![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 2 April 2007
REFERENCE: 0462-2006
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT 1997
|
Number of Scheme:
|
6750
|
|
Name of Scheme:
|
Westwater
|
|
Address of Scheme:
|
QUEENSLAND
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
William and Robin Butler, the co-owners of lot 52
|
I hereby order that the application for an order
"that the building be made watertight and proper construction of the roof/exterior membranes of the building, and improvements, so as to achieve a performance consistent with: a) the Building Code of Australia In lieu I order as follows
5.
that the body corporate shall recall the relevant contractors and/or arrange
replacement of the damaged floor tile
in the Applicants’ unit which
tile was damaged during the repairs in August 2005, and also arrange to
match the grout
with the existing tile grout.
|
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION -
REF 0462-2006
"Westwater" CTS 6750
APPLICATION
This is an application dated 16th June
2006 and amended on 12th July 2006 by William Butler and Robin
Butler, (the Applicants) co-owners of Lot 52, against the body corporate
for the scheme (the body corporate), for an order as follows
–
"that the building be made watertight and proper construction of the roof/exterior membranes of the building, and improvements, so as to achieve a performance consistent with:
a) the Building Code of Australia
b) a cessation to flood and water damage to the internal finishings and surfaces and improvements in Lot 52
c) payment of sums due to the applicant for work completed."
Since the filing of this Application, the
Applicants confirm that they have now been paid for repairs for internal
rectification of
damage prior to the pool terrace membrane being replaced. On
10th April 2006, the Applicants sent a statement of account to the
body corporate seeking payment of invoices dated December 2004 and
November
2005, with accrued interest totalling, $2853.94. On 10th
August 2006, the body corporate paid for works done but has not paid the accrued
interest charged on the accounts. I am not therefore
making an order in
respect of item (c) above.
JURISDICTION
"Westwater"
Community Titles Scheme 6750 is a community titles scheme governed by the
Body Corporate and Community Management Act 1997 (the Act) and the
Body Corporate and Community Management (Standard Module) Regulation 1997
(Standard Module). There are 52 lots in the scheme created under
Building Unit Plan of subdivision.
Section 276(1) of the Act
provides that an adjudicator may make an order that is just and equitable in the
circumstances (including a declaratory
order) to resolve a dispute, in the
context of a community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section
284(1)).
SUBMISSIONS
The Applicants’ case is
that they purchased their lot, a penthouse apartment, with a roof-top pool and
spa, in April 1996.
At the time of purchase they noticed water entering around
the vent duct to the kitchen and that some of the internal panels to the
kitchen
cupboards had started to delaminate. The water coming through the vent duct
also continued down into Lot 50 (the sub-penthouse)
below Lot 52. This leak is
now numbered as Leak 7 in the list prepared by the Applicants.
The
Applicants also noted water damage to the electrical/hot water unit cupboard
which abuts a mechanical ventilation duct shaft. This is now numbered as
leak number 4. There was also water damage in the lobby adjacent to the
ventilation duct which had caused
damage to Lot 50 below. They were "assured
at (the) time of purchase that leaks would be attended to by the body
corporate and that that internal damage was covered by
insurance."
Lot 52 has suffered from roof leaks "over a number of
years." In all, there are 11 leaks to the interior of the
Applicants’ lot. The Applicants say that despite long-running discussion
about the leaks with the body corporate, and some remedial treatment as
described below, the body corporate has failed to stop or
cease water ingress
into the building or to take any remedial steps to prevent continuing or further
water damage or repair the water
damage that has occurred.
The 11 leaks
are positioned as follows –
1. Bedroom 2 above window
2. Bedroom 2 within WIR
3. Bedroom 3 cornice and lintel
4. Laundry duct area
5. Inside entry door
6. In kitchen ceiling below the pool
7. Kitchen vent duct
8. and 9. lounge under windows and doors to pool mezzanine area – (repairs now made.)
10. Front balcony over dining terrace
11. Bedroom 1 terrace.
The Applicants have noted that all leaks are occurring at junctions with
floors and vertical surfaces of parapets, walls, solid handrails,
ducts and the
pool.
