You are here:
AustLII >>
Databases >>
Environment Resources and Development Court of South Australia >>
2011 >>
[2011] SAERDC 39
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
CITY OF SALISBURY v MWS ENGINEERING PTY LTD & ORS [2011] SAERDC 39 (29 September 2011)
Last Updated: 29 September 2011
ENVIRONMENT, RESOURCES AND
DEVELOPMENT COURT OF SOUTH AUSTRALIA
DISCLAIMER - Every effort
has been made to comply with suppression orders or statutory provisions
prohibiting publication that may
apply to this judgment. The onus remains on
any person using material in the judgment to ensure that the intended use of
that material
does not breach any such order or provision. Further enquiries
may be directed to the Registry of the Court in which it was generated.
CITY OF
SALISBURY v MWS ENGINEERING PTY LTD & ORS
[2011] SAERDC 39
Judgment of His Honour Judge
Costello
29 September 2011
ENVIRONMENT AND PLANNING - BUILDING
CONTROL - OTHER MATTERS - OFFENCES AND PENALTIES - UNAUTHORISED WORK
Three defendants each charged with two separate offences of undertaking
building work without approval - pleas of guilty to each offence
entered -
defendants erected two warehouse buildings without approval - conduct of
defendants inadvertent not deliberate - convictions
entered - corporate
defendants each fined $3,000 for each offence - defendant director fined $4,500
for each offence - no occasion
to invoke "totality principle".
Development Act 1993; Criminal Law (Sentencing) Act 1988,
referred to.
R v Major [1998] SASC 7089; (1998) 70 SASR 488; Nixon 66 A Crim R83; City of
Salisbury v Ahrens Group [2010] SASC 254; (2010) 108 SASR 54; Rossi (1988) 142 LSJS
451, 455, discussed.
CITY OF SALISBURY v MWS
ENGINEERING PTY LTD &
ORS
[2011] SAERDC 39
THE COURT DELIVERED THE FOLLOWING JUDGMENT
The Complaint
- The
defendants are charged upon complaint with breaches of section 44(1) of the
Development Act 1993 (“the Act”).
- The
complaint is as follows:
Offence Details
- Between
January 2009 and October 2009 at Pooraka in the said State, the First Defendant
undertook development which was not an approved
development contrary to section
44(1) of the Development Act 1993 (the
Act).
Particulars
1.1 Between the said dates the First Defendant caused, suffered or permitted
development, namely building work, comprising the construction
of an extension
to its existing workshop on the land known as 27-29 Maxwell Road Pooraka In the
said State, comprised in Certificate
of Title Register Book Volume 5919 Folio
142 (the subject land).
1.2 The said development was not an approved development.
Offence Details
- In
or about October 2009 at Pooraka or elsewhere in the said State the First
Defendant undertook development which was not an approved
development contrary
to section 44(1) of the Act.
Particulars
2.1 On or about the said dates, the First Defendant caused, suffered or
permitted development, namely building work, comprising
the construction of an
extension to the existing Adelaide Precast Workshop, on the subject land.
2.2 The said development was not an approved development.
Offence Details
- Between
January 2009 and October 2009 at Pooraka, in the said State, the Second
Defendant undertook development which was not an approved
development contrary
to section 44(1) of the Act.
Particulars
3.1 Between the said dates the Second Defendant caused, suffered or permitted
development, namely building work, comprising the construction
of an extension
to the First Defendant’s workshop on the subject land.
3.2 The said development was not an approved development.
Offence Details
- In
or about October 2009 at Pooraka or elsewhere in the said State, the Second
Defendant undertook development which was not an approved
development contrary
to Section 44(1) of the Act.
Particulars
4.1 On or about the said dates the Second Defendants caused, suffered or
permitted development, namely building work comprising the
construction of an
extension to the existing Adelaide Precast Workshop, on the subject land.
4.2 The said development was not an approved development.
Offence details
- Between
January 2009 and October 2009 at Pooraka or elsewhere in the said State the
Third Defendant undertook development which was
not an approved development
contrary to section 44(1) of the Act.
Particulars
5.1 Between the said dates the Third Defendant caused, suffered or permitted
development, namely building work, comprising the construction
of an extension
to the First Defendant’s workshop on the subject land.
5.2 The said development was not an approved development.
Offence details
- In
or about October 2009 at Pooraka or elsewhere in the said State, the Third
Defendant undertook development which was not an approved
development contrary
to section 44(1) of the Act.
