You are here:
AustLII >>
Databases >>
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders >>
2007 >>
[2007] QBCCMCmr 685
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Glades Easthill North [2007] QBCCMCmr 685 (27 September 2007)
Last Updated: 6 November 2008
Office of the Commissioner for Body Corporate and
Community Management
SPECIALIST ADJUDICATION
(Caretaking Service
Contractor Dispute)
Number: 0384-2007
Applicant: BRIAN RUSHWORTH Respondent: BODY
CORPORATE FOR GLADES EASTHILL NORTH COMMUNITY TITLES SCHEME 32506
|
O R D E R S
27 September 2007
|
DECLARATORY ORDERS that:
- The
Remedial Action Notice dated 15 December 2006 does not comply with the
requirements of section 84C of the Body Corporate and Community Management
(Accommodation Module) Regulation 1997 (“Module”) and is
therefore void and of no effect.
- The
Notice dated 15 December 2006 served under clause 7.1(d) of the Caretaking
Agreement dated 16 August 2004 is defective in that
it failed to adequately
identify and particularise breaches of the Agreement the effect of which, if not
remedied, would be sufficient
to justify termination of the Agreement and is
therefore void and of no effect.
- The
Notice dated 15 December 2006 served under clause 7.1(a)(iv) of the Letting
Agreement dated 16 August 2004, having been withdrawn
by the Respondent, cannot
be further relied upon by the Respondent.
- The
Notice dated 13 February 2007 served under clause 7.1(d) of the Caretaking
Agreement dated 16 August 2004 is defective in that
it failed to adequately
identify and particularise breaches of the Agreement the effect of which, if not
remedied, would be sufficient
to justify termination of the Agreement and is
therefore void and of no effect.
FURTHER
ORDERS that:
- The
secret ballot voting papers held by or on behalf of the Respondent in respect of
motion 11 proposed to the Respondent’s
annual general meeting on 17 May
2007 be destroyed without being counted or otherwise examined.
- The
Respondent pay the costs of the adjudication within 60 days of receipt of an
invoice for those costs.
|
G F Bugden OAM
Specialist Adjudicator
Office of the Commissioner for Body Corporate and
Community Management
SPECIALIST ADJUDICATION
(Caretaking Service
Contractor Dispute)
Number: 0384-2007
Applicant: BRIAN RUSHWORTH
Respondent: BODY CORPORATE FOR GLADES EASTHILL NORTH
COMMUNITY TITLES SCHEME 32506
DETERMINATION
27 September 2007
Application
- This
is an application for resolution of a dispute involving a body corporate and a
caretaking service contractor that must be determined
by specialist adjudication
in accordance with the provisions of section 265 of the Body Corporate and
Community Management Act 1997 (‘Act’). The Act,
including that section, was amended substantially by the Body Corporate and
Community Management and Other Legislation Amendment Act 2007
(‘Amending Act’) which commenced on 1 July 2007.
- The
Amending Act inserted section 395 into the Act. That section requires
applications made but not disposed of before 1 July 2007
to be dealt with under
the Act as if the Amending Act has not been enacted. It follows, that
references in this determination are
references to the provisions of the Act as
they were in effect immediately before 1 July 2007.
- The
Applicant is a co-owner of lot 63 in community titles scheme 32506
(‘Scheme”), which can generally be referred to as the
Caretaker’s lot. The current Caretaker, Ambro Australia Pty Ltd, is a
company
related to the Applicant.
Management Agreement
- The
Body Corporate entered into a Caretaking Agreement with THL Robina Pty Ltd
dated 16 August 2004 (‘Agreement’). The Agreement is
for a term of 25 years from 10 August 2004. In the Agreement THL Robina Pty
Ltd was referred to as
the Caretaker, a term that I will use in this
determination.
- On
or about 28 February 2005 THL Robina Pty Ltd assigned the Agreement, as
well as a Letting Agreement which I will deal with
shortly, to Ambro (Aust) Pty
Ltd. The Body Corporate was a party to the Deed of Assignment and provided its
consent by means of
that deed. The Applicant is also the nominated on site
manager for Ambro (Aust) Pty Ltd.