In summary they put the leaks down to a poor hydraulic design for
the roof, lack of construction detailing at junctions, non-compliance
with the
Building Code of Australia 2004 and relevant Australian Standards, body
corporate contractors for remedial works not adopting
the membrane
manufacturers’ recommendations, the contractors’ failure to abide by
the contract conditions in relation
to water-testing of the membrane prior to
covering it up, and no inspection of the membrane by the manufacturers’
representative.
In 2004, the body corporate arranged for Remedial
Building Services Australia Pty Ltd (Remedial) to replace part of the
roof/pool terrace membrane. The work was overseen by Burchill Partners,
Consulting Engineers, (Burchills) and the Applicants say that Burchills
certified that the work was "complete and free from defect" on 1st
December 2004, and that the membrane was guaranteed for "15 years from the date
of installation."
On 5th December 2004, however, they
noticed a leak after light rain at leak points 8 and 9. On 9th
December 2004 they sent a fax to the body corporate manager stating that various
works had not been completed in accordance with
the contract, amongst other
things that that the tiling was incomplete and "sealant under window and door
frames not installed."
The Applicants were "speechless" as to why no
examination and testing had been carried out of the membrane in accordance with
Clause 11 of the contract, and why the topping and tiles had been put on prior
to testing. This was a "critical part of the work"
and the rain on
5th December 2004 caused damage to the newly repaired plaster and
paint, which had been paid for by the body corporate insurers. The
membrane
turn-up had not been sealed to the underside of the sill. The Applicants
advised:
"rectification of this new damage will be charged to the body
corporate" and that the body corporate should not pay the
contractor.
At Easter 2005, the Applicants noticed a new leak, Leak no.
6. On 30th June 2005 after the first heavy rain since the repairs
were done, Lot 52 again suffered water damage. Since that date, water damage
has re-occurred after rainfall.
In August 2005, the body corporate
organised for the removal and reinstallation of the sliding doors to the pool
area mezzanine. The
work was overseen by Strata Project Management Service,
(Strata) a division of Burchills. The body corporate disputes that
all or some of the leaks are caused by rainwater, or says that certain areas are
the responsibility
of the Applicants. The body corporate suggests to the
Applicants that it is the pool and/or the spa which is leaking, and that the
remedial work done in 2004 was sufficient and properly undertaken.
The
Applicants have noted that the leaks only occur after heavy rain and the pool
does not otherwise leak even though it is always
full. The Applicants have had
the pool ‘dye tested’ "returning no discernable leak." The
body corporate says that it has also tested the water coming through the slab
and that the presence of salts proves that it
is poolwater. The Applicants say
that the salts are consistent with "leachate salts contained within the
concrete" of the slab.
The Applicants meanwhile have continually sought
scientific explanations for the leaks.
On 7th November 2005,
the Applicants obtained a report from the "Leak Detective," Dan Davidson.
(Leak detective report) The leak detective report found that there were
"no leaks in pipes and filter equipment" for the swimming pool or spa. It also
reported
–
"A hose test against outside wall under pool decking
proved water to be leaking past the waterproofing membrane and water drips
appearing
on window casements in room below. A further wet spot appears
directly under pool in room below after heavy rain, however this
spot dries out
in dry weather. A hairline crack has appeared in spa end of pool and an
evaporation test being carried out over
the next week. If there is no rain will
prove if the leak is coming from the pool or spa..."
On
20th November 2005, the Leak Detective further reported that a dye
test had also been done, and an evaporation test over 4 days. The
pool
evaporated slightly more than spa, but that was acceptable considering high
winds and the surface area. He reported that
-
"a hairline crack in
spa does not show on the outside pool shell and did not prove to leak at the
evaporation test. In the time
I have been there water has showed in lower rooms
after rain, and after 2 days of fine weather dried."
He also did a
hose test on the topping slab under the pool deck between the spa and the
southern external wall and this caused a leak
in bedroom 2, which proved to him
that "the waterproof membrane has failed."
On 7th
February 2006 the Applicants received a report from hydraulic engineers, Deluca
Design Hydraulic Engineering Consultants Pty Ltd
(Deluca) following an
examination by Deluca on 25th January 2006. Deluca examined the roof
drainage of the eastern podium of Lot 52 and conducted flow analysis tests by
modelling in
relation to 6 of the 7 water drainage outlets on the roof. It
found that an overflow channel on the northern façade had been
"plugged."
