per shed.
Substantial work was carried out by the respondent until the Laidley Shire
Council issued a stop work order on 14 February
2005. By then the appellants
had made payments totalling $522,578.95 pursuant to the agreement.
[3] The
respondent then commenced proceedings in the Supreme Court on 21 July 2005
seeking to recover what it asserted was the balance
due and owing. By the
original statement of claim filed 21 July 2005 the respondent claimed the sum of
$348,385.95 as being due
and payable pursuant to the agreement. In the
alternative, a claim was made on the basis of the reasonable cost of labour and
material
supplied; it was asserted that a total of $841,825.76 was payable on
that basis and in consequence a claim was made for $318,556.47
as being due and
owing.
[4] The appellants filed a defence and counter-claim on 29 August
2005. In paragraph [8] of that pleading it was alleged that the
respondent was
in breach of s 42(1) of the Queensland Building Services Authority Act 1991
(Qld) ("the Building Act") which provided that a person must not carry out
building work unless the appropriate licence was held. The assertion was made
that the respondent did not hold the appropriate licence and therefore
contravened s 42(1). It was then asserted that the respondent's only remedy was
pursuant to s 42(3) and s 42(4) of the Building Act. Again in the counter-claim
(paragraph [11]) it was asserted that the respondent did not hold the requisite
building licence to
perform the work the subject of the agreement.
[5] In a
reply filed 13 October 2005 the respondent effectively put in issue whether it
held the appropriate licence at the material
time.
[6] Pursuant to r 378 of
the UCPR the respondent amended its statement of claim on 5 July 2006.
Those amendments introduced
a claim pursuant to the Building and Construction
Industry Payments Act 2004 (Qld) ("the Payment Act"). It was alleged that the
Payment Act applied to the contract and that in terms of that Act the appellants
were responsible for payment. It was then alleged that between
1 November 2004
and 4 April 2005 the respondent carried out work pursuant to the contract. It
was then asserted that work to the
value of $493,339.45 had been carried out and
payment had not been received. It was asserted that pursuant to s 13 of the
Payment Act the respondent was entitled to progress payments in that sum. Then
it was alleged that on 31 March 2006 the respondent served a
payment claim
pursuant to s 17 of the Payment Act for the sum in question and that no payment
schedule was served on the respondent by the appellants within the time limit
prescribed
by s 18(4) of that Act. Reference in the pleading was then made to
other provisions found in s 18 and s 19 of the Payment Act, and the respondent
claimed the sum of $493,339.45 as a debt due and owing pursuant to s 19(2)(a)(i)
of the Payment Act.
[7] In paragraphs [8A], [8B] and [8C] of the amended
defence and counterclaim of 19 July 2006, the appellants pleaded defences
to the claim under the Payment Act. In essence it was asserted that nothing in
the Payment Act derogated from the obligation of the respondent as a builder to
comply with s 42 of the Building Act. It was then alleged that the respondent
was not entitled to any benefits under the Payment Act, but was limited to a
remedy pursuant to s 42(3) and s 42(4) of the Building Act.
[8] With the
pleadings in that state the respondent applied for summary judgment by
application filed 3 August 2006; the matter was
heard on 24 August 2006 and
judgment given for the respondent on 1 September 2006.
[9] Before considering
the reasons for judgment of the Chief Justice it is necessary to refer to the
relevant provisions of the statutes
in question. The Building Act defines
"building work" as including the "erection or construction of a building"; it
was disputed that the construction of the poultry
sheds in question constituted
building work. Section 42(1) of that Act then provides:
"A person must not carry out, or undertake to carry out, building work unless that person holds a contractor's licence of the appropriate class under this Act."
Contravention of the section constitutes an offence; subsection (9). Relevantly then for present purposes subsection (3) thereof provides:
"Subject to subsection (4), a person who carries out building work in contravention of this section is not entitled to any monetary or other consideration for doing so."
[10] Subsection (4) then provides some amelioration for the builder who carries
out work in contravention of the section. Such a
person may claim "reasonable
remuneration for carrying out building work" but only as calculated in
accordance with the provisions
of that subsection. The builder is not entitled
to recover anything for his own labour or any profit; the claim is limited to
the
actual cost of supplying other labour and materials.
[11] Leaving aside
for the moment the provisions of the Payment Act, if it was held that the
respondent did not hold the requisite licence for carrying out the building work
in question, then it would
not be entitled to recover the amounts claimed in the
statement of claim as originally drawn. It would not be entitled to recover
monies due under the contract or on the common law quantum meruit basis alleged
in that statement of claim. It would be restricted
to a claim quantified in
accordance with
s 42(4) of the Building Act.
[12] The long title of the
Payment Act states that it is an "Act to imply terms in construction contracts,
to provide for adjudication of payment disputes under construction
contracts,
and for other purposes." Section 3 relevantly provides that the Act applies to
"construction contracts"; that expression
is then defined in s 10(2) to include
"building work" as defined in the Building Act.
