![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 12 November 2007
REFERENCE: 0777-2007
INTERIM ORDER OF AN
ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
10951
|
|
Name of Scheme:
|
De Ville
|
|
Address of Scheme:
|
3645 Main Beach Parade MAIN BEACH QLD 4217
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by Elizabeth Reynolds, the owner of Lot 84
|
I hereby order that the application for an interim order by
Elizabeth Reynolds, the owner of Lot 84 against Clifford Cook, Susanna Cook and
Brian
Keene, the owner of Lot 103 seeking the immediate and urgent cessation of
all renovation works, is dismissed.
|
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0777-2007
"De Ville" CTS 10951
Application
This application is by Elizabeth Reynolds, the owner of
Lot 84 (applicant) against Clifford Cook, Susanna Cook and Brian Keene, the
owner of Lot 103 (respondents) seeking the following outcomes.
The final
outcome sought is:
1. An order that all works which result in nuisance to the owners and occupiers caused by drilling, grinding, jack hammering or other similar building activities all of which create unreasonable and incessant serious noise pollution, be prohibited from taking place between the following holiday periods:
29 September to 23rd October 2007
15th December 2007 to 31st January 2008.
2. The use of the external hoist be limited only to the following hours:
Monday to Friday 8am to 8.45am, 12noon to 1pm, 4.45pm to 5pmSaturday 8am to 8.30am, 12noon to 12.30pm.
3. Obstruction to common property caused by the external hoist be removed and access to common property areas be reinstated. 4. That a schedule of hours be agreed upon which clearly defines and limits the dates and hours at which any noise inducing work in the penthouse renovations are permitted to take place.
The applicant has also
sought the following interim order:
Immediate and urgent cessation of all works to enable mediation and/or
conciliation to take place. As we are in a holiday letting
period it is
imperative that all works cease immediately as not to do so will interfere with
owners rights to use and enjoyment as
historically building works have had the
effect of occupiers leaving the building demanding rental refunds. I wish to
have my own
use and enjoyment and privacy reinstated and the immediate cessation
will enable mediation and / or conciliation.
Jurisdiction
"De
Ville" community titles scheme 11512 is scheme under the Body Corporate and
Community Management Act 1997 (Act).
In accordance with section 247
of the Act, the Commissioner for Body Corporate and Community Management has
referred the application
to me even though affected persons have not been given
notice of the application, or afforded an opportunity to make submissions
about
the application.
Section 276(1) of the Act provides that an adjudicator
may make an order that is just and equitable in the circumstances to resolve
a
dispute, in the context of a community titles scheme, about a claimed or
anticipated contravention of the Act or the community
management statement; or
the exercise of rights or powers, or the performance of duties, under the Act or
the community management
statement. Section 279(1) provides that an adjudicator
may make an interim order if satisfied, on reasonable grounds, than an interim
order is necessary because of the nature or urgency of the circumstances to
which the application relates.
Procedural matters
In accordance
with the investigative powers of an adjudicator stated in section 271 of the
Act, on 2 October 2007 I invited submissions
and a copy of the application was
provided to the respondents and to Body Corporate Services Pty Limited (the body
corporate manager)
for distribution to the committee with an invitation for the
respondents and the committee to make submissions regarding the interim
order
application. The respondents and the committee made written submissions.
Martin Corkery also made written submissions (uninvited).
On 10 October
2007, the applicant provided further material about the interim order
application. By notice dated 11 October 2007,
I invited the respondents, the
committee and Mr Corkery to make submissions on the matters raised in the
further material. The committee
responded to the further
material.
