You are here:
AustLII >>
Databases >>
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders >>
2007 >>
[2007] QBCCMCmr 683
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Help]
Heritage Village Ormiston West [2007] QBCCMCmr 683 (25 September 2007)
Last Updated: 13 October 2008
Office of the Commissioner for Body Corporate and
Community Management
SPECIALIST ADJUDICATION
(Caretaking Contractual
Matter)
Number: 0274A-2007
Applicant: FIRST RESPONSE MAINTENANCE PTY
LTD Respondent: BODY CORPORATE FOR HERITAGE VILLAGE ORMISTON
WEST COMMUNITY TITLES SCHEME 19720
|
INTERIM ORDER
30 April 2007
ORDER under section 279(1) of the Body Corporate and Community
Management Act 1997 that the Respondent refrain from taking any further
action in reliance on either or both of the Notices of Breach of Caretaking
Agreement,
each dated 14 March 2007, until such time as this order expires or
the application on which this order is made is finally determined,
whichever
first occurs. FURTHER ORDER that the applicant be granted leave to
seek further interim orders on the application should the need arise.
|
Gary Bugden OAM
Specialist Adjudicator
Office of the Commissioner for Body Corporate and
Community Management
SPECIALIST ADJUDICATION
(Caretaking Contractual
Matter)
Number: 0274A-2007
Applicant: FIRST RESPONSE MAINTENANCE PTY LTD
Respondent: BODY CORPORATE FOR HERITAGE VILLAGE ORMISTON WEST
COMMUNITY TITLES SCHEME 19720
INTERIM DETERMINATION
30 April 2007
- This
application relates to a dispute between a Caretaking Service Contractor (the
applicant), which is also a Letting Agent, within
the meaning of the Body
Corporate and Community Management Act 1997 (“Act”) and a
community title body corporate (the respondent). The application was made under
section 238(1) of the Act and referred
by the Commissioner for specialist
adjudication pursuant to section 265(1) of the Act.
- The
application seeks both interim and permanent relief and it has been referred to
me at this stage so that I can consider whether
an interim order should be made
pending the processing of the application and its final referral and
determination.
- The
applicant is “the Manager”, by assignment, under a Management and
Letting Agreement dated 17 May 1993, which was varied
by Deed on 2 October 1998
(“Agreement”). The Second Schedule of the Agreement, as
amended by clause 3 of the variation Deed, sets out the duties of the Applicant.
The applicant also has a similar role in an adjoining community title scheme,
Heritage Village Ormiston East.
- If
the Manager fails to perform its duties under the Agreement provision is made in
the Agreement for either immediate termination,
or termination after failure by
the Manager to rectify a notified breach, depending upon the seriousness of the
breach.
- Section
118(1)(b) of the Act provides that a code of conduct set out in Schedule 2 of
the Act applies to “a caretaking service contractor in performing
obligations under the person’s engagement as a service
contractor”. That code contains a number of obligations and
prohibitions, many of which are very general in nature. If there is a breach
of
the code and the body corporate is required by an ordinary resolution of a
general meeting, decided by secret ballot, to give
the letting agent a
“code contravention notice”, then the body corporate must give that
notice.
- If
the letting agent does not comply with that notice, or further contravention of
the code occurs in certain circumstances, then
the body corporate can give a
“transfer notice”. A transfer notice effectively requires the
letting agent to transfer
their “management rights” within a stated
period to an unrelated third party. This is effectively a forced sale of the
management rights to a new manager who the body corporate has the right to
approve, within certain guidelines.
- In
this case the body corporate purportedly passed an ordinary resolution by secret
ballot on 18 September 2006 authorizing service
of both a code contravention
notice and a transfer notice. The body corporate then served a code
contravention notice dated 6 October
2006 on the applicant alleging a number of
contraventions of the code of conduct. Shortly after that the body corporate
served a
transfer notice dated 16 November 2006 on the applicant alleging that
the earlier notice had not been complied with as well as continuing
breaches of
the code of conduct.
- On
28 February 2007 Mahoney Lawyers wrote to the body corporate’s solicitors,
Herdlaw Solicitors, disputing the validity of
the 2 notices and responding to
the alleged breaches of the code of conduct. Certain correspondence then passed
between the 2 solicitors
about whether or not the breaches of the code occurred
and whether the notices were valid.
- The
body corporate then served 2 notices of breach of the Agreement pursuant to the
breach procedures in the Agreement; alleging failures
on the part of the
applicant to perform duties in the agreement, one being a failure to follow a
direction to remove watering systems
“from all units in Heritage
Village West” and the other alleging failure to cut certain hedges.
These notices were met by a strong rebuttal from the applicant’s
solicitors, as well as an accusation that the body corporate was effectively
acting in bad faith.
- Because
of the nature of applications for an interim order, neither the body
corporate’s allegations against the applicant,
or the applicant’s
rebuttal of those allegations, have been tested. It is sufficient to say that,
on the papers before me,
the applicant has established a prima facie rebuttal of
the matters on which the various notices were founded. Of course, that does
not
mean that, in due course after the application is fully dealt with, the
applicant’s rebuttal will prevail. But for the
moment the applicant has at
least an arguable case.
- That
brings me to the question whether it is appropriate to make an interim order. If
an interim order is not made the body corporate
may, in reliance on one or both
of the breach notices, move to terminate the Agreement and thus deprive the
applicant of an asset
of considerable value. An interim order would preserve the
status quo while the application is determined. However, it would prevent
the
body corporate moving to terminate the Agreement in circumstances where it might
ultimately be held entitled to terminate it.