[13] Sections 7 and 8 then
deal with the objects of the Act. Section 7 provides that the "object of this
Act is to ensure that a person is entitled to
receive, and is able to recover,
progress payments if the person - (a) undertakes to carry out construction work
under a construction
contract". That is provided for pursuant to s 8 by
"granting an entitlement to progress payments whether or not the relevant
contract
makes provision for progress payments". The expression "reference
date" is defined to mean either the date stated in a contract
as the date on
which a progress payment may be made or in the absence of such a provision the
last day of the month in which the
construction work was first carried out and
the last day of each succeeding month. Relevantly s 12 then provides:
"From each reference date under a construction contract, a person is entitled to a progress payment if the person has undertaken to carry out construction work . . . under the contract".
It would appear from the definition of "progress payment" in Schedule 2 and
section 13, that the claim under the Act could be for
the whole of the contact
price.
[14] That then leads to sections 17, 18 and 19 which are central to
the resolution of the issues raised in this case; relevantly they
provide:
"17(1) A person mentioned in section 12 who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment (the respondent).
(2) A payment claim -
(a) must identify the construction work . . . to which the progress payment
relates; and
(b) must state the amount of the progress payment that the
claimant claims to be payable (the claimed amount); and
(c) must state that
it is made under this Act.
. . .
18(1) A respondent served with a payment
claim may reply to the claim by serving a payment schedule on the claimant.
(2) A payment schedule -
(a) must identify the payment claim to which it
relates; and
(b) must state the amount of the payment, if any, that the
respondent proposes to make (the scheduled amount).
(3) If the scheduled
amount is less than the amount claimed, the schedule must state why the
scheduled amount is less and, if it is
less because the respondent is
withholding payment for any reason, the respondent's reasons for withholding
payment.
(4) Subsection (5) applies if -
(a) a claimant serves a payment
claim on a respondent; and
(b) the respondent does not serve a payment
schedule on the claimant within . . . 10 business days after the payment claim
is served.
(5) The respondent becomes liable to pay the claimed amount to
the claimant on the due date for the progress payment to which the
payment claim
relates.
19(1) This section applies if the respondent -
(a) becomes liable
to pay the claimed amount to the claimant under section 18 because the
respondent failed to serve a payment schedule
on the claimant within the time
allowed by the section; and
(b) fails to pay the whole or any part of the
claimed amount on or before the due date for the progress payment to which the
payment
claim relates.
(2) The claimant -
(a) may -
(i) recover the unpaid portion of the claimed amount from the respondent, as a debt owing to the claimant, in any court of competent jurisdiction;
. . .
(4) If the claimant starts proceedings under subsection 2(a)(i) to
recover the unpaid portion of the claimed amount from the respondent
as a debt
-
(a) judgment in favour of the claimant is not to be given by a court unless
the court is satisfied of the existence of the circumstances
referred to in
subsection (1); and
(b) the respondent is not, in those proceedings,
entitled -
(i) to bring any counterclaim against the claimant; or
(ii) to
raise any defence in relation to matters arising under the construction
contract."
[15] It was not disputed in the present case that the appellants did not serve a
payment schedule on the respondent in accordance
with the provisions of the
Payment Act. In support of the application for summary judgment the respondent
relied on
s 19(4)(b) of that Act.
[16] On the hearing of the application
for summary judgment there was no dispute about the procedural regularity of
what the respondent
did relying on the Payment Act. The Chief Justice noted in
his reasons that the contract between the parties entitled the respondent to
"progress payments"; prima
facie that brought the Payment Act into play.
[17] The Chief Justice then said that on the basis of the pleadings as
originally drafted the respondent had to "confront the circumstance
that . . .
[it] did not, when it carried out the relevant work, hold a requisite
contractor's licence". He noted that if that was
eventually established the
respondent "would be limited, in its recovery by s 42(4)" of the Building Act.
But he then recorded the submission of counsel for the respondent that "that
would be irrelevant to the claim added by amendment,
founded on s 19" of the
Payment Act.
[18] The issue raised by the appellants at first instance was
that the Payment Act "should be read as subject to the qualified right of
recovery limited by s 42" of the Building Act. Counsel for the respondent met
that by saying that in order to rely on the absence of the requisite licence the
issue had to be
raised in a "payment schedule". Thus the Chief Justice was able
to identify the issue before him as follows:
"The issue is whether, the defendants having failed to deliver a payment schedule the defendants can resist the plaintiff's apparent right to judgment under s 19(2)(a) by subsequently raising the licensing issue; in other words, whether the ultimate operation of the mechanism established by the [Payment Act] is to be read as subject to a supervening qualification arising from s 42 of the [Building Act]."
[19] The Chief Justice referred to the absence of any express qualification
giving effect to the condition of the appellants in s
19 and to the decisions of
Einstein J in Lucas Stuart Pty Ltd v Council of the City of Sydney [2005] NSWSC
840 and the New South Wales Court of Appeal in Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004)
61 NSWLR 421. The Payment Act appears to be based on the Building and
Construction Industry Security of Payment Act 1999 (NSW) ("the NSW Act"). After
referring to those matters the Chief Justice said he accepted the submissions of
counsel for the respondent and granted
summary judgment.
