You are here:
AustLII >>
Databases >>
Environment Resources and Development Court of South Australia >>
2009 >>
[2009] SAERDC 94
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
CITY OF SALISBURY v ROCCA & ORS [2009] SAERDC 94 (22 December 2009)
Last Updated: 23 December 2009
ENVIRONMENT, RESOURCES AND
DEVELOPMENT COURT OF SOUTH AUSTRALIA
DISCLAIMER - Every effort
has been made to comply with suppression orders or statutory provisions
prohibiting publication that may
apply to this judgment. The onus remains on
any person using material in the judgment to ensure that the intended use of
that material
does not breach any such order or provision. Further enquiries
may be directed to the Registry of the Court in which it was generated.
CITY OF
SALISBURY v ROCCA & ORS
[2009] SAERDC 94
Reasons for Sentence of Her
Honour Judge Trenorden
22 December 2009
ENVIRONMENT AND PLANNING - BUILDING
CONTROL - OTHER MATTERS - OFFENCES AND PENALTIES
Pleas of guilty by first and third defendants - Whether appropriate to impose
penalty without conviction.
HELD: First and third defendants convicted and fined.
Environment, Resources and Development Court Act 1993; Development
Act 1993; Criminal Law (Sentencing) Act 1988, referred to.
Zefi v Police [2003] SASC 218; Leonello v Police [2005] SASC
29; Piva v Brinkworth (1992) 59 SASR 92, considered.
CITY OF SALISBURY v
ROCCA & ORS
[2009] SAERDC
94
THE COURT DELIVERED THE FOLLOWING REASONS FOR SENTENCE:
- A
large building comprising a warehouse and office was constructed on land at
35-37 Maxwell Rd Pooraka (the site), without development
authorisation first
having been obtained. The first and third defendants have each pleaded guilty
to an offence contrary to s44(1) of the Development Act 1993, in that
between 17 March 2008 and 13 November 2008, they undertook development at the
site, which was not an approved development.
- The
chronology of relevant events is as
follows:
|
19/10/07
|
Stafford Architects Pty Ltd, on behalf of the owners of the site, applied
to the City of Salisbury (the Council) for development plan
consent for the
construction of the proposed warehouse and office building (the project)
|
|
29/11/07
|
Ahrens Group Pty Ltd, builders, submitted to the first defendant a revised
quotation for the project in which the following were among
the terms and
conditions:
• no work will commence until written confirmation is received by
Ahrens; and
• the practical completion date will only be guaranteed providing
the council approvals are obtained as set out in the construction
program
|
|
17/03/08
|
Development plan consent was granted for the project
|
|
late 07/08
|
Construction work commenced
|
|
late 09/08
|
The third defendant poured the slab for the project
|
|
22/10/08
|
The architects informed the first and third defendant that development
authorisation had not been issued in respect of the project
by the Council
|
|
1/11/08
|
The warehouse and office building were being occupied
|
|
10/11/08
|
Building rules consent was granted for the project by private
certification
|
|
13/11/08
|
The project building was substantially completed
|
|
17/12/08
|
The first defendant tendered an apology to the Council and acknowledged
ultimate responsibility
|
|
03/04/09
|
Development authorisation was granted
|
|
22/09/09
|
The complaint was issued in relation to three defendants
|
- Stafford
Architects Pty Ltd (Stafford) was engaged by the first defendant as the
architects for the project. Stafford was responsible
for obtaining development
plan and building rules consent for the project, except that TNK Engineering was
to provide engineering
designs and obtain building rules consent for the
designs.
- It
was submitted that the owners engaged Stafford to draw plans and to obtain the
necessary development approval. However, an owner
cannot abdicate all
responsibility to another person. The Development Act provides in s32,
that “no development may be undertaken unless the development is an
approved development”. The meaning of “development”
in s4 of
the Act includes both building work and a change in the use of land, and
“to undertake development” means “to
commence or proceed with
development or to cause, suffer or permit development to be commenced or to
proceed.”
- The
first defendant is a director of two of the four companies which are the
registered proprietors (the owners) of the site. He
negotiated and executed an
agreement with the second defendant for the design and construction of the
warehouse and office building
on the site, in accordance with his appointment to
do so by the owners of the site.
- The
third defendant, who is the father of the first defendant and a licensed
builder, being a partner in the partnership of F &
E Rocca, licensed
builders, was engaged by the owners to carry out civil works including bench
levels, the construction of a concrete
slab for the building and construction of
a bitumen car park.