The body corporate would therefore
suffer delay if an interim order is made.
- Section
279(1) of the Act says:
“The adjudicator may make an
interim order if satisfied, on reasonable grounds, that an interim order is
necessary because of the nature
or urgency of the circumstances to which the
application relates.”
- I
am satisfied that –
- (a) the
applicant has an arguable case;
- (b) because of
the nature and circumstances to which this application relates; and
- (c) having
regard to the alternate remedy that would otherwise be available to the
applicant (i.e. an action for damages) and the
adequacy of that remedy; and
- (d) in
balancing the rights and interests of the 2 parties,
it is
appropriate for an interim order to be made.
- I
therefore propose to make an interim order to prevent the body corporate from
taking any action pursuant to the 2 notices of breach
it has served on the
applicant pending determination of the application. Given the period for
compliance with the transfer notice
there appears to be no need to include that
notice in the order, but I will grant leave for the matter to be brought back to
me by
the applicant if the need arises for consideration of further interim
orders.
Gary Bugden OAM
Specialist Adjudicator
|
Office of the Commissioner for Body Corporate and
Community Management
SPECIALIST ADJUDICATION (Caretaking Service
Contractor Dispute)
Number: 0274-2007
Applicant: FIRST RESPONSE MAINTENANCE PTY LTD
Respondent: BODY CORPORATE FOR HERITAGE VILLAGE ORMISTON WEST
COMMUNITY TITLES SCHEME 19720
PRELIMINARY DETERMINATION 25 September 2007
|
Application
- This
is an application for resolution of a dispute involving a body corporate and a
caretaking service contractor that must be determined
by specialist adjudication
in accordance with the provisions of section 265 of the Body Corporate and
Community Management Act 1997 (‘Act’). That section,
plus numerous other sections of the Act, was amended by the Body Corporate
and Community Management and Other Legislation Amendment Act 2007
(‘Amendment Act’) which commenced on 1 July 2007.
- Because
this application was made but not disposed of before 1 July 2007, section 359 of
the Act, inserted by the Amending Act, requires
the application to be dealt with
under the Act as if the Amending Act had not been enacted. Therefore,
references in this Preliminary
Determination are references to the provisions of
the Act as they were in effect immediately before 1 July 2007.
The Management Agreement
- On
17 May 1993, the Respondent body corporate (‘Body Corporate’)
entered into a Management and Letting Agreement with GTP Developments Pty Ltd
(‘Agreement’). The Agreement was for a term of 5 years with
two options, each for 10 years. The Agreement was varied by Deed of Variation
dated 2 October 1998 between the Body Corporate and Stewart Daniel McAuslan
and Glenda Irene McAuslan, presumably after an assignment
or assignments that
substituted the McAuslans for GTP Developments Pty Ltd and also after the first
10 year option was exercised.
- Community
Title Scheme 19720 (‘Scheme’) is regulated by the Body
Corporate and Community Management (Standard Module) Regulation 1997
(‘Standard Module’), under which a 25 year agreement,
including options, would not be permitted. However, because the Agreement was
entered
into before commencement of the Act and the Standard Module, the
transitional provisions in section 344 of the Act effectively preserved
the then
existing 25 year term of the Agreement.
- While
there is no direct evidence before me, it appears that the Agreement was further
assigned and the current manager under the
Agreement is the Applicant, First
Response Maintenance Pty Ltd.
Extraordinary general meeting
- On
18 September 2006 an extraordinary general meeting of the Body Corporate
was held. The Body Corporate committee proposed
a motion for an ‘ordinary
resolution’ by secret ballot for consideration by that meeting. That
motion was passed in
the following terms:
‘The Body
Corporate give the Caretakers a signed contravention notice as attached and that
the body corporate may, without further
notice, give the caretakers a transfer
notice if the Caretakers:
(a) do not comply with the contravention notice; or
(b) after having been given the notice, continue to breach a provision of
the code.’
- There
are 48 lots in the Scheme and, according to the Minutes of the extraordinary
general meeting referred to, 39 valid votes were
received in respect of the
motion for ordinary resolution. Of those, 29 were in favour, 8 were against and
2 were abstentions. This
will be relevant to one of the matters that I need to
determine.
Code Contravention Notice
- On
or about 6 October 2006, the Body Corporate’s solicitors, Herd Law,
Solicitors, served a Code Contravention Notice (‘Code
Notice’) on the Applicant under section 139 of the Act. Presumably,
that Code Notice was in the same terms as the notice attached
to the minute of
the ordinary resolution. There is nothing in the Commissioner’s file that
enables me to confirm this.
- The
Code Notice alleged that the Applicants had contravened all 11 rules of the
Code of Conduct for Body Corporate Managers and Caretaking Service
Contractors (‘Code’), as set out in Schedule 2 of the
Act. The alleged contraventions related to:
‘1. Knowledge
of Act, include code.
2. Honesty, fairness and professionalism.
3. Skill, care and diligence.
4. Acting in the Body Corporate’s best interests.
5. Keeping the Body Corporate informed of developments.
6. Ensuring employees comply with Act and code.
7. Fraudulent or misleading conduct.
8. Unconscionable conduct.
9. Conflict of duty or interest.
10. Goods and services to be supplied at competitive prices.
- Body
Corporate Manager to demonstrate keeping of particular records.