Particulars
6.1 On or about the said dates, the Third Defendant caused, suffered or
permitted development, namely building work, comprising the
construction of an
extension to the existing Adelaide Precast Workshop, on the subject land.
6.2 The said development was not approved development.
Offence Details
- Between
January 2009 and October 2009 at Pooraka, or elsewhere in the said State, the
Third Defendant was a director of a company
which undertook development which
was not an approved development and thereby contravened section 44(1) of the Act
contrary to section 105(3) of the Act.
Particulars
7.1 Between the said dates the Third Defendant was a director of the First and
Second Defendants.
7.2 Between the said dates the First Defendant and/or Second Defendants caused,
suffered or permitted development, namely building
work, comprising the
construction of a warehouse extension to the First Defendant’s warehouse
on the subject land.
7.3 The said development was not an approved development.
Offence Details
- In
or about October 2009 at Pooraka or elsewhere in the said State, the Third
Defendant was a director of a company which undertook
development which was not
an approved development and thereby contravened section 44(1) of the Act
contrary to section 105(3) of the Act.
Particulars
8.1 On or about the said dates the Third Defendant was a director of the First
and Second Defendants.
8.2 On or about the said dates the First Defendant and/or the Second Defendants
caused, suffered or permitted development, namely
building work, comprising the
construction of an extension to the Adelaide Precast Workshop on the subject
land.
8.3 The said development was not an approved development.
Offence Details
- In
or about October 2009 at Pooraka or elsewhere in the said State, the Fourth
Defendant undertook development which was not an approved
development contrary
to section 44(1) of the Act.
Particulars
9.1 On or about the said dates, the Fourth Defendant caused, suffered or
permitted development, namely building work, comprising
the construction of an
extension to the existing Adelaide Precast Workshop, on the subject land.
9.2 The said development was not an approved development.
Offence Details
- Between
January 2009 and October 2009 at Pooraka, or elsewhere in the said State, the
Fourth Defendant was a director of a company
which undertook development which
was not an approved development and thereby contravened section 44(1) of the Act
contrary to section 105(3) of the Act.
Particulars
10.1 Between the said dates the Fourth Defendant was a director of the First and
Second Defendants.
10.2 Between the said dates the First Defendant and/or Second Defendants caused,
suffered or permitted development, namely building
work, comprising the
construction of a warehouse extension to the First Defendant’s warehouse
on the subject land.
10.3 The said development was not an approved development.
Offence Details
- In
or about October 2009 at Pooraka or elsewhere in the said State, the Fourth
Defendant was a director of a company which undertook
development which was not
an approved development and thereby contravened section 44(1) of the Act
contrary to section 105(3) of the Act.
Particulars
11.1 On or about the said dates the Fourth Defendant was a director of the First
Defendant and the Second Defendant.
11.2 On or about the said dates the First and/or Second Defendants caused,
suffered or permitted development namely building work
comprising the extension
of the Adelaide Precast Workshop on the subject land.
11.3 The said development was not an approved
development.
- The
first defendant has pleaded guilty to Counts 1 and 2. The second defendant has
pleaded guilty to Counts 3 and 4. The third defendant
has pleaded guilty to
Counts 5 and 6. The complainant has applied to withdraw Counts 7 and 8 and I
dismiss these charges.
- No
plea has been entered by the fourth defendant and further consideration of
Counts 9-11 inclusive must await the outcome of negotiations
between the
parties.
Statement of Agreed Facts
- On
the hearing, the complainant submitted a Statement of Agreed Facts which is as
follows:
- The
First Defendant is a licensed builder authorised to undertake building work that
does not exceed one storey in height in addition
to structural steel erection in
South Australia by virtue of building licence number BLD 36042.
- The
First Defendant is a steel fabrication company which employed approximately
forty (40) people in the said State however now employs
twelve (12) people.
- The
Operation Manager of the First Defendant requested permission from the Third
Defendant to construct an extension to an existing
workshop (Building B)
on the land known as 27-29 Maxwell Road, Pooraka (Land) as the First
Defendant required additional workshop area within which to conduct and operate
its business on the Land. The Third
Defendant gave permission for the said
extensions to be constructed. The First Defendant was directed by the Third
Defendant to
construct an extension to the existing Adelaide Pre-Cast workshop
(Building C and D) on the Land as Adelaide Pre-Cast required additional
workshop area within which to conduct and operate its business on the
Land.