[20] The principal
submission on behalf of the appellants in this Court is that the Payment Act
does not overrule s 42 of the Building Act, and that when the Payment Act refers
to a "construction contract" it must be referring to a lawful contract.
Further, the use of the word "entitled" in sections 7, 12 and 17 must mean
lawfully entitled.
[21] Counsel for the respondent in a very careful argument
contended that the Payment Act was designed to ensure that a contractor received
progress payments on an interim basis, with the parties having the right at a
later
point of time to litigate all issues arising under the construction
contract (cf s 100 of the Payment Act and Roadtek, Department of Main Roads v
Davenport and Anor [2006] QSC 47). On that approach the failure to raise the
illegality in a "payment schedule" precluded the appellants from relying on that
illegality
on the summary judgment application (s 19(4)(b)(ii) of the
Payment Act).
[22] Because the judgment at first instance and the
submissions on appeal on behalf of the respondent relied heavily on the
reasoning
in the New South Wales decisions referred to, it is necessary to
consider the relevant New South Wales legislation and the reasoning
in those
cases.
[23] Section 15 of the NSW Act is in the same terms as s 19 of the
Payment Act. Einstein J in Lucas Stuart was concerned with a claim for summary
judgment in circumstances where the principal failed to serve
a payment
schedule. On the hearing of the summary judgment application the principal
sought to rely on a defence of equitable estoppel
and defences under the Trade
Practices Act. Summary judgment was granted. The reasoning emphasised that the
legislation provided
for a determination on "an interim basis" which was
"subject [to] a final hearing in the fullness of time". There was no basis for
"moving outside of this scheme" and in consequence it was held that the
principal was not entitled, given the terms of the section,
to rely on the
matters sought to be raised by way of defence. Significantly for present
purposes, there was no question in that
case of the contract founding the claim
for progress payments being illegal or unenforceable.
[24] The Court of
Appeal in Brodyn had to consider a somewhat similar question to that which
arises in the instant case, but it arose
in different circumstances. The
contractor delivered a payment claim and the principal responded with a payment
schedule. The matter
then went to adjudication, and there was a finding in
favour of the contractor. The contractor then filed that decision in the court
and it became enforceable as a judgment debt (the NSW equivalent of s 31 of the
Payment Act). The principal then applied to the Supreme Court for relief in the
nature of certiorari. That relief was refused at first instance
and an appeal
was lodged. Between the lodging of the notice of appeal and it coming on for
hearing the principal became aware for
the first time that the contractor did
not have at relevant times a licence under the Home Building Act 1989 (NSW). So
far as is relevant s 10 of that Act provided:
"(1) A person who contracts to do any residential building work, or any specialist work, and who so contracts:
(a) in contravention of section 4 (Unlicensed contracting), or
. . .
is
not entitled to damages or to enforce any other remedy in respect of a breach of
the contract committed by any other party to the
contract, and the contract is
unenforceable by the person who contracted to do the work. However, the person
is liable for damages
and subject to any other remedy in respect of a breach of
the contract committed by the person."
[25] It is also necessary to have regard to s 94 of that Act; relevantly it provided:
"If a contract of insurance required by section 92 is not in force, in the name of the person who contracted to do the work, in relation to any residential building work done under a contract (the uninsured work), the contractor who did the work:
(a) is not entitled to damages, or to enforce any other remedy in respect of a
breach of the contract committed by any other party
to the contract, in relation
to that work, and
(b) is not entitled to recover money in respect of that
work under any other right of action (including a quantum meruit)."
[26] Against that background Hodgson JA, with the concurrence of Mason P and Giles JA, concluded at 449:
"It
was submitted for Brodyn that, because Dasein did not have a licence
under the Home Building Act, the subcontract was illegal
(s 4) and
unenforceable (s 10). Accordingly, Dasein was not entitled to any progress
payment.
In my opinion, the civil consequences for an unlicensed contractor for its breach of s 4 are those set out in s 10, and not any wider deprivation of remedies. In my opinion this is confirmed by the different provisions of s 94, which explicitly precludes, in the event of breach of the insurance provisions, the obtaining of a quantum meruit unless a court considers it just and equitable. In my opinion, the remedy given by the Act is not of the nature of damages or any other remedy in respect of breach of contract nor is it enforcement of the contract: it is a statutory remedy, albeit one that in part makes reference to the terms of a contract, and thus it is not affected by s 10 of the Home Building Act.
Accordingly, in my opinion Dasein's failure to have a licence could not be a ground on which the adjudicator's determination could be considered void, or for otherwise giving relief in respect of the determination."
[27] It will be immediately obvious that s 94 of the Home Building Act is
substantially similar to s 42(3) and (4) of the Building Act; that distinguishes
the present case from Brodyn. Clearly the New South Wales Court of Appeal would
have reached a different conclusion
in Brodyn if s 94 and not s 10
applied.