‘
Transfer Notice
- Subsequently,
on or about 16 November 2006, after expiry of the time allowed in the Code
Notice for remedial action, the Body
Corporate’s solicitors served a
Transfer Notice (‘Transfer Notice’) under section 140 of the
Act and section 86C of the Standard Module. The inclusion of the reference to
section 86C is confusing,
because this effectively meant that the Transfer
Notice sough to achieve two contradictory things; the first a transfer of the
Agreement
and the second, termination of the agreement. However, in the event,
nothing turns upon this.
- The
Transfer Notice alleged that the remedial action had not been carried out by the
Applicant, or carried out in a way to the Body
Corporate’s satisfaction,
and that the Applicant continued to breach provisions of the Code. The Transfer
Notice particularised
those continuing breaches as:
‘(a) Not exercising reasonable care, skill, and diligence
in performing the person’s functions under the person’s
engagement;
(b) Not acting in the Body Corporate’s best interests;
(c) Continuing to act in a confrontational and disagreeable way and not in
the spirit of the engagement; and
(d) The following specific actions:
(i) Not attending to hedges evenly throughout the Scheme;
(ii) Not watering in fertiliser;
(iii) Attending to common property gardens in a haphazard way;
(iv) Not attending to overgrown shrubs that were blocking safe access out
of driveways;
(v) Carelessly and recklessly poisoning plants;
(vi) Not putting out all Recycle bins, owners have to do this when one or
two have been left; and
(vii) Not communicating with the Body Corporate delegate.’
- On
28 February 2007, Mahoney Lawyers, on behalf of the Applicant, wrote to the Body
Corporate’s solicitors alleging a number
of things, including:
- (a) the Code
Notice did not comply with the Act;
- (b) the
Transfer Notice was not supported by a valid ‘majority resolution’
decided by secret ballot;
- (c) the
Transfer Notice introduced material not covered in the Code Notice;
- (d) the
Transfer Notice had ‘absolutely no effect whatsoever’;
- (e) the
allegations in the Code Notice concerned very minor matters, or matters clearly
outside the Applicant’s duties under
the Agreement (supported by a
detailed response in respect of each allegation in the Code Notice).
- This
letter was followed by further exchanges of letters between the two solicitors,
the details of which it is not necessary for
me to go into at this
stage.
Breach Notices
- On
or about 14 March 2007 the Body Corporate’s solicitors served two
breach notices (‘Breach Notices’) under clause 12.3 of the
Agreement. The first notice specified certain duties set out in the Second
Schedule of the Agreement,
relating to:
- (a) keeping the
common property in good order and repair;
- (b) keeping
order on the property; and
- (c) performing
such other acts and things as are reasonably necessary and proper in the
discharge of duties under the Agreement, including
any additional duties or
responsibilities that may be referred by the owner to the manger.
- The
first notice required the manager to ‘comply with the requirements of
the Second Schedule Manager Duties as specified in the Management Agreement
within 14 days of receipt
of this notice’.
-
The second notice referred to items (a) and (c) mentioned above, and in
addition, the trimming of hedges on a monthly basis. The
second notice again
required compliance with ‘the requirements of the Second Schedule
Manager’s Duties as specified in the Management Agreement within 21 days
of receipt
of this notice.’
Directions
meeting
- The
general nature of many of the particulars given in the Code Notice suggests that
the notice may have been in the nature of an
‘ambit claim’, but when
given the opportunity at a directions meeting on 8 August 2007 to elect
which items were
to be relied upon, the Body Corporate’s solicitors
indicated that the Body Corporate intended to rely upon all items.
- At
that meeting I indicated that it would be necessary for me to examine each item
of alleged contravention in order to decide whether
the Code Notice was well
founded and whether the Applicant had remedied any of the established
contraventions prior to service of
the Transfer Notice. There was also
discussion at that meeting about:
- (a) whether the
Transfer Notice was supported by the required ‘majority
resolution’;
- (b) whether
orders in strict terms of the orders sought by the Applicant will achieve what
the Applicant is seeking to achieve, namely
preventing the Body Corporate from
enforcing the Transfer Notice and/or Breach Notices; and
- (c) if not,
whether I can make orders other than in the strict terms sought by the
Applicant.
- I
set aside two days for further meetings to investigate the contraventions
alleged in the Code Notice and indicated that at the commencement
of the first
meeting I would consider any written submissions the parties may wish to make on
the question of what orders I have
power to make on the application.
- Before
those further meetings were due to be held, I received a telephone call from the
Applicant’s solicitor asking whether,
to save costs for both parties, it
would be preferable if I determined the preliminary point on permissible orders,
and possibly
the question of whether the Transfer Notice is supported by the
necessary ‘majority resolution’ before the parties prepare
more
detailed evidence and witnesses on the individual contravention allegations.
- I
indicated I would be prepared to do this if the Body Corporate’s solicitor
agreed with the proposal and the Applicant’s
solicitors were requested to
inquire regarding that agreement. I indicated that upon receiving confirmation
from the Body Corporate’s
solicitors I would vacate the meeting dates.
- As
things turned out, the communications between the solicitors were not the most
satisfactory and the Body Corporate’s solicitors
took exception to those
discussions in their absence. Progress of the matter was temporarily delayed as
a result. However, the
issues arising were resolved in a telephone conference
involving the two solicitors and myself and it was agreed that the two
preliminary
legal points should first be resolved and then the meeting should be
held. A timetable was agreed, and subsequently met, for the
written submissions
on the second preliminary legal point, namely:
‘Whether
the resolution of 18 September 2006 was a majority resolution meeting the
requirements of the Act (particularly if the Transfer
Notice of 16 November
includes material that was not in the Code Contravention Notice dated
6 October 2006).
- The
Applicant’s written submission on the second point canvassed issues apart
from the second point. The Body Corporate objected
to this, alleged that this
additional material amount to an amendment of the Application and asked that the
Application be dismissed.