4. The Second Defendant is the registered proprietor of the Land.
5. The Third and Fourth Defendants are directors of the First and Second
Defendants.
- The
Fourth Defendant is a licensed builder and is licensed to undertake any building
work limited to structural steel erection and
domestic building work not
exceeding one storey in South Australia by virtue of building licence BLD
40002.
Building B
- A
development application identified as development application number
361/2587/2009/2B was submitted to the Council on or about 15
October 2009 for
the construction of Building B.
- The
development application form submitted to the Council or on about 15 October
2009 for Building B indicated that the “development
cost” was
$120,000.
- Construction
of Building B commenced on the Land on or about August 2009 and was completed on
or about 22 October 2009. The building
was occupied at that date.
- Building
B is an extension to an existing building on the Land. It is a class 7B
building under the Building Code of Australia (BCA). It is predominately
used to cure paint on steel.
- The
total floor area of Building B is approximately 844 square metres with a height
of 4.5 metres. Together, Building B and the building
which it extended have a
total floor area of 1688 square metres and a height of 4.5
metres.
12. Development Plan consent was granted to Building B on 5 March
2010.
- To
date, neither Building Rules consent nor Development Approval has been granted
by any relevant authority, to Building B.
14. To date, a certificate of Occupancy has not been granted in relation to
Building B.
- On
or about 22 October 2009, the Complainant issued a notice pursuant to section
84(2) of the Development Act 1993 (Act) to the First and Second
Defendants in relation to the construction of Building B on the Land. The said
notice provided that development
was being undertaken on the Land without a
valid development approval. The said notice directed that the First and Second
Defendants
“refrain from all construction work and occupation of the
building until further notice or a valid development approval has been
granted”.
- It
is accepted by the Complainant that when the said notice was issued in relation
to Building B the building was essentially completed.
For a period of time
after the said notice was first issued in relation to Building B, Building B
ceased to be occupied. However,
at present, Building B is now
occupied.
Buildings C & D
- A
development application identified as development application number
361/1885/2009/1B was submitted to the Council on or about 30
July 2009 for the
construction of Building C. Subsequently, a further development application
identified as development application
number 361/2586/2009/2B was submitted to
the Council on or about 15 October 2009 for the construction of Building C &
D. Effectively,
the latter application incorporated the construction of
Building C which had been included in the earlier application. The latter
application sought to combine the construction of Building C with Building
D.
- The
development application form submitted to the Council on or about 30 July 2009
for Building C indicated that the “development
cost” was $350,000.
The development application form submitted to the Council on or about 15 October
2009 for Building C &
D (as a combined development) indicated that the
“development cost” was $1.1 million.
- A
number of steel posts forming part of the framework for Building C and one steel
post forming part of the framework for Building
D were erected on the Land on 28
October 2009. Some trenches had been excavated and concrete pads were poured in
preparation for
the erection of the steel posts on or before 19 October
2009.
- Building
C & D together are a class 5 and 7B building under the BCA. Building C is
presently used by the company Adelaide Precast
Pty Ltd who operates its business
from a portion of the Land. It is proposed that Building D, once completed,
will be similarly
used.
- Building
C & D together when completed also will involve an extension of an existing
building on the Land and will have a total
area of approximately 1300 square
metres and a height of 10 metres.
- Development
Plan consent was granted to Building C on 11 August 2009. Neither Building
Rules consent nor development approval was
granted to development application
number 361/1885/2009/1B (for the construction of Building C) because the latter
application for
Building C & D, as combined structures (361/2586/2009/2B)
superseded it.
23. Development Plan consent was granted to Building C & D on 01 December
2009.
24. Building Rules consent was granted to Building C & D on 22 December
2009.
25. Development Approval was granted to Building C & D on 22 December
2009.
- Subsequent
to the grant of the Development Approval the part of the extension identified as
Building C has been completed. To date,
that portion of the extension
identified as “D” has not been completed.
- To
date a Certificate of Occupancy has not been granted in relation to Building C
or the portion of Building D that has been constructed.
- On
or about 3 November 2009, the Complainant issued a notice pursuant to section
84(2) of the Development Act 1993 (Act) to the Second Defendant in
relation to the construction of Building C and portion of Building D on the
Land. The said notice provided
that development was being undertaken on the
Land without a valid development approval. The said notice directed the Second
Defendant
to “refrain from all construction work and occupation of the
building until further notice or a valid development approval has been
granted”.