- It
is quite clear from these provisions of the Development Act that an owner
has a responsibility not to allow building works to commence unless the
development has been approved by the relevant
planning authority under the
Development Act. The land owner, the developer and anyone engaging in
building work on land may be undertaking development unlawfully if development
approval has not first been obtained for building works. All have a
responsibility to check that development approval has been obtained
before
building work is commenced. This is confirmed by the offence provision, namely
s44(1) under which the defendants have been charged.
- The
offence to which each of the first and third defendants have pleaded guilty is
of the kind known as a regulatory offence. In
determining an appropriate
sentence for offending of this nature, the Courts have emphasised the importance
of the element of general
deterrence, a matter to which the Criminal Law
(Sentencing) Act 1988 requires that I have regard: s10(1).
- The
first defendant asked the Court to take into account that he relied on a
provision in the revised quotation for the development,
provided by Ahrens Group
Pty Ltd that “no work will commence until written confirmation is received
by Ahrens” as meaning
that no work would commence until the relevant
development approval had been obtained. I cannot take the assertion into
account.
The statement quoted is set out under the heading “Terms and
Conditions” in what is clearly a revised quotation for
the project. It is
a standard type of statement in a quotation, indicating no more than that the
company wanted written confirmation
of acceptance of the quotation, before work
would commence. The first defendant has undertaken other developments. I do
not accept
that he would have interpreted the statement in the quotation as is
asserted.
- It
is clear to me that both the first and third defendants did not deliberately
offend. Their error was to rely on Stafford having
obtained development
approval without checking whether approval had been obtained. The omission
amounted to inadvertence, an oversight
or carelessness, rather than a deliberate
breach of the law.
- I
accept that both defendants were surprised, angry, dismayed and embarrassed,
when told by the architects on 22 October 2008 that
the development had been
constructed without development approval.
- I
note that the development has now been completed in accordance with the
development approval, with the exception of the landscaping,
which is not able
to be completed for reasons that are understood by the complainant and which I
do not need to go into here. In
effect, the situation has been
regularised.
- I
note that the warehouse and office building were tenanted from 1 November 2008.
However, the owners decided, in view of the offending,
not to accept any rent
from the tenants until development approval was obtained. Rent has been
received by the owners (the four
companies) in the amount of $25,000 per month
since the date of the grant of development approval, namely 3 April 2009. As
the complainant
pointed out, the owners have had the benefit of rent from the
date of development approval, which is much earlier than would usually
be the
case. Development approval is usually the point at which construction
commences; not the date upon which rent begins to be
payable and is received.
Thus, the owners (the four companies) received rent some eight months earlier
than they would have otherwise,
having regard to the time it took to construct
and complete the building works. However, on the other hand I note the owners
were
probably also required to obtain and outlay finance earlier than they
otherwise would have, for the building works.
- The
maximum penalty for an offence against s44(1) of the Development Act is
and was at the relevant time, $120,000.
The First Defendant
- I
have taken into account all that has been put to me with respect to the
background and history of the first defendant. I note that
he has overcome
early physical setbacks and is a successful businessman with an excellent
character, with no previous convictions.
- The
first defendant is a representative of the owners, being a director of two of
the four owner companies and having been given the
responsibility to negotiate
and execute an agreement with the second defendant for the design and
construction of the warehouse and
office building the cost of which was not
insignificant, on the site.
- He
is an accountant with some history of involvement in developments and
businesses. Given his past involvement in developments,
I conclude that he must
have been aware of the requirements of the Development Act with respect
to undertaking development.
- While
I accept that he relied upon others, as a representative of the owners of the
site he had a responsibility to check that development
approval had been
obtained, before allowing the development to proceed.
- I
agree that the offending is at the lower end of the scale. However, it is
important that others in a similar position to the first
defendant understand
that the law must be upheld, so I am aware of the need, in determining sentence,
to generally deter others from
offending in similar circumstances.
- I
accept that the first defendant is very unlikely to offend against the
Development Act again. He has learnt his lesson. I note particularly in
this regard, that the first defendant tendered an apology in a letter to
the
complainant dated 17 December 2008. In that letter, the first defendant
acknowledged ultimate responsibility for the breach
of the Development
Act. It is clear that the first defendant is contrite.