However, in the alternative, the Body Corporate asked
for the Applicant’s submissions to be constrained to the second point.
- It
seemed sensible to me to dispose of all preliminary legal points that can
reasonably be disposed of to limit the provision of evidence
that might
otherwise not be required. Potentially, this could save both parties from
preparation for and attendance at meetings
scheduled over two days. However, I
was not entirely satisfied, in view of the scope of the submissions by the
solicitors for the
Body Corporate, that this would not take the Body
Corporate’s solicitors by surprise. I therefore allowed the Body
Corporate’s
solicitors a further opportunity to respond to the additional
issues raised by the Applicant.
Departure from the orders
sought
- I
am now in a position to determine what I understand are the main preliminary
issues. I will start with the question of the types
of orders that can be made
on the Application. In the Body Corporate’s submission, any departure
from the wording of the outcomes
sought in the Application, or extension of the
issues to include consideration of broader questions of validity not raised in
the
Application, effectively amounts to an amendment of the Application, which
is prohibited at this late stage by section 245 of the
Act.
- On
this point let me start with section 4(h) of the Act which says one of the
secondary objects of the Act is ‘to provide an efficient and effective
dispute resolution process’. Section 239 provides for applications to
the Commissioner for resolution of disputes. It requires, inter alia, an
application
to be in an approved form and to state:
- (a) the
outcomes sought by the application; and
- (b) the
grounds, in detail, on which the outcomes are sought.
- Following
receipt of the application the Commissioner seeks comments from other
stakeholders in the Scheme. These comments are received
by way of formal
submissions which are incorporated in the Commissioner’s file in readiness
for forwarding to the relevant
adjudicator.
- Section
245 of the Act provides:
‘(1) The applicant may, with the
commissioner’s permission, change the application at any time before the
commissioner
makes an initial dispute resolution recommendation under part 5.
(2) The commissioner has discretion to give or withhold permission and, if
the commissioner gives permission, the commissioner may
impose
conditions.’
(I have omitted the footnote and example from the section.)
- Section
269 of the Act then provides:
‘(1) The adjudicator must
investigate the application to decide whether it would be appropriate to make an
order on the application.
(2) When investigating the application, the adjudicator –
(a) must observe natural justice; and
(b) must act as quickly, and with as little formality and technicality, as
is consistent with a fair and proper consideration of the
application; and
(c) is not bound by the rules of evidence.’
- Section
271(1) of the Act then provides:
‘When investigating the
application, the adjudicator may do all or any of the following –
(a) require a party to the application, or someone else the adjudicator
thinks may be able to help resolve issues raised by the application
–
(i) to obtain, and give to the adjudicator, a report or other information;
or
(ii) to be present to be interviewed, after reasonable notice is given of
the time and place of interview; or
(iii) to give information in the form of a statutory declaration;
(b) require a body corporate manager, service contractor or letting agent
who is a party to the application, to give to the adjudicator
a record held by
the person and relating to a dispute about a service provided by the person;
(c) invite persons the adjudicator considers may be able to help resolve
issues raised by the application to make written submissions
to the adjudicator
within a stated time;
(d) inspect, or enter and inspect –
(i) a body corporate asset, or record or other document of the body
corporate; or
(ii) common property (including common property the subject of an
exclusive use by-law); or
(iii) a lot included in the community title scheme concerned.
Example of report for sub-section (1)(a)(i) – Engineering
report’
- Sub-sections
271(3) and (4) confer certain powers of entry on an adjudicator and sub-section
271(5) confers powers for an adjudicator
to compel the production of documents.
- It
is fair to say that the entire process for resolving disputes under
Chapter 5 of the Act is relatively informal. It envisages
that a party in
dispute may act without legal representation. It even allows a party to be
represented by an ‘agent’
who does not need to be a legal
practitioner (refer to section 273 of the Act). It follows that the standard of
applications under
Chapter 5 of the Act will in most cases be relatively low
when compared to more formal jurisdictions. That has certainly been my
experience as a specialist adjudicator in dealing with applications under
Chapter 5 over the past 5 years.
- To
impose strict constraints on the wording of applications, particularly those
parts dealing with outcomes sought and grounds for
those outcomes, would serve
more to frustrate the dispute resolution process rather than ‘to
provide an efficient and effective dispute resolution process’, to
quote the words of section 4(h). Even use of the words “outcomes
sought” in section 239 of the Act, as opposed
to say “orders
sought”, is indicative of an informal and flexible process.
- It
seems to me that the only ‘controls’ over what is intended to be a
very informal process to be quickly undertaken are:
- (a) the
limitation in section 245 of the Act on ‘changes’ to the
application; and
- (b) the
obligation in section 269(2)(a) of the Act for an adjudicator to ‘observe
natural justice’.
- A
specialist adjudicator, when dealing with an application, has a wide discretion
on the information that may be taken into account
and the type of order that can
be made. This discretion must be exercised in the natural justice context and
in recognition of the
fundamentals of the underlying dispute and relief sought.
