![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 12 November 2007
REFERENCE: 0313-2007
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
27255
|
|
Name of Scheme:
|
Coolangatta Place
|
|
Address of Scheme:
|
87 Griffith Street COOLANGATTA QLD 4225
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Bradley & Margaret Bishop, the Owner(s) of lots 303, 304, 305, 306 and
401
|
I hereby order that the body corporate for Coolangatta Place must
not operate the cooling tower fan between the hours of 8pm to 6am or cooling
tower
pump between the hours of 10:00pm to 6:00am, unless authorised by further
order of an adjudicator.
I further declare that the recent expenditure associated with noise reduction following an Environmental Protection Authority complaint was not properly authorised by the body corporate. I further order that, within three months, the body corporate must consider by ordinary resolution whether this expenditure should be ratified. I further order that, within three months, the body corporate must stop providing air conditioning services to persons who have not agreed in writing to pay for the services. The body corporate must adopt a formula for payment that will ensure, to the greatest practicable extent, that the total cost to the body corporate (other than body corporate administrative costs) for supplying the service, is recovered from the users of the service. Specifically, all future electrical and maintenance costs must be recovered along with any expenditure ratified by the body corporate as being for noise reduction works following the Environmental Protection Authority complaint. However, it is not necessary that this formula account for recovery of past electricity consumption or past maintenance expenses. I further order that the committee may arrange for the installation of a separate meter to measure the amount of electricity used by the cooling tower provided that the cost of the installation is within the committee spending limit. I further order that the application is otherwise dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0313-2007
"Coolangatta Place" CTS 27255
Application
Coolangatta Place Community Titles Scheme (Coolangatta Place) is a 31
lot scheme under the Body Corporate and Community Management Act 1997
(Act) and the Act’s Commercial Module Regulation
(Commercial Module). The scheme is designed primarily for retail and
office purposes but lot 401 is a private residence owned by Bradley and Margaret
Bishop (applicants).
The application is really three separate
applications. Firstly, an allegation of a conflict of interest by committee
members in nominating
their employer as the Centre Manager. Secondly, a dispute
about the costs and use of the cooling tower. Thirdly, a dispute about
the body
corporate's refusal of the applicants' request to be allowed to extend the
height of their apartment by another three levels.
Decision
Appointment of centre manager
Alleged conflict of interest
The applicant submits that the majority of lots in the scheme are owned by
Piers Property Real Estate Pty Ltd (Piers Property) and associated
companies. It is submitted that the committee acted under a conflict of
interest and contrary to the legislation
in resolving to put forward Piers
Property as centre manager. An order is sought that the resolution appointing
Piers Property should
be declared void.
A submission on behalf of the
body corporate committee is to the effect that the claimed conflict of interest
should not invalidate
the appointment as the committee gave all owners the right
to submit their own quotations and vote accordingly. A letter is attached
showing that the committee provided owners with details of the duties for the
position and invited owners to obtain their own quotations.
It is also
submitted that the prohibition on voting in a situation of conflict of interest
does not apply to voting in general meeting.
Appointment of Piers Property
In terms of an alleged conflict of interest, the legislation provides that a
committee member must disclose potential conflicts of
interest and must not vote
on those issues (Standard Module, 34).
If any committee member
had voted at the committee meeting to appoint an associate, Piers Property, as
centre manager then those committee
members would be voting under a conflict of
interest. However, the resolution at the committee level was simply to put
forward persons
for the owners in general meeting to consider. There is no
conflict of interest in simply voting to put a motion on the agenda for
a
general meeting.
The appointment itself was pursuant to a resolution
passed in general meeting. In general meeting owners are voting in their own
right and not as representatives of other owners. There is no legislative
requirement for owners to refrain from voting in general
meeting because of a
conflict of interest.
This does not mean that owners in general meeting
can act with impunity to vote themselves financial benefits in general meeting
at
the expense of the body corporate. Such actions would justify interference
by an adjudicator on a "just and equitable" ground to overturn the
appointment.[1] However, the
submissions put forward by the applicant do not satisfy me that it would be just
and equitable to overturn the particular
decision to appoint Piers Property in
this instance. Owners had a choice of only two quotations. The quotation from
Piers Property
was significantly higher than the quotation from QAS
International. However, on the material provided, the owners of the majority
interests in Coolangatta Place could have had genuine concerns about the
qualification and experience if QAS International and the
lack of public
liability insurance. The quotation from Piers Property states that "Piers
Property Real Estate Pty Ltd are specialists in the leasing and sales of
Commercial and industrial properties on the southern
Gold Coast and Tweed Heads
area. We currently manage a portfolio of approximately $100 million. We are
registered in both Queensland
and New South Wales Real Estate Institutes and
abide by their 'Code of Ethics'...The office at Coolangatta Place is open,
business
hours from 8.30am to 5pm". There is no similar information about
the background and experience of QAS International.