[28] Further, s 10 of the Home Building Act only disentitles the
unlicensed contractor to damages or other remedy in respect of a breach of
contract committed by the principal,
where s 42(3) of the Building Act
disentitles an unlicensed contractor to any monetary consideration for work done
pursuant to the contract. Hodgson JA may well have
been right in concluding
that, under the legislation in question in Brodyn, a claim for a progress
payment was not "enforcement of
the contract"; but it is not necessary to
consider that aspect further because of the different statutory provision in
question here.
The words "any monetary or other consideration" are of very wide
import and must be given full effect.
[29] It follows that the conclusion in
Brodyn is of no assistance when considering the present appeal. Insofar as the
Chief Justice
relied on Brodyn in support of his conclusion he was, in my
respectful opinion, wrong. On careful consideration the reasoning of
Hodgson
JA, if anything, supports the submission of the appellant in this
case.
[30] Because s 42(3) of the Building Act provides that an unlicensed
contractor "is not entitled to any monetary or other consideration" for doing
work pursuant to the contract,
such a contractor cannot be said to have an
entitlement to progress payments pursuant to ss 7, 12 and 17 of the Payment
Act.
[31] Counsel for the respondent relied heavily on the reference in s 17
of the Payment Act to a person "who is or claims to be entitled to a progress
payment"; he submitted that in consequence a person could come within
the
section even though at the end of the day it was shown that his claim was
unjustified. The inclusion of the expression "claims
to be entitled" is
intended, in my view, to meet the situation where a claim is made under the
Payment Act in the face of an ongoing dispute between the parties as to such
entitlement. But that does not meet the present situation where,
given the
provisions of the Building Act, the respondent has no legal entitlement to any
monetary consideration for work done pursuant to the contract.
[32] Counsel
for the respondent sought to obtain comfort from the reference in s 26(2) of the
Payment Act to the Building Act. Section 26(2) is concerned with the matters an
adjudicator must consider in arriving at his decision. Subparagraph (a) not
surprisingly obliges
the adjudicator to have regard to "the provisions of this
Act" and then it goes on to say regard must also be had to the provisions
of the
Building Act Pt 4A to the extent they are relevant. Relevantly Pt 4A of the
Building Act deals with issues such as set-off under building contracts,
retention amounts, and late progress payments. The reference in s 26 of the
Payment Act to Pt 4A of the Building Act is not surprising because the latter is
concerned with the calculation of the amount owing under a building
contract.
[33] Counsel for the respondent contended that because there was
such a specific reference to Pt 4A, and no specific reference to s 42, the
legislature must have intended that s 42 of the Building Act was not a relevant
consideration when considering a claim under the Payment Act. Such a submission
must be rejected. Parliament could not have intended that pursuant to the
Payment Act an unlicensed contractor could immediately recover the whole of the
contract price for doing the work, in the face of the statutory
prohibition in
the Building Act on such a contractor recovering any monetary consideration,
other than as specified in s 42(4) for doing work under the contract. It is not
a sufficient answer to say that the principal might subsequently obtain a
judgment
entitling it to "claw back" that whole of the contract
price.
[34] As already noted the respondent commenced proceedings in the
Supreme Court not relying on the provisions of the Payment Act. In those
proceedings the question whether or not the money claimed was recoverable in the
face of s 42 of the Building Act was squarely raised. The Supreme Court was
initially seized of the issue as to the legality of the contract and, if the
respondent's
contentions on the appeal are successful, it would effectively mean
that the Court's jurisdiction to determine that issue was ousted.
There are
sound reasons, it seems to me, for concluding that if the parties have joined
issue in Supreme Court proceedings on a
particular question, the jurisdiction of
the Court to adjudicate upon that issue cannot be ousted by subsequent reliance
on provisions
of the Payment Act. But it is not necessary for the determination
of this appeal to express a concluded opinion on that point.
[35] It is
sufficient for present purposes to say that at the time the application for
summary judgment was made there was clearly
a triable issue as to the
respondent's entitlement to recover anything under the contract and s
19(4)(b)(ii) did not in the circumstances then existing preclude the appellant
from relying on s 42 of the Building Act. It follows that summary judgment
ought not to have been granted. The appeal should be allowed, the judgment of 1
September 2006
should be set aside, the application for summary judgment should
be dismissed with costs, and the respondent should pay the appellant's
costs of
the appeal. That would enable the matter to proceed to trial where factual
issues relating to the licensing of the respondent
would be
determined.
[36] JERRARD JA: In this appeal I have read the judgments of
Williams JA and McMurdo J, and agree with their Honours’ reasons
and the
orders proposed by Williams JA. I add the following reasons of my own, which
adopt the relevant facts described by Williams
JA.
[37] The Queensland
Building Services Authority Act 1991 (Qld) (“the 1991 Act”) provides
in s 42 that a person must not carry out or undertake to carry out building work
unless
that person holds a contractor’s licence of the appropriate class
under the 1991 Act. In s 42(3) it provides that “subject
to subsection
(4), a person who carries out building work in contravention of this section is
not entitled to any monetary or other
consideration for doing so.”