Background
At the Extraordinary General Meeting dated
21 March 2007, the body corporate resolved to carry out a number of repairs or
refurbishment
works throughout the scheme including: repairs to the ducting and
exhaust system (Motion 2); waterproofing works on the 27th level
(Motion 3); rooftop repairs (Motion 4); refurbishment of the ground floor entry
(Motion 5); refurbishment of the lift lobbies
(Motion 6); repairs to the
building façade (Motion 8); and repairs to the lift car interiors (motion
10). The body corporate
also consented by special resolution to: the
respondents erecting a lift/hoist on common property; and to entering into a
Licence
Agreement with the respondents about the erection and use of a hoist on
common property for a period of 8 months from 21 March 2007
(Motion 9). Motion
9 referred to attached drawings and to attached terms and conditions. The work
proposed in Motions 2, 3, 4 and
8 were approved in accordance with scope of
works prepared by the Buildcheck (engineers).
On 29 May 2007, a Licence
Agreement between the body corporate and the respondents was executed. On the
same date, a Renovation Agreement
between the body corporate and the respondents
was executed stating the agreed terms and conditions for the proposed
renovations
of Lot 103. Both Agreements restricted the hours jack hammering was
allowed. The Licence Agreement also restricted the times transmission
of
vibration or noise could be caused, including drilling and jack
hammering.
Work on the penthouse level commenced in June 2007 with the
construction of the hoist.
In letters dated 13 and 19 September 2007, the
applicant wrote to Body Corporate Services Pty Limited (BCS) expressing concern
about
the work being performed and the use of the hoist.
Bruce Adam of
BCS responded to these letters by facsimile dated 20 September 2007, advising
that all jack hammering on the building
roof will cease on 21 September 2007,
and that the body corporate has been liaising with the owner’s
representative and building
contractor of the owner of Lot 103 about completion
of the works.
By letter dated 21 September 2007, the applicant wrote to
BCS stating that she is advised that drilling will continue causing worse
noise
pollution throughout the building than jack hammering. The applicant sought an
assurance all drilling will cease until after
Indy. She also expressed concern
about the hoist.
By facsimile dated 21 September 2007, Bruce Adam stated
all jack hammering in Lot 103 will cease on 21 September 2007, all drilling
relating to the rectification of the waterproof membranes on the
building’s roof will also cease on 21 September 2007, and
there will be a
reasonable level of intermittent noise due to the renovations in Lot
103.
By letter to BCS dated 26 September 2007, the applicant stated that she was
resident on 24 and 25 September 2007 and "observed that
sounds of drilling and
grinding continued unabated from the penthouse renovations".
On 26
September 2007, the applicant gave a Notice to Body Corporate of a Contravention
of a Body corporate By-Law citing section 167
of the Act.
On 1 October
2007, the application for an interim order was
made.
Submissions
The applicant submits that work on the
penthouse level has been performed at all hours and has involved jack hammering,
drilling and
the constant use of the hoist. She states that the use of the
equipment reverberates throughout the building; the constant noise
of the jack
hammering, drilling and grinding is unbearable; and that privacy is invaded with
the constant use of the hoist outside
the bedroom window of Lot 84. The
applicant is concerned that there have not been any consultations with owners
around the work
hours or the development of an appropriate works schedule to
reduce the interference with the use and enjoyment of other lots. She
adds that
there have been numerous complaints made to the body corporate manager, the
building manager and committee members (the
applicant provided letters signed by
23 persons indicating, for various reasons, their concerns about the building
works. Many of
the letters have been signed in late September 2007). The
applicant contends that holiday makers have complained and demanded to
be moved
to other levels, while some have walked out demanding refunds of rent. The
applicant submits that requests relating to
reducing the noise and the use of
the hoist have been ignored.
The respondents submitted that it was agreed
with the body corporate that all work would be completed by 12 December 2007.
They say
most noise occurred during the demolition stage completed in early
August 2007 and since then the noise generated has not involved
any jack
hammering or drilling. The respondents state that some jack hammering was
undertaken from 17 to 20 September 2007 in relation
to the waterproofing
membrane and that this has been completed. They submit all efforts have been
made to be respectful to owners
and occupiers, including informal weekly
meetings were offered to be held with the resident manager, meetings and other
communications
conducted with body corporate representatives, and on 10
September 2007 a notice was delivered into every mailbox apologising for
the
disturbances of the construction works. The respondents claim that any
restrictions will extend the contract completion date
and extend the removal
date of the goods lift.