- The
duties of the Caretaker are set out in some detail in the Agreement. Clause 14
of the Agreement deals with the Gardens Maintenance
Policy and that term is
defined with reference to that clause. The clause is in the following
terms:
“14.1 The Caretaker acknowledges that the Common
Property gardens and landscaping are a feature of the Development and will
require a high standard of maintenance and care.
14.2 The Body Corporate Committee shall, upon consultation with a
landscaping consultant set out a list of specific gardening duties
and methods
of maintaining and caring for Common Property gardens, landscaping features and
irrigation. The list shall be set out
in writing and be given to the Caretaker
(“the Gardens Maintenance Policy”).
14.3 The Body Corporate Committee may from time to time upon advice from a
landscaping consultant, amend the Gardens Maintenance Policy.
The Body Corporate
Committee shall act reasonably in amending and compiling the Gardens Maintenance
Policy and the duties imposed
shall be consistent with the Caretaker’s
duties set out in clause 2.
14.4 The Caretaker shall strictly comply with the Gardens Maintenance
Policy and any amendments to the Gardens Maintenance Policy.
14.5 Any amendment of the Gardens Maintenance Policy shall not be an
amendment of this Agreement.”
- A
draft of the Gardens Maintenance Policy was disclosed to prospective purchasers
of lots in the proposed community titles scheme.
However, neither the Applicant
nor the Caretaker were provided with copies of the Gardens Maintenance Policy at
the time the management
rights to the Scheme were acquired back in February
2005.
- There
is nothing before me to establish that the Gardens Maintenance Policy was
formally adopted as required by the Agreement, but
I assume that was done. It is
also relevant to note that the parties to the Agreement have acted in acceptance
of the Gardens Maintenance
Policy. It is also common ground that the Gardens
Maintenance Policy has never been amended.
- Clause
7.1(d) of the Agreement is in the following terms:
‘This
Agreement may be terminated by the Body Corporate delivering a notice in writing
to the Caretaker if:
(a) ....;
(d) the Caretaker is in breach of this Agreement and that breach continues
at the end of thirty (30) days after notice in writing
delivered by the Body
Corporate to the Caretaker requiring that breach to be remedied.’
Letting Agreement
- The
Body Corporate also entered into a Letting Agreement with THL Robina Pty
Ltd dated 16 August 2004. (‘Letting Agreement’) for a
period of 25 years from 10 August 2004. In the Letting Agreement THL
Robina Pty Ltd is referred to as the “Letting
Agent”.
- The
Letting Agreement was also the subject of the assignment to Ambro (Aust) Pty Ltd
that I previously referred to.
- Clause
7(a)(iv) of the Letting Agreement provides as follows:
‘(a) This agreement may be terminated by the Body
Corporate delivering a notice in writing to the Letting Agent if:
(i) ....
(iv) the Letting Agent is in breach of this Agreement and that breach
continues at the end of thirty (30) days after notice in writing
delivered by
the Body Corporate to the Letting Agent requiring that breach to be
remedied.’
- I
addition, clause 8 of the Letting Agreement provides as
follows:
“The Letting Agent has entered into a Caretaking
Agreement with the Body Corporate contemporaneously with entering into this
agreement. The parties acknowledge that:-
(i) A default under the Caretaking Agreement shall constitute a default
under this agreement and vice versa; and
(ii) Upon the expiration or termination of the Caretaking Agreement, this
Agreement shall expire or terminate on the same date.’
Breakdown of the relationship
- Since
shortly after the Caretaker took the assignment of the Agreement and the Letting
Agreement the body corporate committee became
dissatisfied with the
Caretaker’s performance. This appears to have corresponded with a change
of committee in January 2006,
although nothing turns on this.
- It
is fair to say that, eventually, the relationship between the Caretaker and the
Body Corporate deteriorated to the extent that
the parties were not able to
effectively work together. This was graphically illustrated by the fact that the
Caretaker was, at worst,
excluded from meetings of the Committee, of which it is
a member, and, at best, was generally unwelcome at those meetings.