- In
this case there is a dispute about the Body Corporate’s entitlement to
enforce the Transfer Notice and Breach Notices. There
may be a number of
reasons why the Body Corporate cannot enforce those notices. To my mind, it
would be contrary to the clear intent
of the legislation if I were to restrict
the Applicant to the reasons in the application where another reason sought to
be relied
upon is closely aligned to those reasons. In my view, the test is
whether allowing such additional reasons changes the nature of
the application
so as to significantly lessen the effectiveness and relevance of the submission
process undertaken by the Commissioner,
or so as to deny natural justice to a
party to the dispute.
- The
Applicant is seeking two declarations, the second being to the effect that the
Body Corporate and the committee cannot enforce
the Transfer Notice. The
grounds in the application make reference to ‘attached copies of
correspondence and other documents containing the relevant details, background
and arguments’. One such document is a letter from Mahoney Lawyers to
Herd Law Solicitors dated 28 February 2007 in which the Applicant refers
to
documents that ‘purport’ to be a code contravention notice
and a transfer notice and states the view that the former notice does not comply
with the
requirements of the Act.
- The
Applicant’s submissions essentially address the question of whether the
Code Notice complied with the Act. Those submissions
are therefore in
furtherance of the grounds of the Application and cannot be categorised as an
attempt to amend the application.
The only issue that concerned me was the
departure of the Applicant’s submissions from the issue that was
identified for resolution;
namely the question relating to the resolution of
18 September 2006. I was concerned that, despite the fact that the Body
Corporate’s
solicitors attempted to address the points in its submissions
in reply, they may have been prejudiced by the time constraint on delivery
of
their submission. That time was designed to accommodate the response to a much
narrower issue. To remedy this, I allowed the
Body Corporate’s solicitors
more time to provide a further response on the broader submissions made by the
Applicant’s
solicitors.
- I
therefore propose to consider and deal with the submissions of the
Applicant’s solicitors. Having regard to the reasons I
have already
given, I am satisfied that those submissions do not amount to an amendment of
the application. I am also satisfied
that if I decide to make an order on the
application, I am not confined to the exact wording of the outcome sought in the
Application.
At the very least I can make any order that is consistent with
that outcome or that is necessary as an ancillary or consequential
provision.
- However,
before proceeding I will comment briefly on an objection by the
Respondent’s solicitors to me considering at all the
“additional” matters raised by the Applicant’s solicitors
effectively on the basis that:
- (a) the Body
Corporate has been put to additional costs by these “late”
submissions; and
- (b) these
additional costs will require an extraordinary general meeting to approve
expenditure on legal costs beyond the committee’s
limit.
- In
response I point out that the Applicant in its application has sought general
outcomes to the effect that it is not in breach of
“any law, or the
Management and Letting Agreement” and that the Body Corporate
“cannot enforce the transfer notice” and in its grounds has
referred to the material attached to the application. That material canvassed a
range of reasons why
the outcomes sought should be successful, including the
very questions that I am being asked to decide. My decision to deal with
those
matters now should actually save the Body Corporate costs. If I left those
matters until later, then a good deal of un-necessary
testing of evidence may
have been the result.
- The
course taken by the Body Corporate in relation to the Agreement was bound to
involve the Body Corporate in substantial costs and
any expectation that a
challenge to that course could be met within the committee’s expenditure
limit was, in my view, naive.
The attempts by the solicitors for the Body
Corporate to confine the issues as far as possible are understandable, but those
attempts
have been frustrated by the wide scope of the outcome sought and the
attachment of substantial material to the application.
The Code
Notice, the Transfer Notice and the Act
- I
turn now to the merits of the Applicant’s arguments that the requirements
of the Act were not met in relation to the Transfer
Notice. There are three
limbs to those arguments that can be summarised as follows:
(1) Defects in the Code Notice, on which the Transfer Notice was
based; namely the alleged failure of the Code Notice to:
(a) provide sufficient detail to identify the alleged contraventions; and
(b) state a reasonable (or, in some cases, any) period of time within which
the breaches must be remedied).
(2) Both the Code Notice and the Transfer Notice were authorised by the same
resolution, whereas two separate and distinct types of
resolution are required
by the Act.
(3) Defects in the Transfer Notice; namely it’s reliance on a ground of
default that was not previously alleged in the Code
Notice.
The Code Notice
- I
have already indicated that the Code Notice gives the impression of being an
ambit claim. When one examines the detail given in
relation to the various
alleged contraventions, it is clear that the detail refers to relatively minor
points or to circumstances
that do not necessarily constitute a breach of the
relevant item in the Code. This raises the question whether all or any of those
alleged contraventions have been set out in a way that complies with the
Act.
- Section
139(2) of the Act is relevant and provides:
“The code
contravention notice must state—
(a) that the body corporate believes the person has or is contravening a
provision of the code of conduct for—
(i) letting agents; or
(ii) body corporate managers and caretaking service contractors;
and
(b) the provision the body corporate believes has been or is being
contravened; and
(c) details sufficient to identify the contravention; and
(d) the reasonable period within which the letting agent must remedy the
contravention; and
(e) that the body corporate may, without further notice, give the letting
agent a transfer notice if—
(i) the letting agent does not comply with the code contravention notice;
or
(ii) the body corporate reasonably believes the letting agent, after
being given the notice, has contravened a provision of a code
mentioned in
paragraph (a).”