Comparing the two
quotations objectively, it is not obviously unreasonable for Piers Property to
have been chosen in preference to
QAS International and I do not consider it is
just and equitable to overturn the decision, particularly at this late stage.
Any
owners who consider that another party can provide the services at an
appropriate level for a better price should obtain a quotation
from that party
setting forward all relevant information including the qualifications of the
nominee. That quotation can then be
submitted for consideration at the next
general meeting.
Excessive noise from cooling tower
The applicants claim that the noise from operating the cooling tower is
excessive and orders are sought to stop the body corporate
operating the air
conditioning cooling tower from 8pm to 6am or to require the body corporate to
undertake further noise attenuation
measures to meet Environmental Protection
Agency requirements.
A submission on behalf of the body corporate
committee refers to the Environmental Protection Agency requirements that an
occupier
of premises must not use air conditioning equipment from 7am to 10pm if
it causes noise to be made of more than 50 dB(A) or before
7am or after 10pm if
it causes noise more than the higher of 40 dB(A) or 5 dB(a) above the background
noise level (Environmental Protection Regulations 1998, 6Z). However,
submissions were made to the effect that Coolangatta Place is a commercial
scheme and it was submitted that the body corporate
cannot refuse to supply air
conditioning when requested by tenants.
An acoustical report has been
provided from Heggies Pty Ltd, a member firm of the Association of Australian
Acoustical Consultants.
This report measured noise levels from within the
applicant's bedrooms with no cooling plant operating, with the pump only
operating,
and with both the pump and fan operating. The report indicates that,
at least within one of the bedrooms, the use of the pump and
fan exceeded these
guidelines at all times and the use of the pump only exceeded these guidelines
if used before 7am or after 10pm.
Measurement at the window indicated use of
the pump only may slightly exceed these guidelines even during the day.
However, measurements
also indicated that closing the bedroom window would
significantly reduce noise to well within these limits.
The present
application is not an application for enforcement of Environmental Protection
Agency requirements and there is no jurisdiction
to enforce those specific
requirements as part of this application. However, an adjudicator has the power
to make an order that
is just and equitable in the circumstances to resolve a
dispute between an owner and the body corporate (Act, 276). A body
corporate is expected to act reasonably in administering the common property and
body corporate assets and there is a dispute
about the reasonableness of the
committee recently allowing operation of the cooling tower at night (Act
94(2), 152(1)).
The applicant has sought orders about the operation
of the cooling tower specifically between the hours of 8pm and 6am. Based
primarily
on the acoustical report provided I am satisfied that it is just and
equitable to grant an order that the body corporate must not
allow operation of
the cooling plant fan between the hours of 8pm and 6am, and must not allow
operation of the cooling plant pump
between the hours of 10pm and 6am.
If there is a change of circumstances, for example if further noise
attenuation measures are taken, then a further order of an adjudicator
can be
sought to remove this prohibition. Alternatively, it may be unnecessary to use
the cooling tower at night if it is possible
to install separate air
conditioners for any lots that require air conditioning at night.
User pays basis for cooling tower operation
The applicants claim that the body corporate only began operating the cooling
tower twenty four hours a day because one of the tenants
of Piers Property
started operating during those hours. It is submitted that Piers Property
should have provided that tenant with
a split system air conditioner rather than
causing the whole cooling tower to be operational for only that
tenant.
It is also submitted that the continual operation of the cooling
tower resulted in noise complaints from residents of a neighbouring
scheme and
that the owner of lot 108 should pay the entire costs of noise attenuation works
that resulted from that complaint. These
costs were estimated to be around
$42,000.
A submission on behalf of the body corporate committee was to
the effect that the body corporate was served with a warning notice
from the
Environmental Protection Agency and was therefore required to perform the work
to reduce the noise to the neighbouring scheme.
It is submitted that this work
was necessary to reduce day time noise levels as well as night time levels so
should not just be
the responsibility of the owner of the lot who sought night
time use. It was also submitted that the cooling tower is a common property
facility that is readily available to all units and the committee feels that it
cannot reject a request for 24 hour use regardless
of which lot requests the
use.