- The
Committee of the Body Corporate decided to take enforcement action against the
Caretaker.
Remedial Action Notice
- By
letter dated 15 December 2006 from Piper Alderman, Solicitors, acting for the
Body Corporate, to Ambro (Aust) Pty Ltd, 3 notices
were served on Ambro (Aust)
Pty Ltd on behalf of the Body Corporate, namely:
- Notice
under clause 7 of the Caretaking Agreement.
- Notice
under clause 7 of the Letting Agreement.
- Remedial
Action Notice under section 84C (although expressed in the letter to be section
84) of the Body Corporate and Community Management (Accommodation Module)
Regulation (‘Accommodation Module’).
- Service
of these 3 notices appear to have been authorised by the Committee of the Body
Corporate. Under the terms of the Act and
the Accommodation Module, combined
with the provisions of the Agreement, if the Applicant failed to comply with
those notices, then,
subject to certain procedural matters, the Body Corporate
could terminate the Agreement.
- On
13 February 2007 Piper Alderman, on behalf of the Body Corporate,
served a further default notice under clause 7 of the
Caretaking Agreement on
the Applicant. The alleged defaults covered by that notice were substantially
the same as some of the alleged
defaults in the earlier notices.
- The
length and scope of the various notices are extensive and it should not be
necessary for me to set them out in detail. I will
therefore refer only to the
relevant items in the various notices.
Annual General
Meeting
- Following
the break down in the relationships and efforts by the Caretaker to sell its
management rights for the Scheme, the Body
Corporate convened its annual general
meeting to be held on 17 May 2007. The Body Corporate Committee proposed
to that meeting
a motion for an ordinary resolution to be decided by secret
ballot, in the following terms:
‘That except where the
Body Corporate has consented to the proposed assignment of the interest of Ambro
(Aust) Pty Ltd ACN 099 989 358
in the Caretaking Agreement and
Letting Agreement, each dated 16 August 2004, to Investor Property
Management Pty Ltd ACN 120 653
643, and the assignment has been completed
prior to the holding of this Annual General Meeting in accordance with the terms
of consent
of the Body Corporate, that the Body Corporate terminate both the
–
(i) Caretaking Agreement pursuant to clause 7.1 and section 84C of the
Body Corporate and Community Management (Accommodation Module)
Regulation 1997;
and
(ii) Letting Agreement pursuant to clause 7 and section 84 of the Body
Corporate and Community Management (Accommodation Module) Regulation
1997.’
- An
explanatory schedule that accompanied the Notice of Annual Meeting indicated,
inter alia:
At the direction of the Committee, notices have
been issued by the Body Corporate’s solicitors, Piper Alderman, Lawyers,
for
Ambro (Aust) Pty Ltd, in respect of breaches under terms of the Caretaking
Agreement. The notices required these breaches to be
remedied within thirty
days in accordance with the terms of the Caretaking Agreement, and the Body
Corporate and Community Management Act 1997 and Accommodation Module.
The Committee considers that the breaches complained of have not been
rectified by Ambro (Aust) Pty Ltd.’
Interim order
- Before
that motion could be considered by the annual general meeting, the Applicant
made the current application. In the application,
the Applicant sought an
interim order to restrain the Body Corporate from putting that motion to a vote
at the meeting. By interim
order dated 11 May 2007, I so restrained the
Body Corporate.
- Therefore,
in relation to the 4 notices I have referred to, the question is whether the
Body Corporate was, and therefore still is,
entitled to consider the relevant
motion and, if passed, proceed to terminate the Agreement and the Letting
Agreement.
Remedial Action Notice
- The
Remedial Action Notice was served under section 84C of the Accommodation Module.
It alleges that the Applicant:
- Engaged
in misconduct, or was grossly negligent, in failing to carry out functions
required under the Agreement.
- Failed
to carry out duties under the Agreement.