It also found that the primary drainage system was allowing for water
"overtopping" adjacent to the glass sliding door
entry to the podium roof, and
that a minimum freeboard of 50mm above the estimated water level should be
adopted by reviewing and
modifying the waterproofing membrane and/or glazing
systems.
Deluca also found that there was no provision for secondary or
overflow drainage which is a "fundamental part of a roof drainage system."
It
recommended a "full failure overflow system be installed to provide a level
of protection form overtopping." Deluca did not inspect or evaluate
any weatherproofing membranes.
The Applicant, Mr Butler who is a plumber
licensed in New South Wales, inspected all the areas of damage on
11th April 2006, following a previous study by him on 30th
December 2005. His findings contain 19 coloured photographs of several areas of
water-damaged ceilings and moisture affected décor,
as well as water
dripping on bedroom and bathroom balcony edges.
He says that on the
11th April 2006 there had been no rain for three days. All leaks were
dry except leaks numbered 10 and 11 which were still dripping.
The body
corporate did further repairs to the door sill in August 2005 at Leak 8 by
removing and re-installing the doors, and whilst
Leak 8 might now have been
fixed, the repair work was not well executed in that the tiling grout used on
the tiled step below the
door does not match and a floor tile was cracked in the
process.
The Applicants say that they believe that the roof membrane is
not installed in accordance with the manufacturers’ instructions.
It
should have a cove or fillet installed between the floor and the wall surfaces
to prevent a sharp right angle risking damage or
splits in the membrane. This is
possibly what has happened but the Applicants cannot investigate the membrane
without causing damage
to their property above the membrane (eg. the tiles and
paving), and the membrane is the body corporate’s property, and the
work
commissioned by the body corporate and they cannot interfere. They have sought
confirmation from the body corporate about the
materials and the ‘Ardex
system’ used and have asked to see the specification and the warranty,
which at the date of
the application had not been supplied to them. Further
they say that the tiles and topping as placed, do not allow for any freeboard
between the upturn of the membrane and the height that can be achieved by
stormwater.
The Applicants also allege that the membrane was not tested
after installation and before the tiles were placed on top of it as per
the
manufacturer’s specification. The Applicants further say that the window
installation does not meet required Australian
Standards or the Building Code of
Australia in that there is no proper sealing or external coating.
The
capacity to rent out Lot 52 has been considerably reduced since bedroom 2 is
"uninhabitable" because a cornice and blinds cannot
at present be installed
because of the continual leaks. It was renting for $1400 per week. Following
the new membrane installation
and paving completed in December 2004, the
Applicants spent in excess of $60,000 upgrading their pool decks. If the
membrane has
to be uncovered again, much of the upgrade work will now be lost.
In accordance with section 243(2)(b) Act submissions were sought
from all lot owners.
John and Julie McDonald (Mr and Mrs McDonald)
of Lot 51 also a penthouse property adjoining the Applicants’
lot, state that "eventually the roof membrane to (their) unit will
need to be replaced.." They say that "there is obviously a fundamental
fault " if water is leaking in 11 different places and the body corporate
has a legal and moral obligation to make good the defects.
John and Amy
Disley, co-owners of Lot 12 support the body corporate in any decision it makes
in relation to this dispute. David and
Barbara Noakes of Lot 11 also support
the body corporate, and Daisy Cameron of Lot 26 supports the actions of the
committee.
Betty Mitchell of Lot 46, objects to the body corporate having
to pay for Lot 52’s building maintenance. She says that the
building is
18 years old and the Applicants are not the original owners, and the onus is on
them to maintain what they have purchased.
Jeanette Avery of Lot 38 wants
the issues resolved and asks that independent experts be commissioned to give
their findings as to
where the leaks are coming from and where the
responsibility lies. She is chairman of the body corporate and is concerned
that the
body corporate may already have done remedial works to Lot 52 for which
it was not responsible.
TF and NL Stanley of Lot 42 say the Applicants
purchased in 1996 when the lot was 8 yrs old and that they have been told by a
committee
member that so far the body corporate has spent "over $100,000 " on
this lot from the sinking fund. The Applicants should have searched
body
corporate records before settlement for "previous records with water leakage."