The body corporate submitted the only previous
official complaint to the body corporate had been made by the owner of lot 4 and
this
complaint was addressed by the committee at its meeting dated 20 August
2007. The body corporate states that of the 24 owners (including
the applicant)
who signed the letters of concern, 13 voted on Motion 9 at the EGM and of these,
3 voted against the Motion. It says
the supervising engineer (Buildcheck) has
advised that all jack hammering and drilling associated with work to
replace/repair the
roof membrane has ceased, however there will still be some
noise generated in Lot 103. The body corporate states the respondents
are
obligated to remove the external lift by 10 December 2007 and any delays would
impact on this obligation. It is stated that
a major source of noise from works
on the roof emanated from the replacement of the roof membrane by the body
corporate. The body
corporate contends that the applicant has not demonstrated
the noise from work in Lot 103 and the operation of the external lift
is beyond
a reasonable level and above general background noise and supported by an
acoustics engineers test report. It states that
when the proposal from the
respondents was first considered, it was deemed desirable for the work not to
run into the 2007 Christmas/New
Year period.
In further material, the
applicant stated she has been advised by the building manager and other
occupants that work and the noise
has continued at the same or greater level
than prior to the letter dated 21 September 2007 causing walkouts and financial
refunds
having to be made. She states that there have been times when committee
members have not been in occupation and could not monitor
the work. The
applicant states that "last night" there was severe flooding in 9 lots
(including Lot 84) during heavy rains "apparently
caused by some tradesmen
blocking pipes with debris from the Penthouse renovations". The applicant
referred to sections 100(5),
101A and 167 of the Act.
In responding to
the further material, the body corporate states the applicant’s claims
about continued noise can only be hearsay
and have not been supported by
statutory declarations. The body corporate provided a copy of an emails dated
12 and 13 October 2007
from Vince Rehbein (committee member and resident)
stating that the noise is not greater than before; is not worse than experienced
from other renovations; as at 11 October 2007, he and his wife have been in
residence except for 3 days early in October; and neither
the applicant nor the
building manager has tried to contact him regarding this matter even though his
Lot adjoins the applicant’s.
The body corporate states that the water
ingress was dealt with promptly.
Determination
Given section
279(1) of the Act, it is necessary to determine at the outset whether, because
of the nature or urgency of the circumstances
relating to the application, an
interim order is in fact necessary or appropriate. The examples included in the
Act under section
279(1) are suggestive of the usual circumstances where an
interim order might be made. Both examples are in the nature of injunctive
relief. Whilst the range of matters which might be the subject of an interim
order is not capable of definition, the applicant does
need to establish that
the circumstances of the application warrant the making of an interim
order.
In March 2007, the body corporate approved entering into a Licence
Agreement with the respondents. The executed Agreement contains
terms and
conditions about the position and use of a hoist related to the renovation work
to be done on Lot 103, and about the work
specifically restricting the times for
drilling and jack hammering. Work relating to the renovations commenced in June
2007. While
the applicant makes general comments about earlier complaints, it
has been shown that in September 2007 the applicant and other owners
had
complaints about the noise and interference with the use and enjoyment of lots
caused by the renovations. Even though it is
evident that the body corporate
had made a decision about the work, a person such as an owner or occupier is
able to complain relying
on an alleged contravention of a provision of the
legislation or the scheme by-laws.
In seeking an interim order under the
dispute resolution provisions of the Act, the applicant does need to demonstrate
that such an
order is warranted given the nature or urgency of the circumstances
or given that it raises a serious legal question that will need
to be ultimately
determined.
The applicant has principally relied on section 167 of the
Act which states:
Nuisances
The occupier of a lot included in a community titles scheme must not use, or permit the use of, the lot or the common property in a way that--
(a) causes a nuisance or hazard; or
(b) interferes unreasonably with the use or enjoyment of another lot included in the scheme; or
(c) interferes unreasonably with the use or enjoyment of the common property by a person who is lawfully on the common property.