- Contravened
the Code of Conduct for Body Corporate Caretaking Service Contractors.
The notice allowed 30 days from the date of delivery of
the notice for the Applicant to remedy the misconduct or gross negligence,
carry
out the duties and remedy the contravention,
- Section
84C(4)(b) of the Accommodation Module requires a remedal action notice to set
out details of the action sufficient to identify
the misconduct, gross
negligence, duties and Code violations complained of. The process envisaged by
that section is one whereby
a body corporate can bring to the attention of a
non-performing caretaking service contractor misconduct, gross negligence,
failure
to carry out duties or failure to comply with the Code of Conduct. The
caretaking service contractor is then given the opportunity
to remedy the matter
complained of and if they fail to do that, their agreement can be terminated.
- A
remedial action notice must be clear about what is complained of so that the
caretaking service contractor will know what has to
be done to remedy the
complaint. The subject of the complaint must be capable of being remedied. In
the case of failure to carry
out duties, there must be a clearly identifiable
duty that has not been carried out.
- In
the case of the Remedial Action Notice dated 15 December 2006, at a
preliminary meeting of the parties, the Body Corporate
indicated that it would
not be relying upon 7 of some 17 alleged issues in the notice. The 7 that were
not being relied upon were
those in clause 2(b)(iii), (v), (vi), (vii), (viii),
(xii) and (xiii).
- Subsequent
to that meeting I considered the contents of the Commissioner’s file, the
contents of the Remedial Action Notice
and the relevant provisions in the
Agreement. Having done that, I reached one of 2 conclusions in relation to 9 of
the 10 remaining
issues, namely:
- There
were insufficient particulars to enable the Caretaker to understand exactly what
the complaint was and what action was need
to remedy that complaint.
- There
was no duty that required the Caretaker to do what the Body Corporate
required.
- On
the question of particulars, it is relevant to note that in response to the
Remedial Action Notice, the solicitors for the Applicant,
Robinson &
Robinson, made a request to Piper Alderman for further and better particulars.
That request was denied. The basis
of the denial was that the Applicant had
previously been advised and provided with material sufficient to identify the
numerous breaches
and where applicable, the actions required to remedy those
breaches.
- I
do not propose to deal with all 9 issues on which I reached the conclusions I
have referred to. However, I will provide examples,
the first being the alleged
breach of duty in clause 2(b)(ii) of the Remedial Action Notice, which is in the
following terms:
“2 Details of the action sufficient to
identify the items in 1(a), 1(b) and 1(c) herein are as follows:
- .....
- The
Body Corporate believes you are in breach of the Agreement due to
the:
- (i) ....
- (ii) Failure
to administer the Common Property to ensure it is able to be used and enjoyed by
the Occupiers and is properly maintained
and kept in good repair. (cl
2.1)”
The items in “1(a), 1(b) and
1(c)” are the items set out in paragraph 25 above.
- There
are insufficient details in that item to allow the Caretaker to understand what
duties have not been carried out. The Caretaker
could not reasonably be expected
to remedy that alleged breach of duty. Furthermore, referring the Caretaker to
advice and materials
previously provided, when there had been numerous instances
of advice and quantities of materials provided in previous months, does
not do
anything to assist the Caretaker.
- The
second example concerns the swimming pool. Clause 2(a)(i) of the Remedial Action
Notice provides the following particulars:
“2 Details of
the action sufficient to identify the items in 1(a), 1(b) and 1(c) herein are as
follows:
- (i) Failure
to comply with clauses 2.1(a)(viii), 2.1(m) and 2.1(o) of the Agreement, and
disregard of the Queensland Health Swimming
and Spa Pool Water Quality and
Operational Guidelines issued by Queensland Government (“the
Guidelines”):
Failure to implement a strategy for the
clenliness and safety of the pool facilities including the keeping of a log of
water testing
and chemical balance and/or chemical additives, you have failed to
incorporate the keeping of a log as part of your caretaking duties
concerning
the pool facilities. In addition, you have communicated your intention to not
regard or have reference to the Guidelines
or Council’s Local Law No 31
– Swimming Pools. You will not comply with this reasonable direction of
the committee.