Terry and Lyn Toomey. co-owners of Lot 48, say that the failure of the
body corporate to waterproof the building affects everyone
not just the
penthouses. The building is receiving bad publicity. Waterproofing of the entire
roof needs to be carried out, and "
no short cuts or partial repairs" should be
undertaken. They " strongly suggest the body corporate takes immediate
steps to rectify the current situation mainly affecting apartment 52, but no
doubt
also apartment 51 and all those floors below." The responsibility for
the work and the cost can be resolved later but the remedial work should be done
immediately to a standard
approved by a design engineer.
Rex and Joan
Flowers, co-owners of Lot 8, say that the problem has "been with the building
for an extremely long time" and cost all
owners a lot of money. They are
concerned about the lack of accountability between "the two lots of engineers
and contractors who
have been engaged to rectify this ongoing water leaking
problem." They have been told that $50,000 should fix the problem once and
for
all, and that the areas of responsibility have been identified.
Trevor
Simes (Mr Simes) of Lot 36 says he and his wife purchased in 2000 and
they were at that time aware of "ongoing problems" with the penthouse roofs.
He got on the committee in 2001. In 2002-2003 they carried out repairs on two
occasions to the Eastern Patio of Unit 52 in an attempt
to stop water leaks.
They replaced the roofing membrane of the Eastern Patio and Burchills were
employed to make sure the work was
done properly and to help the body corporate
select the right tenderer. The refurbishment tender did not include replacing
the membrane
under the Applicants’ pool.
He has been personally
involved with the remedial works and says that during the course of repairs "
it was found that the Pool ...was leaking." Since the
Applicants’ pool is built on top of the membrane, the Applicants on 8th
November 2004 wrote to Burchills and said
they accepted that to remove and
replace the pool would be prohibitive to the body corporate, but that attention
should be given
to sealing the new membrane to the existing membrane under the
pool before any turn up around the pool is undertaken. On 19th
November 2004, in a letter to the body corporate, the Applicants
acknowledged that they were aware of defects in the pool walls and said they
intended to repair them prior to reinstatement of the
deck.
The body
corporate says that the Applicants have carried out repairs to pool on three
occasions, the last being in August 2005. Mr
Simes says-
" Heavy rain
.. at the end of June 2005 caused leaks to reappear where they have existed for
a number of years."
Engineers employed by the body corporate said
the water "could be coming from above the new membrane and leaks could have
penetrated the membrane under the pool."
In August 2005, the body
corporate attempted to address the leaks and had the southern window checked and
re-sealed and the wall on
the exterior sealed and painted. It also removed the
sliding doors and windows that lead onto the pool patio and found that four
extra holes had been drilled into sub-sill and that water could have entered
through these holes. The sub-sill was replaced and
windows and doors resealed.
This should have fixed the leak but as at the date of the submission there had
been no heavy rain since.
I asked the body corporate for a copy of the
engineers’ report referred to by Mr Simes. Burchills responded that there
was
no actual report prepared. However memos dated 18th August 2005
from P.R Bell (Mr Bell), director of Strata, to the body corporate were
provided, detailing meetings about the remedial works to be carried out to the
sill
and the sliding door. It was decided at a meeting on 17th August
2005 to remove the sliding door and glazing frame between the upper level of
Unit 52 and the pool deck after removal of the
sill tiles had been inconclusive
as to the fixing of the subsill. It was suggested that Opat, a Gold Coast
painting and maintenance
firm (Opat) check and provide "an approved
waterproofing detail to the existing hob", and any other work that Opat
thought necessary.
A report dated 29th August 2005
prepared by Mr Bell was sent to the body corporate, with seven photographs
attached, and he advised that on 23rd August 2006, a glazier had
removed the complete frame which revealed as follows -
1. the membrane as
placed had been taken above the level of the concrete hob and sealed to the sub
sill frame.
2. the void between face of kerb and lip of the sub-sill had
been completely filled with sealant
3. extra holes, other than those needed
for fixing, had been drilled in sub sill.
The glazier found that slots
for the drainage of water collecting in the subsill and bottom glazing rail had
been covered up. These
were re-opened prior to and during the remedial works
and had been filled with silicone again by others. Opat was to be engaged
to
do further waterproofing to the hob and the glazier would then fit a new
sub-sill which will again be sealed to the membrane.