The
applicant has also mentioned section 100(5) of the Act stating The committee
must act reasonably in making a decision and section 101A which provides
protection of committee members from liability. Given the terms of the outcome
sought, the references
to sections 100 and 101A of the Act are not of any
consequence in the determination of the interim order application. The
applicant
has given the body corporate notice about a suspected by-law
contravention pursuant to section 185 of the Act. However, she has
not referred
to a particular by-law and from my reading of the by-laws stated in the
community management statement for the scheme,
there does not appear to be a
by-law relevant to the dispute.
In the circumstances, section 167 may be
applicable. There is a question about this provision given the respondents
would seem to
reside in New Zealand and the term ‘occupier’ (in
part) is defined to mean a resident owner or resident lessee (Schedule
6
Dictionary, Act). For the purposes of making an interim order, I have
considered the nuisance provision given that the work is
being done on the
respondents’ lot. The parties may choose to make submissions about this
matter should they be invited to
at some point in the resolution of this
dispute.
It is relatively clear from the submissions that the work on Lot
103 has caused noise and has interfered with the use and enjoyment
of lots
included in the scheme. The respondents in a letter to all occupiers have
stated "the noise levels resulting from the recent
demolition work were more
strident than might have been anticipated". While section 167 regulates
nuisance, this provision cannot
be read to prevent renovation work and should
not impose an unfair burden on the person proposing to have the work carried
out.
It would be unreasonable to expect that repair or refurbishment work
within a lot could be done without there being likelihood that
on occasions the
work would breach a general nuisance provision such as section 167. In my view,
the relevant question is whether
in the circumstances the disturbance is
unreasonable, unwarranted or excessive.
The applicant proposes an order
effectively stopping work which has been in progress since June until such time
as the dispute is
resolved. This is a significant issue with a potential to
expose the body corporate, owners and/or the respondents to liability.
Other
than any contractual difficulties which may arise should the work be delayed, it
would be expected that the delay will also
extend the completion date into the
Christmas holiday period.
In these circumstances, the applicant does have
to clearly demonstrate the nuisance or that unreasonable interference is
evident.
The claimed instances of nuisance do indicate that a number of owners
are concerned about the work being carried out in the building.
However, I am
not satisfied that the applicant and the complaining owners have shown that the
work and the use of the hoist (including
its position) has been contrary to what
was contemplated by the body corporate or what would be reasonably expected
given the work
being done in Lot 103. For example, it has not been shown that
the hoist has been used or that the jack hammering and drilling has
occurred at
times outside the Licence Agreement or that these times are contrary to a
particular law, rule or regulation or industry
standard. The terms and length
of the Agreements point to the significant work being proposed to Lot 103.
Nothing has been presented
suggesting that owners queried the extent of the work
before the March EGM or that the resolution of the body corporate was questioned
or disputed.
It would now seem that the bulk of the demolition and
construction work has been completed. I am not satisfied from the material
presented that the applicant has substantiated any claim that jack hammering and
drilling or other major work will be ongoing, that
this work was not forecast,
and that it will cause unreasonable interference with the use and enjoyment of
another lot or common
property.
In addition, it is evident that, at the
EGM, the body corporate approved what would seem to be extensive work throughout
the building.
The applicant has not clearly shown that the disruptions
mentioned in the material presented were entirely due to work being carried
out
on Lot 103 and were not caused by work organised by the body
corporate.
In my view, the applicant has not raised a serious legal
question nor has she demonstrated that the nature or urgency of the
circumstances
warrants the making of the interim order. In balancing the
interests of the parties I am also satisfied that the interests of the
respondents prevail. For these reasons, the application for an interim order is
dismissed. This application will now be administered
in accordance with the Act
and the normal processes of this Office. The application will be finally
determined in due course.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2007/596.html