- The
underlying question is whether section 139 of the Act has to be strictly
complied with by a Body Corporate before a code contravention
notice is valid
and effective. The solicitors for the Applicant submitted that the requirement
for specificity (in terms of identifying
the contravention) is a critically
important one when considering the validity of the notice for a number of
reasons. In particular:
- (a) if a
caretaker does not (or is unable to) comply with a code contravention notice,
the ramifications are extremely serious and
endanger the caretaker’s
entire livelihood;
- (b) vague or
broad allegations of contravention are difficult, if not impossible, to comply
with or remedy;
- (c) the
intention of the legislature in enacting these provisions was to provide a
mechanism whereby:
(i) specific instances of breach could
formally be brought to the caretaker’s attention;
(ii) the caretaker, in the full knowledge of what constituted the breach,
could then take steps to remedy it; and
(iii) if, despite having been appraised of a specific and legitimate breach,
the caretaker failed or refused to remedy it, the Body
Corporate could compel
the transfer of the management rights to another.
- That
submission appears to me to have substantial merit. Given the serious
consequences of non-compliance with a code contravention
notice, it is difficult
to argue that the legislature did not intend that the pre-requisites for a valid
notice should be strictly
complied with. That being the case, it is clearly
arguable that the Code Notice is not in compliance with section 139 and
therefore
is not valid and effective. An examination of each of the alleged
contraventions, including consideration of the time delay between
matters
complained of and the date of service of the Code Notice and its relevance to
the ability of the applicant to rectify, as
well as the strong denials on the
part of the Applicants, will be necessary before I can come to a final view on
the validity of
the Code Notice.
- To
the extent that I am able to undertake that exercise now, I will do so. In this
way the issues to be dealt with as the determination
of the application moves
forward will be further confined. This will result in further cost savings for
the parties. I now turn to
the allegations in the Code Notice.
- The
first allegation is in the following terms:
1. Knowledge of Act,
including code
A body corporate manager of caretaking service contractor must have a good
working knowledge and understanding of this Act, including
this code of conduct,
relevant to the person’s functions.
The Managers, as evidence by their actions as outlined below, are not
familiar with the required conduct pursuant to this code.
- Section
139(2)(c) requiring identification of the contravention has not been complied
with in relation to this allegation. There is
simply insufficient detail. In
addition, the Code Notice does not specify any period in which this alleged
contravention must be
remedied, with the result that section 139(2)(d) has also
not been complied with. This allegation is therefore ineffective.
- The
second allegation is in the following terms:
2. Honesty,
Fairness and Professionalism
- The
Managers have displayed an unprofessional attitude in their correspondence to
the body corporate, and specifically that of 13
February 2006, and June 7 2006.
In said correspondence, referring to the Chairman and body corporate delegate as
Mr R. “Wimpey”
instead of Mr R. Impey illustrates a clear lack of
courtesy, respect and professionalism.
- The
Managers have not been honest or fair in their duty to the body corporate as
evidenced by Mr Barry Neave’s non-disclosure
of his alternative
employment. This has, and continues to cause him to be unavailable to attend to
the body corporate.
- The
Managers persistently display a non-cooperative attitude towards lot owners and
are highly confrontational (Eg. 14 February 2006.
9.20am towards the owner of
Lot 43; letter dated 13th February 2006, admission by
managers to “blowing my stack” in a Committee meeting)
- On
this allegation I reserve my conclusion pending any further evidence the parties
may wish to provide and formal submissions from
the parties.
- The
third allegation is in the following terms:
3. Skill Care and
Diligence
A body corporate manager or caretaking service contractor must exercise
reasonable skill, care and diligence in performing the person’s
functions
under the person’s engagement.
The Managers persistently refuse to water the gardens, the lawns are very
roughly mowed. A report of inspection of the grounds dated
5th May 2006 by the Committee is attached detailing
specific evidence of the lack of skill, care and diligence in the regard,
A further letter from the managers dated 18th
January 2006 states, “We are still learning about herbicides ect”.
This is evident from the fact that they have used
weed spray on quite windy
days.
Item 6 of Minutes of 27 June 2006 refer to a Caretaker removing plants from
lot owner’s garden.
- Given
that the Code Notice was issued in October 2006, these alleged contraventions
are old and there is a question whether they were
appropriate to be raised at
the time the notice was served. There is also a question whether a clear period
for remedy has been specified.
On balance, I reserve my conclusion on this
alleged contravention pending any further evidence the parties may wish to
provide and
formal submissions from the parties.
- The
fourth allegation is in the following terms:
4. Acting in the Body Corporate’s best interests
A body corporate manager or caretaking service contractor must act in the
best interests of the body corporate unless it is unlawful
to do so.
Not attending to duties as requested by the Committee delegate was listed in
the minutes of 27 June 2006
Haranguing behaviour on the 14 February 2006 towards the posting of
committee Meeting Minutes on the Notice Board, which is a requirement
of the
Act s101 and Regulations s28(4)(c).
- The
only period for remedy that could apply to this alleged contravention is the one
expressed in the terms; “The Committee require the managers
unacceptable behaviour as outlined above to cease forthwith.” That is
probably neither adequate nor reasonable. In any event the 2 alleged
contraventions do not amount to a failure to
act in the Body Corporate’s
best interests within the meaning of the item. This allegation is therefore
ineffective.
- The
fifth allegation is in the following terms:
5. Keeping body
corporate informed of developments
A body corporate manager or caretaking service contractor must keep the
body corporate informed of any significant development or
issue about an
activity performed for the body corporate
The Managers are regularly unavailable, particularly during holiday times
and specifically during the Christmas period of 2005.