Accordingly, there are no records available to the Body Corporate
concerning the maintenance of the pool facilities. There is potential
risk to
health of all individuals including lot owners and occupiers and guests, as a
result of your failure to adhere to the Guidelines,
and breach of the
Agreement.”
- Clause
2.1(a)(viii) of the Agreement is in the following
terms:
“2.1 The Caretaker shall administer the Common
Property to ensure the Common Property is able to be fully used and enjoyed by
the Occupiers and is properly maintained and kept in good repair and the
Caretaker shall attend to the following:
(a) As reasonably required:
(i) ....
(viii) maintain and clean the swimming pool(s), fountains, water features,
spas and steam room;”
- Clause
2.1(m) imposes a duty on the Caretaker to “Monitor and administer the
use of all recreation facilities including any swimming pool ...” .
Clause 2.1(o) requires the Caretaker to carry out “the additional
duties specified in Schedule 1 ...” but the Schedule simply says
“Any duties agreed to by the Caretaker and the Body Corporate and
evidenced in writing.” There is no evidence that there are any such
agreed duties.
- The
allegations do not suggest that the pool is not being cleaned. The allegations
are:
- disregard
of the Guidelines;
- failure
to implement a strategy for the cleanliness and safety of the pool facilities as
recommended by the Guidelines;
- failure
to keep a log;
- failure
to comply with a reasonable direction of the committee; and
- a
communicated intention not to comply with the Guidelines and Local Law
31.
The dispute in this respect is therefore one of
standards rather than outright default.
- The
difficulty with this allegation is that there is noting in any of the duties
cited by the notice that actually requires the Caretaker
to do what is being
asked of it. They may be things that the Body Corporate would like to see done,
but they are not things that
the Caretaker is obliged to do. They cannot simply
be imposed on the Caretaker.
- If
the Guidelines amounted to a legal obligation on the Body Corporate, then the
Caretaker’s position may not be so straight
forward. But the Guidelines
themselves make it clear that they do not apply to the Scheme’s swimming
pool.
- My
review concluded that there was only one item that may have been adequately
particularised in the remedial action notice, namely
the item in clause
2(a)(xv). That item related to an alleged failure on the part of the Applicant
to comply with the Gardens Maintenance
Policy. In my review, I did not feel
that I was able to determine with certainty that there were sufficient
particulars supporting
this item and I elected to receive further evidence and
submissions in relation to this allegation.
- The
difficulty that confronted me was the extent of the allegations of
non-compliance. There were 8 allegations of non-compliance
for this item alone.
The other thing that troubled me was the fact that it was non-compliance with a
Policy that:
- was
formulated after the agreement was entered into;
- that
made reference to and incorporate other documents;
- is
said to be capable of amendment (but not in a way that amends the Agreement);
and
- appeared
to be in conflict with the Agreement.
Gardens
maintenance issues
- At
a second meeting of the parties I examined, with the parties, each of the 8
allegations relating to garden maintenance. I have
since considered each
allegation in detail. In so doing I was mindful that clause 2.1(a)(iv) and (iv)
of the Agreement is in the
following terms:
“2.1 The
Caretaker shall administer the Common Property to ensure the Common Property is
able to be fully used and enjoyed by
the Occupiers and is properly maintained
and kept in good repair and the Caretaker shall attend to the following:
(a) As reasonably required:
(i) ....
(iv) mow the Common Property lawns and trim the edges of the
lawns;
(v) maintain the Common Property lawns, gardens and shrubs, including
watering, fertilizing, weeding, mulching and top dressing according
to the
Gardens Maintenance Policy;”
- There
is a threshold issue of whether the Gardens Maintenance Policy is binding on the
Caretaker. However, assuming that it is use
of the words “as reasonably
required” in clause 2.1(a) effectively means that the Garden Maintenance
Policy may well
specify how things are to be done and what chemicals or
substances are to be used, but it cannot specify how frequently things must
be
done. This is because they need only be done “as reasonably
required”. It follows that the detailed schedule in the
Gardens
Maintenance Policy specifying intervals for certain actions or tasks to occur is
in conflict with the Agreement and unenforceable.