Section 42(4) allows such a person to claim as reasonable remuneration the
amount paid by that
person in supplying materials and labour, but not any amount
for the person’s own labour, for profit, or for costs incurred
in
supplying materials and labour if not reasonably incurred. Section 42(9)
provides that a person who contravenes s 42 commits
an offence.
[38] The
Building and Construction Industry Payments Act 2004 (Qld) (“the 2004
Act”) provides a regime for prompt payment of sums claimed as owing under
construction contracts. Those
are defined in schedule 2 of the 2004 Act to mean
a contract, agreement or other arrangement under which one party undertakes to
carry out construction work for, or to supply related goods and services to,
another party. Section 10(2) declares that construction
work includes building
work within the meaning of the 1991 Act.
[39] Section 12 of the 2004 Act
provides that:
“From each reference date under a construction contract, a person is entitled to a progress payment if the person has undertaken to carry out construction work, or supply related goods and services, under the contract.”
A progress payment is defined in schedule 2 to mean a payment to which a person is entitled under s 12, and includes, without affecting any entitlement under the section:
“(a) the final payment for construction work carried out, or for related goods and services supplied, under a construction contract; or
(b) a single or one-off payment for carrying out construction work, or for supplying related goods and services, under a construction contract; or
(c) a payment that is based on an event or date, known in the building and construction industry as a ‘milestone payment’.”
[40] Schedule 2 defines a reference date under a construction contract to mean:
(a) a date stated in, or worked out under, the contract as the date on which a claim for a progress payment may be made for construction work carried out or undertaken to be carried out, or related goods and services supplied or undertaken to be supplied, under the contract; or
(b) if the contract does not provide for the matter –
(i) the last day of the named month in which the construction work was first carried out, or the related goods and services were first supplied, under the contract; and
(ii) the last day of each later named month.
[41] Section 13 provides for the amount of the progress payment. It reads:
“The amount of a progress payment to which a person is entitled in relation to a construction contract is –
(a) the amount calculated under the contract; or
(b) if the contract does
not provide for the matter, the amount calculated on the basis of the value of
construction work carried
out or undertaken to be carried out, or related goods
and services supplied or undertaken to be supplied, by the person, under the
contract.”
[42] It seems obvious that the 2004 Act has attempted to catch all varieties of
construction contracts, in the expansive definitions
of progress payment,
reference date, and in the provisions as to the amount of progress payment.
Progress payments include final
payments, single or one off payments, milestone
payments; reference dates, if not provided for, are the last day of each month;
the
amount of the progress payment, if not provided for, is the value of the
work carried out. The 2004 Act applies to situations where
a contract makes no
provision for progress payments at all. But there is no sign of an intent to
outflank or override the requirements
in the 1991 Act, that builders be
appropriately licensed.
[43] In this matter the appellant defendants pleaded
in their original defence that the respondent plaintiff did not hold the classes
of licence required to perform the building work the subject of the building
agreement between the plaintiff and the defendants,
and that accordingly the
plaintiff’s only remedy was pursuant to s 42(3) and (4) of the 1991 Act.
Subsequent to that pleading
the plaintiff responded by amending to add a claim
under the 2004 Act. The plaintiff’s amended claim under the 2004 Act was
for construction work it had carried out, to a claimed value of $493,339.45. In
paragraph 21 of its amended claim, it pleaded an
entitlement, pursuant to s 13
(of the 2004 Act), to progress payments in that sum under the contract.
[44] Its counsel on this appeal submitted that, although it was pleaded and
not denied that the respondent plaintiff was an unlicensed
builder prohibited
from carrying out or undertaking to carry out that building work, and although
it committed an offence under the
1991 Act by undertaking to carry out that
construction work, and although it was not entitled to any monetary or other
consideration
for any building work that it carried out in contravention of s
42, and although by reason of that Act it could recover only the
cost of labour
and material supplied, it was nevertheless “entitled” to a progress
payment in terms of s 12 of the 2004
Act for the work it had carried out or
undertaken to carry out. Respectfully, I disagree. The respondent was not
entitled under
ss 12 or 13 of the 2004 Act to a progress payment for any
building work it had carried out, because s 42(3) of the 1991 Act says
so. The
progress payment it claimed was a monetary consideration for the building work
carried out. The amended defence pleaded
in paragraph 8A(b) that the plaintiff
was not entitled to any benefits under the 2004 Act.
[45] The respondent
accepted on the appeal that it was not a person “entitled” to a
progress payment within the meaning
of s 17(1) of the 2004 Act, although arguing
it was “entitled” under s 12. Section 17(1) reads:
“A person mentioned in section 12 who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment (the respondent).”