- Section
139(2)(c) has not been complied with in that the contravention has not been
sufficiently identified. Again, the only period
for remedy that could apply to
this alleged contravention is the one expressed in the above general terms. That
is probably not adequate,
but in any event is unreasonable. Therefore, in
addition, the Code Notice does not specify a reasonable period in which this
alleged
contravention must be remedied, with the result that section 139(2)(d)
has also not been complied with. This allegation is therefore
ineffective.
- The
sixth allegation is in the following terms:
6. Ensuring
employees comply with Act and Code
A body corporate manager or caretaking service contractor must take
reasonable steps to ensure an employee of the person complies
with this Act,
including this code, in performing the person’s functions under the
person’s engagement.
What a relief caretaker has been in place during holiday periods, albeit
without the prior knowledge or acceptance of the Committee,
it is evident that
the relied caretaker as employee of the Managers has not been aware of the
required duties under the contract
and under the Code
- Section
139(2)(c) has not been complied with in that the contravention has not been
sufficiently identified. Again, the only period
for remedy that could apply to
this alleged contravention is the one expressed in general terms. Again, that is
neither adequate
nor reasonable, with the result that section 139(2)(d) has also
not been complied with. This allegation is therefore ineffective.
- The
seventh allegation is in the following terms:
7.
Fraudulent or misleading conduct
A body corporate manager or caretaking service contractor must not engage
in fraudulent or misleading conduct in performing this
person’s
functions under the person’s engagement
On the 23rd February 2006 the managers did send a
letter addressed to property owners and residents. This letter fraudulently
misrepresented
the intent of the body corporate committee meeting and was
misleading in content.
The letter fraudulently characterised specific services as
‘free’ and also purported to offer legal advice to property
owners
and residents I n defining their property boundaries.
- I
do not accept that this conduct, if it did occur, was fraudulent and to the
extent it may have been misleading and not waived by
the Body Corporate, I do
not accept that it is misleading within the meaning of this item of the Code.
There is also an issue about
whether a reasonable time for remedy was allowed.
This allegation is therefore ineffective.
- The
eighth allegation is in the following terms:
8. Unconscionable
Conduct
A body corporate manager or caretaking service contractor must not engage
in unconscionable conduct in performing the person’s
functions under the
person’s engagement
The managers assert that they are not responsible for certain duties or
areas common property. The managers in doing so are requiring
the body
corporate to comply with conditions that are unlawful or not reasonably
necessary.
The managers in a letter to the Secretary dated 1 August 2006, state that
their only duties are in writing as laid out in the second
schedule of their
contract. They include a copy in writing which clearly states at 1.1.12
that,
“to perform such other acts and things as are reasonably
necessary and proper in the discharge of its duties under this
Agreement
including any additional duties or responsibilities that may be referred to
the manager by the owner.”
The managers refuse to empty green waste bins on common property and
have been found trying to relocate a bin from the scheme. They
state that one
of the green recycling bins does not belong to the body corporate when records
shows clearly to bins were purchased.
The managers state in a letter received 7 June 2006 that they have asked
the committee to ‘remove lower limbs on the easement
trees to provide a
safe working environment for us’.
The nature of the confrontational correspondence from the Managers, and
their demeanour, is indicative of exerting undue influence
on, or using unfair
tactics against, the body corporate or owners in the scheme many of who are
elderly.
- I
do not accept that the conduct complained of, if in fact it did occur,
constitutes “unconscionable conduct in performing the person’s
functions under the person’s engagement” within the meaning of
this particular provision of the Code. There is also an issue about whether a
reasonable time was allowed
for remedy. This allegation is therefore
ineffective.
- The
ninth allegation is in the following terms:
9. Conflict of duty
or interest
A body corporate manager or caretaking service contractor for a community
titles scheme if doing so will place the person’s
duty or interests for
the first scheme in conflict with the person’s duty or interests for the
other scheme.
The poor standard or performance is considered as partly attributable to
the Managers concurrent contracts with Heritage Village
Ormiston West CTS
19720 and Heritage Village Ormiston East 20152.
In addition, the Manager Mr Barry Neave has additional employment outside
the scheme and is rarely seen to be working in the scheme.
This leaves most of
the work to be done by Brenda Neave.
- It
is clear from the Commissioner’s file that these circumstances were known
to the Body Corporate when it consented to the
transfer of the Agreement to the
Applicant. This item of the Code speaks prospectively and not retrospectively.
Therefore an existing
commitment, particularly if known to a body corporate,
will not constitute a breach. This allegation is therefore ineffective.
- The
tenth allegation is in the following terms:
10. Goods and
services to be supplied at competitive prices
A body corporate manager or caretaking service contractor must take
reasonable steps to ensure goods and services the person obtains
for or
supplies to the body corporate are obtained or supplied at competitive
prices
It is noted that consultation with the committee on the purchase price of
goods and supplies minimal.
- This
alleged contravention has not been particularised. The mere fact that there has
been no consultation does not lead to the conclusion
that goods or services
acquired were not acquired at competitive prices. In addition, the Code Notice
does not clearly specify a
reasonable period in which this alleged contravention
must be remedied, with the result that section 139(2) (d) has also not been
complied with. This allegation is therefore ineffective
- The
eleventh and final allegation is in the following terms:
11.
Body Corporate Manager to demonstrate keeping of particular records
If a body corporate or its committee requests in writing, the body corporate
manager to show that the manager has kept the body
corporate records as
required under this Act, the manager must comply with the request within the
reasonable period stated in the
request.