- Having
reached that conclusion, my findings in relation to the 8 alleged breaches are
as follows (without setting out the lengthy
wording of the allegations):
- 1st
dot point – The Caretaker is not under a duty to “implement a
strategy or schedule of frequency of works” and there is insufficient
particulars of the alleged failure to maintain the landscaped areas in
accordance with the Policy.
The allegation is therefore not substantiated.
- 2nd
dot point – There is evidence that the Caretaker failed to replace some
trees that appeared sick or dead. Its failure was not
a total failure. The
Caretaker’s explanations related to the drought and the pointlessness of
replacement; the reduction in
its approved expenditure limit; its exclusions
from Committee meetings and general failure of the committee to work with it in
decision
making about the tree replacements. On balance I think the Caretaker
has a case to answer in relation to this allegation.
- 3rd
dot point – The evidence is that the fertilising did occur in accordance
with the Policy and there is no evidence that the
timing was otherwise than
“as required”. There is no duty requiring the giving of evidence to
the body corporate about
fertiliser used. This allegation is not
substantiated.
- 4th
dot point – The evidence is that the weeding did occur and there is no
clear evidence that it was otherwise than “as
required”. In any
event, it was probably in accordance with the non-binding timings in the Policy.
There is no duty requiring
the giving of any evidence of things to the body
corporate. This allegation is not substantiated.
- 5th
dot point – This allegation is not clear. It appears to require the
Caretaker to provide “a schedule of pruning or garden maintenance
activity”. The Body Corporate says it refers to the pruning and
activity rather than a schedule. In any event, it is not clear and there
are
insufficient particulars. This allegation is not substantiated.
- 6th
dot point – I am not satisfied that there is sufficient evidence to
support this allegation. That is not to say that at times
lawn levels are higher
than normal. Indeed, the Body Corporate produced a number of photographs showing
lawns that needed mowing.
The difficulty is knowing whether this is a regular or
occasional occurrence. The Body Corporate says it is regular but the Caretaker
says the lawns are mown regularly and there are reasons why they are sometimes
overdue for a cut. The general nature of the Body
Corporate’s claims, the
lack of particulars and the difficulty of determining the situation as at the 2
relevant dates, 15
December 2006 and 13 February 2007 adds to the difficulty of
being satisfied that there has been a breach of duty at the relevant
times.
Therefore, on balance, I am not satisfied that this allegation is
substantiated.
- 7th
dot point – The complaint here related to top dressing and aerating the
lawns. The Body Corporate conceded that top dressing
had been done as required.
The Caretaker maintained that aerating has not been required to date and there
is no evidence to the contrary.
The allegation is not substantiated.
- 8th
dot point – the allegations were that the caretaker failed to maintain the
Central Spine Park in accordance with the “maintenance
schedule”;
has not implemented any system of maintenance and failed to provide
documentation evidencing such schedule maintenance.
The Caretaker provided
detailed evidence of a substantial amount of work undertaken in relation to this
Park. It appears to me that
the expectations of the Body Corporate exceed the
obligations of the Caretaker under the Agreement. Apart from that, the
allegation
is not sufficiently particularised and there are no duties relevant
to any system of maintenance or provision of documentation. This
allegation has
not been substantiated.
- The
Code Contravention Notice also alleges breaches of provisions of the Code of
Conduct for Body Corporate Service Contractors; although
it does not expressly
state which Code provisions have been breached. There are 4 allegations in this
regard. For the first allegation
there are no particulars at all; just a general
accusation accompanied by the extraordinary statement that the Caretaker is not
entitled
to remuneration.
- The
second and third allegations also contain no particulars and are broad
statements. The fourth allegation is that the Caretaker
engaged in
“unconscionable conduct” because its employees
“exerted undue influence on or used unfair tactics against the Body
Corporate in the carrying out of duties and obligations under the
Agreement”. No particulars are given.