However, the respondent contended it was a person who “claims to be
entitled” to a progress payment, albeit not a person
who was entitled. Mr
O’Shea submitted for the respondent that “entitled” in s 17
meant entitled both in a “section
12” sense, and in all senses; thus
excluding contractors who did not hold the appropriate contractor’s
licence. Mr O’Shea
argued however that contractors without licence could
“claim to be entitled”, and that respondents to s 17 payment claims
from unlicensed contractors could raise the lack of the appropriate licence in
the payment schedule served in response under s 18
of the 2004 Act. He argued
that any adjudicator to whom the matter was then referred would be obliged to
consider the absence of
a licence, by reason of s 26(2)(d) of the 2004 Act,
because the point would be raised in the payment schedule.
[46] Mr
O’Shea submitted that the decision in Brodyn Pty Ltd v Davenport [2004] NSWCA 394; (2004) 61
NSWLR 421[1] established, for relevantly similar
New South Wales legislation,[2] the essential
requirements for a valid adjudicator’s determination. Those included the
existence of a construction contract,
but did not include that the contract be
with a builder holding the appropriate contractor’s licence. He submitted
that the
reason an unlicensed builder could claim to be entitled to a progress
payment under s 17 was simply because the 2004 Act clearly
provided for claims
to be made, and for payment ordered in respect of them, even if those claims
were later shown to be unjustified.
The purpose of the legislation was to
provide for a system of quick payments, with s 100 of the 2004 Act providing for
later correction
in subsequent civil proceedings, including orders for
restitution of any amount paid.
[47] Assuming the New South Wales Court of
Appeal is correct in Brodyn Pty Ltd v Davenport as to the essential requirements
for a
valid adjudicator’s determination, and accepting that the 2004 Act
has as its object ensuring that a person entitled to receive
progress payments
is able to recover them if the person undertakes to carry out construction work,
the respondent plaintiff was not
entitled in relation to the construction
contract, under s 13, to an amount calculated on the basis of the value of the
construction
work the plaintiff had carried out. Section 42(3) of the 1991 Act
prevented his being entitled. Mr O’Shea conceded the 1991
Act had the
effect that the plaintiff was not entitled under s 17 to a progress payment. In
my opinion the plaintiff could not claim
to be entitled to those payments. It
pleaded an entitlement pursuant to s 13 which it did not have, and pleaded that
only after
pleadings in this Court had raised the issue of its being unlicensed.
If it was unlicensed, no investigation (prompt or slow) could
advance its s 13
claim to entitlement to a progress payment.
[48] The appellants’
pleading, if accurate, revealed that the respondent had no proper claim to be
entitled to a progress payment,
and accordingly the respondent was not entitled
to serve a payment claim for progress payments on the appellants. It was
appropriate
for the appellants to plead, as they did, that the plaintiff was not
entitled to any benefits under the 2004 Act, and although perhaps
unnecessary,
they could have sought a declaration to that effect, or an order setting aside
service of that s 17 payment claim.
Their current pleading, that the plaintiff
was not entitled to any benefits under the 2004 Act by reason of it not holding
the appropriate
class of licence, if upheld, has the result that neither ss 17,
18, or 19 of the 2004 Act could be availed of by the plaintiff.
It follows that
summary judgment for the plaintiff in the amount of $493,339.45 should be set
aside.
[49] PHILIP McMURDO J: Section 42 of the Queensland Building Services
Authority Act 1991 (Qld) (“the Building Act”) prohibits a person
from carrying out, or undertaking to carry out, building work unless that person
holds a licence which
is appropriate for that work. A person who contravenes s
42 commits an offence: s 42(9).
[50] Section 42(3) provides that a person who
carries out building work whilst unlicensed “is not entitled to any
monetary or other consideration
for doing so”, except on the limited bases
allowed by s 42(4). Yet in the present case, the respondent builder, which for
present purposes had to be treated as unlicensed, was held entitled to
a
monetary consideration for doing the work, and without purporting to limit its
claim according to s 42(4). The respondent’s argument, which the Chief
Justice as the primary judge accepted, was that a builder’s entitlement to
a progress payment by the operation of the Building and Construction Industry
Payments Act 2004 (Qld) (“the Payments Act”) was not affected by s
42. The Payments Act does not expressly provide that a builder’s
entitlement to a progress payment is outside the disentitling provisions of s 42
of the Building Act. And s 42(3) is in the widest terms: it refers to
“any monetary or other consideration”, which on any view would
include a payment
for (part of) the work.
[51] The Payments Act closely
corresponds with the terms of the Building and Construction Industry Security of
Payment Act 1999 (NSW). The operation of that Act, in the context of a claim by
a builder which was not licensed as required by the Home Building Act 1989
(NSW), was examined by the New South Wales Court of Appeal in Brodyn Pty Ltd v
Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421. There is no relevant distinction between the
terms of the Payments Act and that corresponding statute in
New South Wales.