- It
is accepted by the Complainant that when the said notice was issued in relation
to the construction of Building C and portion of
Building D, building work
ceased immediately.
- The
First Defendant was directed to construct Building B, C & portion of
Building D by its director the Third Defendant.
- Building
C and portion of Building D was constructed under the supervision of the Fourth
Defendant at the request of the Third Defendant.
- The
First Defendant commenced and completed the construction of Building B, and
commenced the construction of C & D without sighting
a Development Approval
or any plans stamped with such approval.
- The
Defendants did not satisfy themselves that Building Rules consent or Development
Approval had been obtained, nor did it make themselves
aware of the terms of any
such consent or any conditions attaching to it in relation to Building B, C or
D.
- At
all material times, all Defendants were aware of the need to obtain development
approval from a relevant authority before undertaking
development.
- In
his submissions, Mr Roder SC for the complainant referred me to the decisions of
the Supreme Court[1]
dealing with the “totality principle”. He also stressed the
need for the Court to bear in mind the public interest in imposing a penalty
which will operate as
a general deterrence to others who may be tempted to carry
out substantial building works without obtaining the necessary approvals.
Mr
Roder SC however properly accepted and conceded that these offences were
“sins of omission and not commission” in the sense to which I
will later refer.
The Defendants
- Ms
Powell QC, who appeared for all defendants, informed the Court that in 1972 the
fourth defendant (“Clemente”) commenced to operate a steel
construction business under the name of Magill Welding. This later became the
first defendant
(“MWS”). He was subsequently joined by the third
defendant (“Paolo”), his son.
- Paolo
was born in Australia in 1971. He is married with two children, who are 5 and 3
years old. He graduated with an associate
diploma from the University of South
Australia in 1994 and thereafter, as I have said, joined his father in the
business.
- The
business grew and from around 2000 it began tendering for and winning larger
commercial construction projects. Since that time
it has expanded to over a
dozen companies which companies are collectively known as the MWS Group
(“the Group”).
- In
2002 the second defendant was incorporated with its principal purpose being as a
property holding company. It is the owner of
the land on which the offences
occurred (“the subject land”).
- By
2009 the Group had approximately 200 employees, 70 being employed by MWS and 80
by Adelaide Precast Pty Ltd (“Adelaide Precast”).
The Group had
become a leading supplier, fabricator and erector of quality fabricated
structural steel to the industrial and commercial
building industry as well as
the mining industry all around Australia.
- The
Group has successfully contracted for and constructed projects such as the
Wakefield Street car park, the CMI Toyota headquarters
at West Terrace, the
Northland Shopping Centre in Victoria and the Crown Apartment complex in
Hindmarsh Square.
- In
addition to these projects, the Group has been involved in the construction of
numerous warehouse projects in and around the Salisbury
Council area.
- In
2002-2003, the Group relocated its businesses to the subject land and in the
process, constructed a new head office, access roads
and associated earthworks
and landscaping.
- In
2005 Adelaide Precast was incorporated. Its business involved the manufacture,
supply and erection of pre-cast concrete panels.
- In
summary, it is clear from the above (and I accept) that the Group has been very
successful over a number of years in the areas
of the manufacture, supply and
erection of structural steel and pre-cast concrete
panels.
Events surrounding the Offences
- In
around 2009 the Group successfully tendered for the supply and installation of
the structural steel work and pre-cast concrete
panels for the South Australian
Water Desalination Project. The original sub-contract sum for the two areas of
work was in excess
of $10 million. As a result of additional works, the
original sum was increased by $4 million making the overall sum in excess of
$14
million.
- This
was particularly significant for the Group as a hedge against the downturn
caused by the Global Financial Crisis.
- In
2009 the Group needed additional storage space. In the case of Building
“B” it was required to house the structural
steel while multiple
layers of paint were applied to it as part of the Desalination Project.
- Buildings
“C and D”, which Ms Powell QC submits were always intended to be
one, single building, were required, as to
one half, to house and operate a
concrete polishing machine and, as to the other, to store the completed concrete
panels.
- In
August 2009, Clemente and Paolo purchased the polishing machine in Italy.
Whilst they were in Italy finalising its purchase they
were contacted by Mr Mark
Crook, seeking permission to proceed with constructing building “B”.