- I
consider that the offending warrants a penalty of in the order of 15% of the
maximum. I would discount that by 25% for an indication
of a plea of guilty at
the first opportunity. That calculation results in a proposed penalty of
$13,500. The first defendant will
be convicted and fined in the sum of
$13,500.
The Third Defendant
- I
note that the third defendant is the father of the first defendant and is aged
70 years. He has been a bricklayer for 50 years
and for the past 40 years has
held a builder’s licence. He has no convictions, and there was no
suggestion that he has other
than an excellent character.
- The
third defendant poured the slab and carried out other related works for the
building works without checking whether development
approval had been
obtained.
- I
accept that the third defendant is unlikely to offend again and has been upset
and embarrassed by the realisation of his offending.
I am confident he will not
offend again, particularly having regard to the fact that he wishes to retain
his builder’s licence
and is aware of the need to remain a fit and proper
person if he is to retain the licence.
- That
brings me to the submission put on behalf of the third defendant, namely that he
should be sentenced without conviction. This
submission was put on the basis
that the third defendant is afraid of losing his builder’s licence should
a conviction be recorded.
Section 16 of the Criminal Law (Sentencing) Act
enables a court to impose a fine without conviction when a person is found
guilty of an offence in circumstances where the defendant
is unlikely to so
offend again and that good reason exists for not recording a conviction having
regard to:
(i) the character, antecedents, age or physical or mental condition of the
defendant; or
(ii) the fact that the offence was trifling; or
(iii) any other extenuating circumstances.
- As
I have said, I am satisfied that the third defendant is unlikely to commit such
an offence again. The offence is not trifling.
In effect, I was asked to have
regard to extenuating circumstances, namely the prospect that the third
defendant would lose his
builder’s licence if convicted.
- It
will not necessary follow that the third defendant will lose his builders
licence, if convicted of this offence. It is a matter
for the relevant
authority. I must weigh the potential benefit to the third defendant of not
recording a conviction with the public
interest in convictions being recorded:
Zefi v Police [2003] SASC 218. In addition, where a defendant seeks to
have no conviction recorded because a conviction might disqualify him from
obtaining or
retaining a licence issued by a public authority, I must take into
account the countervailing public interest of the licensing authority
having
knowledge of the offending: Leonello v Police [2005] SASC 29.
- I
must also bear in mind that the discretion to sentence without conviction should
only be exercised sparingly in enforcing regulatory
legislation because of the
importance of the deterrent element: Piva v Brinkworth (1992) 59 SASR
92.
- If
a conviction is recorded against the third defendant, it would not automatically
result in loss of his builder’s licence.
On the other hand, the licensing
authority is entitled to know that the third defendant undertook building work
without sighting
a development approval; that is, without ensuring that the law
had been complied with. The licensing authority has to consider the
public
interest in determining whether licences should be granted or continue to be
granted.
- In
all of the circumstances, I am not prepared to exercise the power available
under s16 of the Criminal Law (Sentencing) Act, that is to impose a
penalty without recording a conviction against the third defendant.
- In
considering the appropriate sentence, I am mindful of all that has been put to
me on behalf of the third defendant. I have concluded
that his offending was
not at the same level as that of the first defendant, who was the representative
of the land owners. However,
there was and is a clear obligation on the part of
the third defendant and persons in his position, not to proceed with building
work without having obtained development approval, or having sighted a current
development approval, for the building works.
- In
this case, the third defendant should have asked to see the development approval
before he commenced to do the preparatory works
for the pouring of the
slab.
- In
all of the circumstances, I would impose a penalty in the order of 5% of the
maximum, and discount that by 25% for the indication
of a guilty plea at the
first opportunity. That results in a proposed penalty of $4,500. I would
convict the defendant and impose
a fine upon him of $4,500.
- I
note that each of the defendants have agreed to pay the amount of $7,500 to the
complainant by way of costs.
Sentence and Orders
The First Defendant
1. Is convicted and fined
in the amount of $13,500.
2. Is ordered to pay the complainant’s costs in the amount of
$7,500.
- Is
to pay a levy in the amount of $80 (Victims of Crime
Levy).
The Third Defendant
1. Is convicted and fined in the amount of
$4,500.
2. Is ordered to pay the complainant’s costs in the amount of
$7,500.
- Is
to pay a levy in the amount of $80 (Victims of Crime Levy).
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/sa/SAERDC/2009/94.html