![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 14 November 2007
REFERENCE: 0142-2007
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
30273
|
|
Name of Scheme:
|
Rampage
|
|
Address of Scheme:
|
Raggamuffin Drive Coomera Waters Qld 4209
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Body Corporate for Rampage
|
I hereby order that, within fourteen (14) days of the date of this
order, the Owner of Lot 155 must ensure that any building material left in the
front yard of Lot 155, including bricks and black plastic, is removed or is no
longer visible from other lots or common property.
I further order that the application is otherwise dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0142-2007
"Rampage" CTS 30273
The Rampage community titles scheme (Rampage) consists of 81 lots
and common property. The community management statement (CMS) for
Rampage indicates that the Body Corporate and Community Management (Standard
Module) Regulation 1997 (Standard Module) applies to the scheme.
Department of Natural Resources and Water records show the scheme is registered
as Survey Plan 144798, 144801
and 144803.
APPLICATION
Pursuant to the Body Corporate and
Community Management Act 1997 (Act), this application was made by the
Body Corporate for Rampage on 19 February 2007, pursuant to a committee
resolution on 29 November
2006. The applicant sought orders against Jacqueline
Forest, owner of Lot 155 (respondent) in the following terms:
1. A drive way of the approved finish be installed completed as per architectural code
2. Approved landscaping be completed as per architectural code
3. Approved window coverings be installed as per by-laws
PROCEDURAL MATTERS
In February 2007 the
Commissioner’s Office attempted to organise a conciliation session to
assist in the resolution of this
dispute. Unfortunately conciliation did not
proceed.
Under section 243 of the Act, a copy of the application was provided to the respondents and all owners with an invitation to respond to the matters raised in the application. A submission was made by the respondent. The applicant did not avail themselves of the opportunity to inspect the submission received and make a written reply.[1]
A dispute resolution recommendation was made referring the dispute to departmental adjudication.
MATTERS IN
DISPUTE
The application relates to the respondents’ compliance
with the by-laws and the Architectural and Landscape Code (the Code) for
the scheme. The application said the respondent had a plain concrete driveway
which is not a finish permitted under the Code
(item 8.6(e) and (f)), that the
landscaping was incomplete (item 4.2 of the Code) and that the current window
coverings (blankets
and sheets) are not compliant with the Code (By-laws 9.2 and
9.3).
The Body Corporate wrote to the respondent on 10 December 2006
regarding these issues and requesting attention to the matters within
14 days.
On 25 January 2007 the Body Corporate issued a Notice of Continuing
Contravention of a Body Corporate
By-law[2] in respect of each issue.
These notices requested action within seven days. The application was then
lodged.
The respondent made a submission requesting an extension of time
to complete the required works. They said (at April 2007) that the
garden beds
and retaining walls were nearly complete. They said that the driveway was
delayed due to the quality of a delivery of
stone, bad weather and the Easter
holidays. They estimated the work would be completed by 19 May 2007. The Body
Corporate agreed
to grant an extension and indicated they would review the
matter on 30 May.
On 31 May the respondent wrote indicating that every
attempt was being made to complete the work but further issues with stone
quality
and weather had delayed it. The Body Corporate then requested the
application be held in abeyance on the basis that the work was
nearly complete.
On 18 September 2007 the Body Corporate advised that the driveway was
completed, but the landscaping and window finishes were not
complete. They also
noted that there was a lot of building material on site, including a cement
mixer. Accordingly they withdrew
the first order regarding the driveway and
asked to proceed with the remaining two orders.
I sought clarification
of the outstanding issues and the Body Corporate response included that:
Lot 155 had been occupied for at least 18 months; The landscaping should have been completed within 3 months of occupation or completion; The lawn was not completed to the footpath and the building equipment was unsightly; All windows facing the road had sheets, but they are unsure as to the rear windows; and No application had been made directly to the Body Corporate for window coverings, but the Body Corporate does not have access to any applications to the original Architectural Review Committee as that architectural firm no longer acts for the Body Corporate or the developer.
I then invited the respondent to
this information. The respondent advised that:
All lawns have now been completed; All windows facing the road have now been fitted with blinds; A west facing door will be fitted with coverings as soon as possible, subject to their budget; They choose not to have coverings on the windows and doors at the rear of the property as they extend the view and there are no adjoining properties at the rear of the house; and They will be applying for relaxation not to erect a back fence because this would require removal of trees which would detract from the landscaping and devalue the property. They were advised that Amy Degenhart that she did not consider this to be a problem.
In response the Body Corporate advised
that:
They wanted the window coverings on the west facing door completed within 14 days or the sheets removed; The Body Corporate accepts that it cannot insist on window coverings in the other windows; While the cement mixer has been moved, black plastic and bricks remain and the Body Corporate want these removed within 14 days; and The respondent must apply to the Architectural Review Committee, care of Think Tank Architects (07 3348 3727) within 14 days to pursue any relaxation regarding the rear fence. They note that Amy Degenhart of Design Forum Architects is no longer engaged on behalf of the Coomera Waters bodies corporate.