Paolo gave Mr Crook the
“go ahead”.
- The
total construction time to build it was some 2-3 weeks, it being a portable
frame construction with sheet walls and roof cladding.
The drawings for the
building were on site and the materials at hand. Indeed, I am told that there
is no concrete slab but simply
a quarry rubble base.
- I
accept the submission by Ms Powell QC that although the building is substantial,
in terms of its size, it is not a complicated building
in terms of
infrastructure. I understand Buildings “C and D” to fall into much
the same category.
- In
giving Mr Crook the “go ahead”, Paolo wrongly (but I
accept not unreasonably) assumed that Mr Crook (as the person responsible for
the design and construction
of the building) had attended to the necessary paper
work involved in gaining approvals. There were numerous precedents around the
office available to him. Moreover, he had been with the Group as an Operations
Manager for 2 years and had previously worked extensively
with the
Samari’s Group, a well-known steel fabricator and erector.
- Mr
Crook’s explanation was that he believed the priority was to get the job
done quickly and chose speed over operating lawfully.
I am told that upon
learning of this explanation Mr Crook was subsequently dismissed by Paolo.
- When
Paolo learned that an approval had not been obtained he instructed Mr Pound a
project designer to lodge the appropriate application.
A development
application was submitted on 15 October 2009. Soon after the application was
lodged a section 84 Notice was issued
by the Council in relation to Building
“B”. Although no Development Approval has been granted for
“B” it
is currently being occupied. Ms Powell QC tells me (and I
accept) that Building B is not being “utilised” in an
operational sense as the business is, for practical purposes, not
operating.
- In
relation to Buildings C and D, although a building application for Building
“C” was lodged on 30 July 2009, this was
superseded by a new
application for both buildings, again on 15 October 2009. Construction work
involving concrete pads and the
erection of some framework posts commenced in
October 2009. Following receipt of a s 84 Notice on 3 November 2009, work on
the buildings
ceased. A development approval for the buildings was granted on
22 December 2009.
Defendants Individual Circumstances
- In
the course of the construction of the Desalination Plant, in 2010 there was an
accident in which one of the employees of the Group
was killed. As a
consequence, the site was shut down for many weeks.
- The
head contractor withheld all future payments to the Group. At that time there
were unpaid progress claims in the order of $4.5
million.
- As
a result of being prevented from entering the site, monies due by the Group to
other building contractors were withheld. Performance
guarantees provided by
the Group on other projects were cashed or withheld and the Group lost several
projects it had expected to
win as a result of the accident and its
ramifications.
- As
a consequence of these matters, both the first defendant and Adelaide Precast
appointed a voluntary administrator and in May 2011
both entered into Deeds of
Company Arrangement.
- A
term of the first defendant’s Deed requires its directors to pay into the
Deed Fund the sum of $1 million within 12 months
of executing the Deed. In the
case of Adelaide Precast, the requirement is $½ million.
- The
payment under these Deeds is proposed to come from the sale of the subject land.
I am told that while there was an initial offer
of some $12 million for the
subject land, on learning of these prosecutions, that offer has been reduced to
some $10 million.
- Since
February 2011, the Group has lost all its work, now has only a skeleton work
force and struggles, as a result, to effectively
compete for new work. In
essence, as Ms Powell QC submitted, the Group no longer conducts a viable
business.
- I
am told, and it is not disputed, that it is likely that after the property is
sold there will not be funds left over for the members
of the companies.
- In
relation to Paolo, I am informed that he is being sued by creditors of both the
first defendant and Adelaide Precast under personal
guarantees from both himself
and his wife. The total amount claimed is in excess of $1 million and this
amount may increase.
- One
of the creditors has caveated the family home, which is in his wife’s
name, and he really has very little left. He has
not drawn any salary since
2011 and is in a parlous state, in terms of indebtedness to his various
creditors.
Penalty
- On
this issue generally I first bear in mind the remarks of Bleby
J[2], as to
the compelling public interest in favour of recording a conviction for this type
of offence by way of general deterrence to
others who may be tempted to carry
out substantial development without gaining Development Approval, or in
commencing substantial
development work without making any reasonable enquiry as
to whether Development Approval has been obtained.
- His
Honour’s observations are peculiarly apposite in the context of the facts
of this case and there are accordingly insufficient
grounds to exercise a
discretion to impose a penalty on any of the defendants without recording a
conviction.