The cooling tower is a service supplied by the body corporate for
the benefit to owners and occupiers of lot. The legislation specifically
empowers the body corporate to supply air conditioning or heating services
to owners and occupiers (Commercial Module, 99(1)(c)). However, the body
corporate cannot simply chose to supply a service to one or more owners and then
levy all owners for the costs
of supplying that service. The legislation
specifically provides that when supplying a service of this nature the body
corporate
must, to the greatest practicable extent, ensure the total cost to the
body corporate (other than body corporate administrative costs)
for supplying
the service, including the cost of purchasing, operating, maintaining and
replacing any equipment, is recovered from
the users of the service
(Commercial Module, 99(3)). Each owner can choose whether or not to
accept the services but must pay for the services if they accept them
(Commercial Module, 99(2)).
I have concluded that the operation
of the cooling tower involves the provision of a service by the body corporate
that the body corporate
should, by agreement with persons using the service, be
required to recover the costs of the service from the users (Commercial
Module, 99(3)). However, some further consideration needs to be made of
which expenses need to be recovered and what order is just and equitable
in the
circumstances to resolve the dispute (Act, 276).
Expenses that need to be recovered
No recovery of historical expenses
The cooling tower has been used for a number of years with maintenance and electricity consumption costs being paid by all owners as part of their levies. No orders have been sought in relation to these historical expenses and it would be difficult at this stage to calculate and fairly allocate those costs. Given that owners could have at any time challenged these arrangements rather than simply paying these costs as part of their levy then, as a matter of discretion, I consider it just and equitable not to interfere with the historical arrangement that involved all owners contributing to these expenses by way of their body corporate levies.
No recovery of electricity expenses for night time use
The applicants have expressed the view that around $10,000 additional
electricity has been consumed as a result of a single occupier
wanting to use
the cooling tower at night. In respect of the additional electricity charges it
is again difficult to fairly assess
any additional cost. There is no separate
metering of the electricity used for the cooling tower and no consistent use of
the cooling
tower at night. Information provided by the parties indicates that
sometimes the tower was fully operational and sometimes only
the cooling tower
pump was being used. The estimate provided by the applicants is based on
historical data that may be affected
by a number of matters. In particular, the
claim covers a period that includes a number of months before the application
was lodged
and it is not disputed that the cooling tower has been operated
without expenses being allocated to individual users for a long period
of time.
The cooling tower expenses have been recovered as part of the body
corporate's levies for a long period of time. I consider it just
and equitable
to now give the body corporate a short period of time to put in procedures to
arrange for proper cost recovery from
users. In all the circumstances, I have
concluded that it is not just and equitable to make any order requiring recovery
of past
electricity expenses even in respect of the recent night time usage.
Recovery of costs of noise attenuation works
Recovery of the costs of noise attenuation works of around $42,000 are a
different matter. From reviewing minutes of meeting I am
satisfied that these
works were never properly approved by the body corporate. The works were
effectively an improvement to a common
property facility to address noise issues
and these works should have been approved by ordinary resolution or by the order
of an
adjudicator (Commercial Module, 93). Having said this, submissions
on behalf of the committee indicate that the works were necessary due to the
Environmental Protection
Agency complaint and that persons with majority voting
rights would have voted in favour of the works if the matter had been put
to a
general meeting. In these circumstances, it seems appropriate to give owners an
opportunity to ratify the expenditure in general
meeting.[2] Based on the submissions
the expenditure is likely to be ratified. However, if it is not ratified then
owners may wish to consider
legal options in relation to the matter potentially
including the taking of a representative action on behalf of the body corporate
to seek to recover the unauthorised expenditure from the persons who spent body
corporate funds without authority.
Assuming the body corporate does
ratify the expenditure, the question still arises as to whether the body
corporate should seek reimbursement
of this expenditure from any individual
owners. The applicants have sought that the body corporate recover this
expenditure from
the owner of the lot whose occupier was using the cooling tower
at night. This is based upon a claim that the noise attenuation
works were only
necessary to facilitate use of the cooling tower at night and that this was for
the benefit of only that one person.
It may have been the case that a
complaint to the Environmental Protection Agency was only made, as a matter of
circumstance, because
the cooling tower started being used at night. However,
once that complaint was made, I accept the evidence in the warning notice
from
the Environmental Protection Agency that the noise from the cooling tower was 65
decibels from within the neighbouring property.
This level is above the
Environmental Protection Agency permitted levels for daytime as well as use at
night and I accept the submissions
on behalf of the committee to the effect that
the work needed to be performed to facilitate any future use of the cooling
tower,
even during the day.
I am therefore satisfied that it is all
future users of the service who will receive the primary benefit from the works.