JURISDICTION
I am satisfied that
this is a matter which falls within the legislative dispute resolution
provisions.[3]
Section
276(1) of the Act provides that an adjudicator may make an order that is
just and equitable in the circumstances (including a declaratory
order) to
resolve a dispute, in the context of a community titles scheme, about: a claimed
or anticipated contravention of the Act
or CMS; or the exercise of rights or
powers, or the performance of duties, under the Act or the CMS; or a claimed or
anticipated
contractual matter about the engagement of a person as a body
corporate manager or service contractor; or the authorisation of a
person as a
letting agent.
An order may require a person to act, or prohibit a person
from acting, in a way stated in the order (section 276(2)). An
adjudicator's order may contain ancillary and consequential provisions the
adjudicator considers necessary or appropriate (section
284(1)).
DETERMINATION
The remaining issues in this
dispute are whether the landscaping of Lot 155 has been completed in accordance
with the Code and whether
the window coverings in the lot comply with the
by-laws.
The Code and the by-laws
The CMS for a scheme must
state certain matters, including by-laws, and may include anything that the
regulation module says it may
include.[4] Section 6(b) of
the Standard Module provides that a CMS may include "provisions adopting and
regulating the operation of an architectural and landscape code, including the
establishment and operation
of an architectural review
committee".
By-law 44 in Schedule B of the CMS for Rampage provides
that "The owner and occupier of a lot must observe and comply with the Code
in relation to the lot." The Code is defined in section 1.2 of the by-laws
to mean "the Architectural and Landscaping Code adopted from time to time
pursuant to Schedule D of this Community Management Statement." Schedule D
identifies the Code dated 28 September 2001, and I have viewed a copy of this
document.
Schedule D of the Rampage CMS further provides that the CMS and
each party bound by the CMS adopts the Code as if each provision of
the Code was
set out in the CMS in full. Schedule D refers to section 53 of the Act
(now renumbered as section 59) which has effect that a CMS is binding on
each member of the body corporate and each owner, as if each person bound by the
CMS had
entered into mutual covenants to observe its provisions and had each
signed the CMS.
In regard to landscaping, Item 4.2 of the Code
provides that all front yard landscaping must be completed within three months
of the occupation of the dwelling
or the completion of the dwelling, whichever
is earlier. Item 10 of the Code provides specifically for landscaping. I will
not
restate the entire section, which is more than two pages long, but note that
Item 10.3 provides specifically:
10.3 Front yard
(a) You are required to establish and maintain landscaping of the front yard of Your Lot by way of the planting of trees, hedges, shrubs, gardens or other forms of landscape embellishment, whether or not there is also provided pathways, driveways or privacy fences.(b) All gardens within view from public areas shall be established to a reasonable standard within three months of the earlier of commencement of occupation of, or completion of the building work relating to , the dwelling. You are required to maintain the landscaping and irrigation between the front boundary line and the kerb.
I also note that
Item 4.1(c)(ii) provides that prior to, during and after commencing building
work, owners must not store excavation
material, rubbish and builder’s
waste, and not deposit any part of the same on adjoining properties or in public
areas.
In regard to window coverings, By-law 9 of the CMS provides
as following:
9. Window Covers
9.1 Owner and Occupier of a Lot must not:-
(a) cover any windows with aluminium foil or similar reflective material or tinted; and
(b) affix any shutters, awnings or other window cover externally to any building or visible from the exterior of the building.
This By-law will not prevent security screens being installed over windows but only after the written consent of the Committee of the Principal Scheme as to the type, quality, colour and style of security screen has been obtained. Such consent may be withheld in the absolute discretion of the Committee of the Principal Scheme.
9.2 An Owner and Occupier must not hand curtains visible from outside the Lot unless those curtains have a white backing, or unless such colour and design have been approved by the Committee of the Principal Scheme. 9.3 An Owner and Occupier must not install, renovate and/or replace a curtain backing or window treatment without having colour and design of same approved by the Committee of the Principal Scheme. 9.4 In giving such approvals, the Committee of the Principal Scheme must ensure, so far as practical, that curtain backing and window treatments used in all Lots have colours that are sympathetic to the tones of the improvements on the Scheme Land and present and aesthetic appearance when viewed from common property or any other Lot.
When a body corporate is
pursuing a by-law issue, the first formal step is generally to issue a
contravention notice. The notice,
which must state certain things including the
nature of the breach, must be given to the person who the body corporate
believes is
breaching the by-law. If the notice does not rectify the matter,
the body corporate can either commence proceedings in the Magistrate’s
Court or may lodge a dispute resolution application in the Commissioner’s
Office. I am satisfied that the Body Corporate has
complied with these
processes.
Landscaping
In the absence of any arguments or
evidence from the respondents to the contrary, I am satisfied that the
respondents are bound by
the provisions of the Code as part of the CMS and also
because the by-laws for the scheme bind owners to the Code.