In response to
further information sought by me, on 1st February 2007, Burchills
advised the body corporate that the extra holes drilled in the sub-sill
discovered by the glazier " were a direct result of incorrect drilling during
the original construction phase ( approx 1988)."
The report of
29th August 2005 also mentions that there was "free water" on the
underside of the window head to the bedroom and also bubbling was evident
to the
patch in the kitchen ceiling. At that time rainfall had been at a minimum,
and the writer concluded that it was "possible
that a leak may still exist from
the spa". He suggested that the spa be emptied and checked, and then the pool
be emptied and checked.
Mr Simes says that now Lot 51 is experiencing
" some of the same leak problems." The body corporate continues to work
with Burchills and have discussed making a complaint to the Building Services
Authority, but
will first notify Remedial of the body corporate’s
intention and give them 14 days to respond to a specific complaint about
the
integrity of the membrane. However they may have to wait for a wet day for
this. He says "I am of the opinion that some of the water leaking in the
repeating areas is above the membrane area."
Challenge Strata
Management (the body corporate manager) sent in the submission from the
committee. With regard to the three separate outcomes sought, it says that the
Applicants do not
specify how the building, roof, exterior membranes or
improvements do not meet Australian Standards. The building was constructed
in
1988 and met all applicable standards at that time.
The committee is
aware that there was evidence of water penetration into Lot 52 " some years
ago." On investigation in 2003 –
2004, the body corporate spent more than
$125,000 over two years in replacing the roofing membrane and carrying out
remedial works.
The further water penetration which occurred in June 2005
followed torrential rain which was a record "1 in 1,000 year event" and
caused
extensive damage throughout SE Queensland. The issue flowing from the June
2005 rainfall event is that the stormwater system
is not adequately designed in
the event of "significant flood events", to which it says that there is no
evidence that the drainage
system itself is defective, only that in the
Applicants’ view, it may not be adequate for an event that may never
occur.
With regard to the glass panels and sliding doors, the
body corporate points out that these are entirely within the Applicants’
lot, and is therefore not an aperture between a lot and common property and it
is the responsibility of the owner to maintain those
doors and
windows.
The body corporate has commissioned a report from Opat in
respect of this application in an attempt to satisfy itself about whether
the
leak could be wholly from or contributed to by the pool. Opat carried out tests
on 5th and 6th October 2006, doing " minor water tests to
the main deck area." They also tested the sliding doors and windows by
sandbagging them
and filling the area with water for an hour at a time. They
carried out similar tests under the pool area and above the entry door.
Opat’s report dated 16th October 2006 detected no leaks
from these tests. Opat believes that the leaks " manifest after wind driven
and continuous rain," but proposed to undertake further tests flooding
specific areas for longer periods.
Opat says ; "It also appears that
water leaks to the kitchen ceiling is from the swimming pool" and that some
areas of the pool walls are showing signs of leaks. These were to be tested on
the next visits on 31st October 2006 and 3rd November
2006. The body corporate points out that maintenance of the suspended pool is
the responsibility of the Applicants, and
they have not provided any evidence
that the waterproofing membrane of the roof is defective. It says that the
Applicants’
conclusions are hypothetical and uninformed as they themselves
admit. The body corporate took pains to make sure the work was done
properly
by engaging an independent consulting engineer to oversee the work.
The
body corporate provides a copy of the specifications and warranty in respect of
Remedial’s work. Remedial provide a 10
year product and installation
warranty, and on 12th May 2005 by letter to the body corporate noted
that the warranty only included up to and around the existing pool structure,
and
"the existing pool structure was leaking and was still leaking prior to
our completion of the project."
It says that the committee continues
to address every issue raised by the Applicants and will not resile from its
duty to maintain
those parts of the building for which it is responsible. It
denies that the Applicants have sufficiently demonstrated in what way
the body
corporate has failed in its responsibilities.
The Applicants exercised
their right of Reply through their solicitors. They say that the tender
document supplied by Burchills in
2004 stated that the repair to the membrane
was to be in compliance with "any standard or Code" current 14 days before the
submission
of the tender, ie in 2004 and not 1988. They supplied an extract
from the tender document citing clause 5. They say that non-compliance
with
building codes is evident from the Deluca report.