- In
relation to the two corporate defendants I take into account the provisions of
section 105(1) of the Development Act 1993 which impute to each of them
the state of mind of Paolo as one of their directors. Having said that, I
should also say that I regard
the conduct of the corporate defendants in causing
suffering or permitting the building work to be less serious than the conduct
of
Paolo who was really the “controlling mind” in this
matter.
- I
propose to deal with each defendant in turn. I note that the maximum penalty
for a breach of s 44(1) is $120,000.
- In
relation to the first defendant I take into account the
following:-
1. The company has no prior convictions;
2. It made
admissions through its agent at the first available opportunity;
- The
financial consequences of the death of the employee have led to possible
financial ruin for a successful company and played a
part in deflecting its
attention from ensuring that requisite approvals were put in place in a more
timely fashion
- Although
the buildings were significant, the infrastructure involved meant that it was a
relatively simple construction exercise;
- The
contrition of the company as evidenced by its director, Paolo is both real and
obvious;
- Upon
realising that offences had been committed it put in place measures to ensure
that this would not happen again;
- Although
two separate offences have been committed, it would appear that the second
offence was committed in similar circumstances,
namely without knowledge or
connivance by the defendant..
- I
propose to impose a penalty of $4,000 on each Count but reduce each by 25% for
the plea of guilty making a total fine of $6,000.
- In
relation to the second defendant I make the same comments and I propose to
impose the same total penalty of $6,000.
- In
relation to the third defendant, I take into account the
following:
1. He has no prior convictions;
- He
co-operated with the Council and indicated a plea of guilty at the earliest
practical opportunity;
3. He has demonstrated real contrition;
- The
offences are offences of omission. They came about because of inadvertence
rather than a deliberate or contumelious disregard
for his obligations;
- He
has very properly acknowledged that although the conduct giving rise to the
offences was not his, he is nevertheless responsible
for it;
- He
has taken steps (by putting in place new procedures) to ensure that there is
unlikely to be a repetition of the offences;
- As
a result of the death of one of his employees, he is now in a somewhat parlous
financial state making the imposition of any financial
penalty much more onerous
than would have been the case in 2009.
- Finally
I take into account the character references submitted on his behalf by Ms
Powell QC which depict him to be a hard working
member of the community with
commendable honesty and integrity.
- I
propose to impose a fine on each Count of $6,000 but reduce each by 25% for his
plea of guilty, making an amount of $4,500 each
or a total of $9,000.
- In
their submissions both counsel referred me to the Court’s power to impose
one penalty upon each defendant pursuant to the
provisions of section 18A of the
Criminal Law (Sentencing) Act 1988, particularly in the context of the
“totality principle”.
- In
my view, the circumstances here do not call for the application of section 18A.
As King CJ
said[3]:
There is a principle of sentencing known as the principle of totality, which
enables a court to mitigate what strict justice would
otherwise indicate, where
the total effect of the sentences merited by the individual crimes becomes so
crushing as to call for the
merciful intervention of the court by way of
reducing the total effect.
- Although
His Honour’s observations were made in the context of sentencing for terms
of imprisonment, the principles to which
he adverted are nevertheless relevant
and constructive. I do not regard the total effect of the individual penalties
which I intend
to impose in relation to each offence (even in the straitened
financial circumstances of these defendants) as being “so
crushing”.
- There
is, accordingly, no occasion to depart from the penalties referred to
above.
The Order of the Court
The First Defendant
- On
Count 1, the first defendant is convicted and fined $3,000.
- On
Count 2, the first defendant is convicted and fined $3,000.
- In
addition I impose a Victims of Crime Levy in the amount of
$160.
The Second Defendant
- On
Count 3, the second defendant is convicted and fined $3,000.
- On
Count 4, the second defendant is convicted and fined $3,000.
- In
addition I impose a Victims of Crime Levy in the amount of
$160.
The Third Defendant
- On
Count 5, the third defendant is convicted and fined $4,500.
- On
Count 6, the third defendant is convicted and fined $4,500.
- In
addition I impose a Victims of Crime Levy in the sum of
$160.
[1] R v Major
(1998) [1998] SASC 7089; 70 SASR 488; Nixon 66 A Crim R83
[2] City of
Salisbury v Ahrens Group [2010] SASC 254; (2010) 108 SASR 54
[3] Rossi
(1988) 142 LSJS 451, 455
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/sa/SAERDC/2011/39.html