- I
therefore conclude that the Remedial Action Notice has failed to establish any
breach of the Code of Conduct.
- Apart
from the allegation that the Caretaker failed to replace some of the trees, none
of the other alleged defaults were clearly
established. Even the failure in
relation to the trees was disputed and explained to some extent by the
Caretaker. In my opinion,
this failure in itself does not justify termination of
the Agreement. Also, given the extraordinary number of alleged breaches in
the
notices it would have been very difficult, if not impossible, for the Caretaker
to specifically identify the need for this failure
to be remedied within the 30
day period. It is understandable that the Caretaker was at a total loss to know
what to do in order
to satisfy the various notices.
Breach
Notice
- The
Breach Notice dated 15 December 2006 was served under clause 7.1(d) of the
Agreement. It substantially repeats the alleged
breaches of the Agreement
raised in the Remedial Action Notice. It too required remedy within 30 days of
delivery of the notice.
- Again,
at the preliminary meeting of the parties, the Body Corporate indicated that it
would not be proceeding with items 3, 5, 6,
7, 8, 12 and 13 in the breach
notice. They are the exact same items in the remedial action notice that the
Body Corporate elected
not to proceed with.
- Again,
having examined the items that the Body Corporate wanted to rely upon, I formed
the view that insufficient particulars had
been given in relation to all of
them, with the exception of item 15 which related to the compliance with the
Garden Maintenance
Policy. Again, this was the only allegation that was
potentially effective in the breach notice.
- Because
the Breach Notice is in substantially the same terms as the Remedial Action
Notice, my findings in relation to the Breach
notice are the same as my findings
in relation to the Remedial Action Notice. The obligation to sufficiently
particularise the breaches
complained of applies equally to the Breach Notice.
Letting Agreement Breach Notice
- The
third notice dated 15 December 2006 was served under clause 7(a)(iv) of the
Letting Agreement, alleging that the breach of
the Agreement constituted a
breach of the Letting Agreement and again allowing a period of 30 days of
delivery of the notice to remedy
the breach.
- At
the preliminary meeting, given that there is a clause in the Letting Agreement
providing for it to terminate if the Agreement terminates,
the Body Corporate
indicated that it did not seek to rely upon or continue further with the Letting
Agreement Breach Notice. It
follows that it is not necessary for me to further
consider that notice.
Breach Notice dated 13 February 2007
- The
Breach Notice dated 13 February 2007 was served under clause 7.1(b) of the
Agreement. It effectively complained about three
things:
(1) Failure to maintain the swimming pool to a particular
standard.
(2) The Applicant’s conduct under the Agreement.
(3) Failure to maintain in accordance with the Garden Maintenance Policy.
- It
is fair to say that the allegations in the breach notice dated 13 February
2007 are very similar to the allegations contained
in the earlier notices. At
the preliminary meeting of the parties that I have referred to, the Body
Corporate indicated that it
wished to rely upon all three of those allegations.
Because some of the wording in the latest notice is not identical to the wording
of the earlier notices it is necessary for me to undertake a point by point
analysis of the later notice.
- The
first allegation concerns the swimming pool. The wording is identical with the
corresponding section of the Remedial Action Notice.
Therefore, this allegation
suffers from the same defects and is not substantiated.
- The
second allegation concerns a threatening note to the Body Corporate from an
employee of the Caretaker and the general state of
communications between the
Caretaker and the Body Corporate and the Caretaker’s attitude. The wording
is very general and it
is not clear what is required of the Caretaker to remedy
the allegation. Indeed, it suggests that the state of the relationship is
such
that there is no prospect of remedy. While the allegation suggests that the
Caretaker is solely responsible for the breakdown,
the evidence on the
Commissioner’s file and the evidence of the Caretaker regarding his
exclusion from meetings of the committee
suggests that there is, at the least,
fault on both sides. Apart from lacking in particulars, assuming that the
“complaint”
is well founded, there does not appear to be any
identifiable provision of the Agreement that has been breached.