But, there is a difference between s 42 of the Building Act and s 10 of the Home
Building Act of New South Wales, which is, in these.terms:
“10 Enforceability of contracts and other rights
(1) A person who contracts to do any residential building work, or any specialist work, and who so contracts:
(a) in contravention of section 4 (Unlicensed contracting), or
(b) under a
contract to which the requirements of section 7 apply that is not in writing or
that does not have sufficient description of the work to which it relates (not
being a contract entered
into in the circumstances described in section 6 (2)),
or
(c) in contravention of any other provision of this Act or the regulations
that is prescribed for the purposes of this paragraph.
is not entitled to
damages or to enforce any other remedy in respect of a breach of the contract
committed by any other party to the
contract, and the contract is unenforceable
by the person who contracted to do the work. However, the person is liable for
damages
and subject to any other remedy in respect of a breach of the contract
committed by the person.
(2), (3) (Repealed)
(4) This section does not
affect the liability of the person for an offence against a provision of or made
under this or any other
Act.”
In Brodyn, the conclusion of Hodgson JA, with whom Mason P and Giles JA agreed, was that the builder’s entitlement to a progress payment was a statutory entitlement which was outside the operation of s 10 because it was neither a remedy by way of “damages” nor a “remedy in respect of breach of contract”.[3] Hodgson JA compared s 10 with s 94 of the same Act, which provides for the effect of a builder’s doing work without the insurance as required by that Act. In that circumstance, the uninsured contractor:
“(a) is not entitled to damages, or to enforce any other remedy in respect of a breach of the contract committed by any other party to the contract in relation to that work, and
(b) is not entitled to recover money in respect of that work under any other right of action (including a quantum meruit)”[4]
Hodgson JA said that his opinion as to the limited scope of s 10 was confirmed
by the different terms of s 94. [5] The
difference is that s 94 also contains the wide expression: “money in
respect of that work”. As Williams JA has
said, that expression in s 94
seems much the same as that in s 42 of the Building Act, so that Hodgson
JA’s judgment in Brodyn indicates the difference between the provision
which was relied upon there, s 10 of the Home Building Act and the wider terms
of s 42 of the Building Act. In Brodyn, the alleged entitlement to a progress
payment was simply outside the terms of the statutory limitation upon recovery
by unlicensed builders. In Queensland, that alleged entitlement is apparently
within the terms of s 42. The present question, for which Brodyn does not
indicate an answer, is whether the Payments Act was intended to override the
disentitlement
to any payment resulting from s 42.
[52] The expressed
object of the Payments Act is to ensure that a person is entitled to receive,
and is able to recover, progress
payments if the person undertakes to carry out
construction work or to supply related goods and services under a construction
contract.[6] That object is achieved by granting
an entitlement to progress payments, whether or not the relevant contract
provides for them,
and establishing a procedure for their
recovery.[7] That procedure involves the making
of a payment claim, the possible provision of a response to that claim (“a
payment schedule”),
the referral of a disputed or unpaid claim to an
adjudicator for decision and the payment of the amount decided by the
adjudicator.[8]
[53] Section 12 creates an
entitlement to a progress payment where a person has undertaken, under a
construction contract, to carry
out construction work or supply related goods
and services. As Hodgson JA held in Brodyn, one essential prerequisite for the
operation
of this statute is the existence of a construction contract to which
the Act applies. So in the present case, the respondent’s
entitlement, if
any, to a progress payment and to the benefit of this scheme for its recovery,
must derive from its having undertaken
to carry out construction work. Yet,
assuming that the respondent was then an unlicensed builder, it committed an
offence in undertaking
to carry out that work. The respondent’s case
therefore proceeds from the unattractive proposition that its committing an
offence was an essential step to its becoming entitled to the beneficial
operation of this scheme.
[54] The respondent’s argument meets a
further obstacle in the provisions by which a progress payment is to be
quantified.
Section 13 provides that the amount of a progress payment to which
a person is entitled is either the amount calculated under the
contract, or, if
the contract does not provide for the matter, then an amount calculated on the
basis of the value of the construction
work carried out or undertaken to be
carried out. Section 14 provides for how that value is to be assessed, as
follows:
“(1) Construction work carried out or undertaken to be carried out under a construction contract is to be valued -
(a) under the contract; or
(b) if the contract does not provide for the
matter, having regard to –
(a) the contract price for the work; and
(b) any other rates or prices stated
in the contract; and
(c) any variation agreed to by the parties to the
contract by which the contract price, or any other rate or price stated in the
contract,
is to be adjusted by a specific amount; and
(d) if any of the work
is defective, the estimated cost of rectifying the defect.”
Leaving aside the case of defective work, it can be seen that construction work is to be valued according only to what the parties had agreed, because the valuation of the work, which quantifies the progress payment, must derive from the contract price, from rates or prices stated in the contract or from any agreed variation to those things.
[55] This is a difficulty in the operation of the Payments Act in the case of an
unlicensed builder, because that builder is not
entitled to enforce its contract
and, in particular, to recover its contract price. The builder is limited
effectively to recovering
its costs, according to s 42(4) of the Building Act,
except that if its costs are greater than the agreed price, the builder is
limited to the price: s 42(4)(c). The respondent does not suggest that an
unlicensed builder’s ultimate entitlement (or disentitlement) is not
according to
s 42. It argues only that an unlicensed builder is entitled to
progress payments as if s 42 had no operation, although in the final accounting,
s 42 applies, and a builder could be ordered to make restitution pursuant to s
100(3) of the Payments Act.