- This
allegation is puzzling to say the least. First, the Applicant is not a body
corporate manager within the meaning of the Act,
so the item does not apply to
it. Second, no particulars of the alleged breach are given. Third, no clear time
for remedy is specified.
Therefore, on every account this alleged breach fails
to meet the requirements of the Act and is therefore ineffective.
- The
net effect of the examination just undertaken is to eliminate 9 of the 11
allegations in the Code Notice. Only the allegations
in relation to items 2 and
3 potentially have merit and these must now be addressed by the parties as the
determination of the application
continues.
The Transfer
Notice
- Because
the Code Notice has not totally failed, I cannot at this stage rule out the
Transfer Notice on the basis that it relies upon
a totally ineffective Code
Notice. It is therefore necessary to proceed to examine the Applicants
solicitor’s argument that
both the Code Notice and Transfer Notice were
authorised by the same resolution, whereas two separate and distinct types of
resolutions
are required by the Act.
- On
this point, section 139 requires a code contravention notice to be authorised by
an ordinary resolution decided by secret ballot.
An ordinary resolution is
effectively a simple majority resolution of those voting on the motion. Section
140 of the Act requires
a transfer notice to be approved by a majority
resolution decided by secret ballot. A majority resolution is one where the
votes
counted in favour of the motion are more than 50% of the lots for which
persons are entitled to vote on the motion (vide section
107 of the Act). A
majority resolution is clearly more difficult to get than an ordinary
resolution. However, if one applies the
formula for a majority resolution,
then, in the absence of other formalities, the requisite 50% majority was
achieved at the extraordinary
general meeting of 18 September 2006. The
question is whether this allows one to consider the resolution to be a majority
resolution
or whether a separate resolution is necessary for the purposes of
section 140 of the Act.
- Section
42A(4)(b) of the Standard Module requires a voting paper (being a paper that
must accompany the notice of a general meeting)
to state for each motion whether
a resolution without dissent, special resolution, majority resolution or
ordinary resolution is
required. The minutes of the resolution of
18 September 2006 clearly shows that the motion for the resolution was
submitted
by the Committee and that the resolution required was an ordinary
resolution. Presumably, the notice of meeting and the voting paper
also
indicated to that effect.
- That
being the case, it would not be possible for the resolution once passed to
qualify as both an ordinary resolution and a majority
resolution. This is an
important conclusion because the repeal of a particular type of resolution
requires a resolution of the same
type (see section 58 of the Standard Module).
Therefore, it seems inconceivable if a motion is designated on a voting paper as
being
a motion for an ordinary resolution, yet it is passed by the meeting
without any dissent, that the motion can then qualify as a resolution
without
dissent with the consequence that it can only be amended or revoked by a
resolution without dissent.
- It
follows, in my view that the resolution passed on 18 September 2006, while
adequate to authorise service of the Code Notice,
was not effective to authorise
service of the Transfer Notice. This means that the Transfer Notice is not
valid and effective.
- This
conclusion is supported by the provisions of section 138 of the Act which sets
out two pre-requisites, one of which must be satisfied
before a body corporate
can require the transfer of the letting agent’s management rights. Those
pre-requisites are:
‘(a) the letting agent failed to
comply with the code contravention notice;
(b) the body corporate reasonably believes the letting agent, after being
given the notice, contravened a provision of the Code of
Conduct for
–
(i) letting agents; or
(ii) body corporate managers and caretaking service contractors.’
- As
mentioned, those two circumstances are in the alternative. However, each of
them clearly arises after service of the Code Notice.
They also arise after the
passing of the necessary resolution to authorise service of the Code Notice.
Therefore, in my view it
cannot be successfully argued that the one resolution
can support service of both notices. The sequence required is clear:
(1) There must be a resolution authorising service of the Code
Notice.
(2) There must then be a failure to comply with the Code Notice, or the Body
Corporate must have the necessary belief required by
section 138(b).
(3) There must be a majority resolution authorising service of the Transfer
Notice.
- That
sequence was not satisfied in the case of the Respondent and this is further
support for the proposition that the Transfer Notice
is not valid and effective.
Having reached those conclusions, I am now in a position to make an order along
the lines of the second
outcome sought by the Applicant. The order I propose to
make in due course will not be in exactly the same terms as the outcome
sought,
but will achieve the same result.
Default Notices
- As
I have already indicated, it remains to be seen whether the Default Notices are
effective and, if so, whether they were complied
with by the Applicant. They
are relevant to the outcome sought in that the first outcome sought in the
application effectively requires
a declaration that the Applicant is not in
breach of the Agreement such that the Body Corporate or the committee can
terminate that
agreement. It follows that this is also a matter that still
needs to be determined in relation to the application.
- It
is not necessary for me to determine the third limb of the Applicant’s
solicitors’ arguments given the conclusions
that I have already reached in
relation to the Transfer Notice.
Costs
- The
question of costs is reserved until the remaining aspects of the application are
dealt with.
|
To summarise
- The
following matters still need to be addressed before the application can be
finally determined:
- (a) whether
items 2 and 3 in the Code Notice are valid and effective and, if so, whether
they were complied with by the Applicant;
and
- (b) whether the
Breach Notices are valid and effective and, if so, whether they were complied
with by the Applicant.
- It
is a matter for the parties whether they require a further meeting to provide
verbal or other evidence, plus submissions, in relation
to those outstanding
matters, or whether they are prepared to have the issues determined on the
papers, with or without written submissions.
|

G F Bugden OAM
Specialist Adjudicator
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2007/683.html