Therefore,
unlike past electricity charges, I consider it just and equitable to
make an order facilitating the payment for the works from the
future users of
the service if the expenditure is ratified by the body corporate. While it is
not clear at this time which current
and future owners will use the cooling
tower services, it should be possible for the body corporate to adopt a formula
that ensures
these costs are recovered over a reasonable period of time from
persons who do ultimately use the service. I will make an order
requiring that
this occur.
Recovery of future electricity consumption and maintenance costs
It should now be clear to the committee that the body corporate is required
to put into place arrangements by which the body corporate
recovers the costs of
future electricity consumptions and maintenance costs from the users of the
cooling tower service (Commercial Module, 99).
It is not
generally possible for exact amounts to be determined in advance as different
matters may arise or different numbers of
owners would use the cooling tower
over time. However, I will make an order requiring the body corporate adopt a
formula for charging
users of the service so that the body corporate recovers
future maintenance costs and electricity consumption along with any expenditure
ratified by the body corporate as being for noise reduction works. There may be
more than one way for the body corporate to do this
and the body corporate may
wish to obtain its own advice in this respect. However, it would not seem
unreasonable for the body corporate
to initially estimate all costs over a ten
year period and then average those costs between the expected numbers of owners
using
the service. For example, costs over the next ten years might be
estimated as $200,000 covering the noise attenuation works, future
maintenance,
and expected electricity consumption. It might also be estimated that an
average of ten lots would use the service
for each of the next ten years and use
the service roughly to the same extent. If so, an initial payment of $2,000 per
lot per year
would be likely to cover the estimated costs. At the end of each
year the actual cost recovery verses expenditure could be compared
and any
necessary adjustments could be made to the amount each lot is required to
contribute.
I also understand that the body corporate has made enquiries
about the installation of a separate meter to measure electricity consumption
for the cooling tower. This is likely to be a relatively minor expense that
will greatly facilitate effective cost recovery of the
provision of the cooling
tower service. However, an additional meter may also be an improvement to the
common property requiring
authorisation by ordinary resolution (Commercial
Module, 93). In the circumstances of this application, and to facilitate
compliance with other aspects of the orders made, I consider it just
and
equitable to make an order authorising the committee to arrange for the
installation of a separate meter to measure the amount
of electricity used by
the cooling tower. This is provided that the cost of the installation is within
the committee spending limit.
Extension of lot 401
The applicants' apartment is a two level stand alone structure situated on
part of the rooftop of the scheme. The applicants say
that there is no height
limit on their apartment and they wish to extend the height of their apartment
by an additional three levels.
It is submitted that no other property owner
will be disadvantaged by the proposal.
A submission on behalf of the body
corporate committee is to the effect that the proposal does in fact extend
beyond the bounds of
lot 401 as shown on the registered plan and requires a
resolution without dissent to be approved. It is submitted that this was
appropriately voted on by owners and that the resolution failed.
I have
reviewed the registered plan. It is a building format plan under which the
general rule is that the boundary of a lot created
under a plan and separated
from common property by a floor, wall, or ceiling must be located at the centre
of the floor, wall or
ceiling (Land Title Act, 49C). The plan and
photographs show that the airspace above the applicants' apartment is common
property and the building of any additional
floors on top of the existing
apartment would encroach on common property.
An adjudicator may
overturn opposition to a resolution without dissent if that opposition in the
circumstances is unreasonable (Act 276, Schedule 5 Item 10). However,
the applicants have not satisfied me that the opposition is unreasonable. While
the applicants may have a view that no
other owner will be directly adversely
affected by the proposal, the proposal would amount to a significant change to
the scheme
and require a new plan to be registered. In particular, it may
affect potential future redevelopment of the scheme, the potential
for the body
corporate to make improvements itself to the area in question, or may result in
changes needing to be made to the interest
schedule lot entitlements affecting
rights and liabilities on any future termination of the scheme. This is not a
matter where I
consider it is just and equitable to overturn the opposition to
the proposal.
Order
For these reasons, I make the order above.
[1] Dindas & Anor v Body
Corporate for One Park Road [2006] QDC 302, Wilson SC DCJ, 25 August 2006 at
paragraph 46. See also Hablethwaite & Anor v Andrijevic & Ors [2005]
QCA 336, Jerrard JJA, Keane JJA, Cullinane J, 9 September 2006 at paragraph
33.
[2] For ratification generally
see Warren v Body Corporate for Buon Vista [2007] QCA 160, de Jersey CJ, Keane
JA and Holmes JA at paragraph 12.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2007/599.html