[56] Accordingly, the respondent’s argument
is that the Payments Act is intended to facilitate the recovery of a progress
payment
or payments, which in at least many cases, would be more than the cost
of performing the work to that point, although ultimately
the builder would be
entitled to no more than its costs. Had the Payments Act provided for some
progressive recovery by progress
claims quantified by reference to an unlicensed
builder’s limited entitlement under s 42(4), it would have an evident
policy.
But there is no evident reason in policy why an unlicensed builder
should be given a right to part payments, which must be quantified
not according
to its ultimate entitlement for the whole works, but in higher sums according to
terms of a contract which the builder
cannot enforce.
[57] Section 21
provides that a claimant may apply for adjudication of a payment claim if the
respondent to its claim has duly disputed
the claim or failed to pay such of the
claim which is not disputed. By s 26, an adjudicator is to decide the amount of
the progress
payment, if any, to be paid.[9]
Section 26(2) provides that the adjudicator is to consider only these
matters:
“(a) the provisions of this Act and, to the extent they are relevant, the provisions of the Queensland Building Services Authority Act 1991, part 4A;
(b) the provisions of the construction contract from which the application arose;
(c) the payment claim to which the application relates, together with all submissions, including relevant documentation, that have been properly made by the claimant in support of the claim;
(d) the payment schedule, if any, to which the application relates, together with all submissions, including relevant documentation, that have been properly made by the respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates.
Section 42 of the Building Act is not within Part 4A of that Act. Therefore, in
the case of an unlicensed builder’s claim, the adjudicator could not
consider s 42. The adjudicator
would be obliged to value the work according to
s 14. And, by s 27, in a subsequent adjudication, the adjudicator would
have
to adopt “the same value as that previously decided unless
(satisfied) that the value of the work ... has changed since the
previous
decision”.
[58] Accordingly, another unattractive aspect of the
respondent’s argument is that the regime of adjudication would often
result
in something higher than the commensurate share of the builder’s
ultimate entitlement, and, therefore, in an overpayment.
[59] In some
cases, which the arguments agree is the case here, there could be a genuine
question as to whether the builder is relevantly
unlicensed. In particular,
there could be questions of fact going to the classification of the work for the
purposes of the licensing
requirements, which cast doubt on whether the builder
held the licence appropriate for the agreed work. But, that is not a matter
which could be investigated by the adjudicator, who would be confined to a
consideration of the matters listed in s 26(2). Nor could
the respondent to a
payment claim, dispute the claim on that basis, within its “payment
schedule” given under s 18, because
if this regime applies to unlicensed
builders then the absence of a licence would have no relevance in the valuation
of the progress
claim.
[60] In these ways, the operation of the Payments
Act in the case of an unlicensed builder would lead to a result in at least many
cases which is unjust, judged by the policy of the licensing provisions of the
Building Act. The operation of this scheme by the overpayment of unlicensed
builders pending a final reconciliation, is likely to have effects
which cannot
be cured by an order under s 100. There is no sensible explanation for the
Payments Act to have an operation of
that kind.
[61] The purpose of a
scheme of progress payments is to permit a builder to be paid the agreed
consideration for the works progressively,
by a part payment which is
commensurate with that part of the works performed to that point. This scheme
for progress claims and
their recovery is evidently unsuitable for the case of
unregistered builders, because it operates from a premise of the builder’s
entitlement being according to its contract. The long title of the Payments Act
describes it as an “Act to imply terms in
construction contracts
...” It is unlikely the Act was intended to benefit builders who cannot
enforce the payment provisions
of their contracts, especially when the making of
such a contract involved an offence by the builder. Ultimately, it far from
appears
that the Payments Act was intended to override the disentitlement
according to s 42; the contrary appears. In my view, the Payments
Act operates
only when there is a construction contract of which the terms as to payment are
enforceable by the builder.
[62] The respondent’s claim in these
proceedings, even when given its new appearance as a purported progress claim,
is precluded
by s 42 if the respondent did not hold the relevant licence. As
there is at least an issue to be tried on that matter, the respondent
should not
have been given summary judgment. I agree with the orders proposed by Williams
JA.
[1] [2004] NSWCA 394; Appeal No 40296 of 2004, 3 November 2004.
[2] [2004] NSWCA 394; (2004) 61 NSWLR 421 at 441.
[3] [2004] NSWCA 394; (2004) 61 NSWLR 421, 449.
[4] Subject to an allowance on a quantum meruit basis if a Court or Tribunal considers it just and equitable: s 94(1A).
[5] [2004] NSWCA 394; (2004) 61 NSWLR 421, 449.
[6] s 7.
[7] s 8.
[8] s 8.
[9] As well as the date for payment and the rate of interest payable on any amount: s 26(1)(b) and s 26(1)(c).
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QCA/2006/538.html