The
application stated (although no any evidence was originally provided) that the
respondents had breached the Code by not completing
landscaping. During the
course of the lengthy period of abeyance of the application it seems that much
of the landscaping was completed.
When requested to describe the current
deficiencies in the landscaping, the Body Corporate said the lawn was not
completed and that
building equipment had been left onsite. However the Body
Corporate has not disputed the respondent’s recent claim that the
lawns
have not been completed. Accordingly, in regard to the terms of the Code in
regard to landscaping, I have no evidence that
the landscaping is now not
complete.
The Body Corporate says that some black plastic and bricks have
been left onsite. I find no evidence that the leaving of building
equipment
onsite is contrary to the landscaping provisions of the Code. However these
could arguably be covered by the terms of
Item 4.1(c)(ii) of the Code. Even if
not, I consider it is reasonable in the circumstances that the respondents
remove these items
from public view. If still required, these items could be
stored within the garage or at the rear of the property, provided they
are not
readily visible from other lots or the common property.
Window
coverings
I am of the view that By-law 9 does not prevent owners from
choosing not to have any window coverings on some or all windows. The
Body
Corporate agrees that it cannot require coverings in the windows. Accordingly,
no order is warranted in regard to the rear
facing windows.
The
respondents say that they have fitted coverings on all windows facing the road.
The Body Corporate has not disputed this or raised
any objection to the colour
or type of window covering and so, again, it appears that no order is warranted
in this regard.
Accordingly, the only outstanding issue appears to relate
to a west facing sliding glass door. The respondents say they intend to
replace
the sheet on this door as soon as possible and, as the remainder of the front
windows have been completed I do not doubt
this. The Body Corporate wants this
done within 14 days. However on balance I am not convinced by the material
provided by the
Body Corporate that the sheet is in breach of By-law 9.
By-law 9.2 prevents visible curtains unless they have a white backing or
have been approved. But the By-law does not say that all
windows must have
window coverings, or that any window coverings on windows or glass doors must be
specified types of window coverings.
While By-law 9 generally refers to
windows, By-law 9.2 does not appear to restrict where curtains can be hung so I
do not consider
it necessary to determine whether the sliding glass door
falls within the meaning of a window in the by-law.
When I asked
the Body Corporate to describe how the sheets breached By-law 9 they merely
provided a copy of the by-law. A ‘curtain’ is defined in the
Oxford Concise Dictionary as a suspended cloth used as a screen, usually movable
sideways or upwards. On that
basis I see no reason why a sheet suspended from
the window could not fall within that definition of a curtain.
The Body
Corporate did not respond to my request for clarification of the colour of the
sheets. However it appears from the colour
photographs provided that the sheets
are white. On that basis it would seem that the sheets fall within the scope of
a white curtain.
Given that the apparent key concern of the by-law is
consistency in colours, I am unsure what objection the Body Corporate has to
the
white window coverings. The photographs provided do not indicate that the
sheets, although certainly not idea, are unsightly
or discordant.
By-law 9.3 says that curtain backing or window treatments must not be
installed, renovated or replaced without approval. This could
be seen as in
conflict with By-law 9.2 which apparently allows white backed curtains without
approval. To my mind the logical interpretation
of these two by-laws when read
together is that curtains with white backing may be installed without approval
but that any window
covering other than those within the definition of a
curtain, or any window coverings without a white backing, require approval.
On that basis the white sheet appears to be permitted without approval
under By-law 9.2. Notwithstanding this, I would assume that
the respondents who
have spent such time and effort on their property will not want to continue with
a sheet on their door indefinitely
and will install an appropriate covering in
due course.
Rear fence
The respondents have raised the
issue of fencing of their lot. However this issue was not raised by the Body
Corporate in regard
to the landscaping or otherwise. Accordingly I have no
basis to make any order in this regard. However, the respondent is advised
to
review the Code requirements regarding fencing and have regard to the
information provided regarding approval processes. I would
encourage the
parties to be open in their communication on that issue.
Conclusion
It is clear that the respondents have been slow
in meeting their obligations under the Code. However, they have now
substantially
addressed the Body Corporate’s concerns. While the Body
Corporate has certainly shown forbearance in this regard, it does
seem that more
direct communication with the respondents, and more specific information
regarding the alleged deficiencies, may have
assisted the Body Corporate achieve
an earlier resolution of this matter.
The driveway and landscaping have
now been completed and so no order is warranted in that regard. To the extent
that any building
materials have been left in the respondent’s front yard,
I do consider that it is just and equitable in the circumstances that
these be
removed from public view. In light of the nature of the items I cannot see that
this could present any great burden for
the respondents. In regard to the
window coverings, it seems that the only one door is currently at issue. On
balance I am not
satisfied that the Body Corporate has demonstrated that the
sheet in place is contrary to the by-law. Accordingly, I have dismissed
the
remainder of the application.
[1] See sections 246 and 244 of the Act respectively
[2] BCCM
Form 10
[3] See sections 227,
228, 276 and Schedule 5 of the
Act
[4] See section 66 of
the Act and particularly subsection 2(b)
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2007/623.html