- The
final allegation concerns the Caretaker’s failure to comply with the
Gardens Maintenance Policy. The wording is different
to the wording in the
Remedial Action Notice, but the substance of the allegation is the same. There
is just a broad allegation that
there has been a failure to comply with the
Policy and this is reflected in the poor state of the common property gardens
and landscaping.
This allegation suffers from the same defects as the previous
allegations.
- I
therefore concluded in relation to the breach notice of 13 February 2007
that it was not a valid notice in accordance with
clause 7.1(b) of the
Agreement.
Summary
- This
has been a difficult matter for everyone concerned and I feel compelled to make
a number of comments in the hope they will assist
the parties in their future
relationship:
- The
expectations of the Body Corporate, through its committee, and the level of
performance of the Caretaker are poles apart.
- There
is evidence that the Caretaker may have underperformed in some areas, but this
may be partly excusable given the approach of
the committee to managing the
relationship with the Caretaker. For example; nothing positive can be gained by
excluding, expressly
or by implication, the Caretaker from meetings of the
committee, particularly when it has a legal entitlement to be represented at
those meetings.
- The
committee seems to be treating the Caretaker as an employee rather than a
contractor. An employee can be directed as to how things
are to be done and what
records are to be kept. A contractor is not subject to the same level of
direction as an employee. The contractor
is left to do the job using its own
resources and in the way it sees fit, provided the terms of the contract are
observed.
- The
Garden Maintenance Policy will always be a problem for a caretaking contractor,
and the Body Corporate. It is unsatisfactory for
the Agreement to incorporate by
reference a Policy that then further incorporates other documents by reference,
such as the Gold
Coast City Council Landscape Strategy. Added to that is the
risk of change to those documents. Furthermore, the Policy is in conflict
with
the Agreement and its contents are such that there will always be room for
argument, particularly where a majority of the common
property is effectively
bushland intended to serve as a flood plain. The parties should seriously look
at refining the requirements
of the Policy (having regard to the level of the
Caretaker’s remuneration) and incorporating them into the Agreement.
- The
committee may well have done its best to deliver the best maintenance outcome
for the lot owners in the Scheme. It has also relied
on legal advice in the way
in which it has dealt with the Caretaker. Despite this the outcomes have not
been good for the Body Corporate.
A new approach is needed by both parties if
the outcomes are to be different in the future.
- The
history of this matter suggests that the Body Corporate’s objectives in
serving the various notices the subject of this
application were more designed
to get rid of the Caretaker than to genuinely seek rectification of defaults on
the part of the Caretaker.
Had it taken a less extreme approach and focused on
specific defaults, properly particularised, the results may have been totally
different. Either the Caretaker would have rectified the defaults or the Body
Corporate would have been well positioned to terminate
the Agreement.
Costs
- The
Applicant’s solicitor has submitted that costs should follow the event. He
has also submitted that because of the Body Corporate’s
failure to
particularise the breaches in its notices and its subsequent refusal to provide
such particulars, it should effectively
be penalised by being required to pay
the Applicant’s costs.
- My
power to award costs comes from section 280(2) of the Act. That sub-section
provides that the applicant is responsible for “the costs of the
adjudication” unless the adjudicator otherwise orders. The costs of
the adjudication are my fees and expenses and do not extend to the costs
incurred by the parties.
- A
specialist adjudicator usually takes a number of things into account when
deciding whether or not to award costs. The result is
clearly one of those
things. The conduct of the parties is another important matter that needs to be
considered. In this case I think
it is appropriate for the Body Corporate to pay
the costs of the adjudication given the result of the application and the
failure
of the Body Corporate to provide particulars and genuinely seek remedy
of breaches that may have existed.
- It
may be arguable that I can order other types of costs, but I am not inclined to
do that even if I had the power to. My order relating
to costs will therefore be
confined to the costs of the adjudication.
G F Bugden OAM
Specialist Adjudicator
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2007/685.html