Water
penetration points were assessed by BSW Pty Ltd (BSW) at the direction of
the body corporate, in respect of Lots 51 and 52 in February 2004, prior to the
membrane work being undertaken.
The Applicants in Reply provide a report dated
4th February from BSW. BSW noted that the "external deck is
higher than the internal finished floor level" and that the primary source
of entry "appears to be through the hob." BSW also believed that the
"perimeter upstand details are defective," for both lots and that in
respect of Lot 52, there was also "pipe penetration to..(the)
kitchen."
The Applicants say that the BSW report demonstrated that
the window hobs were leaking before the extreme rainfall event in June 2005.
They also say that the rainfall event in June 2005, was described by www.australiaweathernews.com as
a 1 in 10, to 1 in 30 year flood level and not a one in 1,000 year event, and
that the Building Code of Australia requires designs
to be able to cope with a 1
in 100 year event level, citing part F1 "Damp and Weatherproofing" from page 311
Australian Building
Codes Board BCA 2004 Volume 1. They say that the fact that
such an amount of water enters shows that " the design and/or workmanship
does not cope with torrential rain... with an average recurrence of 1 in 10 to 1
in 30 years." It certainly could not cope with the higher criterion for the
1 in 100 years and "therefore has not been designed and installed to BCA
requirements."
They say that original roof terraced areas were
designed and built with minimal stormwater drainage. During storms and when
using
the pool, water used to run down the outside of the building much to the
annoyance of residents below. The body corporate commissioned
a contractor to
install stormwater drainage to Lots 51 and 52 "and to seal up slots in the
parapets as a solution..." The Applicants have never disputed the original
system or design for stormwater drainage but only this work done by the body
corporate.
The Deluca Report shows that the pipe on the eastern elevation has
‘no grade’ which reduces its ability to remove water,
and the
efficiency of the outlets was further reduced by Remedial overtopping the
membrane . Deluca also found that a bigger freeboard
was required to cope with
a 1 in 100 year rainstorm.
Further, they say that Remedial, Burchills
and Opat are not independent as they do a lot of work for the body corporate.
An independent
hydraulic engineer should assess the problem and report on
compliance with Australian Standards and not a structural engineer.
They would
like to see the manufacturer’s membrane specification from Burchills, and
they refer to Clause 4 of Burchills tender
which says that manufacturers’
specifications will be complied with, and materials will be suitable for the
job.
They point out that they have always remained responsible for the
pool and any substructure on the membrane but the membrane was "originally
integral under the pool" but because of the prohibitive cost the body corporate
decided not to remove the pool and just replace part
of the membrane. There
were originally no leaks under the pool area, but now one has occurred which
they believe is due to faulty
workmanship in the joining of the new membrane to
the remaining membrane. The pool water is present all the time whilst water
penetration
only occurs after rain. The leak under the pool is only one leak,
and does not explain the others. A hose test can make the leak
over the window
in Bedroom 2 active, as demonstrated by the Leak Detective report.
They
still have not got the information which they have requested for the body
corporate about the contract. They believe that the membrane is
still under BSA statutory warranty and the 10 year guarantee given by Remedial.
They cannot tamper with it to see if
it is installed to specification or if
faulty work exists. They are just assuming that the workmanship is faulty
somehow or the
leaks would not be there. No owners should have paid out for
faulty workmanship.
In response to Mr Simes’ overview, which they
found ‘honest and accurate’, they say that the pool walls did have
a number of minor leaks found when they removed the substructure but that there
was no evidence of water penetrating through the
membrane under the pool. They
fixed the leaks and spent $60,000 on refurbishment in December 2004.
They also had the pool and equipment tested for leaks (see Leak Detective
report).
There is now a new and very minor leak which has reappeared in the
pool wall adjacent to the stairs causing only cosmetic deterioration
to the pool
wall. There is no evidence that it is contributing to the leak under the pool.
Regardless of leaks from the pool, the
membrane under the pool should not allow
water penetration. They point out again that water penetration under the pool
only occurs
after rain.
They accept that Remedial could not guarantee the
membrane under the pool since they did not install it but it is the
Applicants’
belief that Remedial "made little or no attempt to ensure a
satisfactory join between the old and new membrane" and it is "hard to
understand the reluctance of the body corporate committee.. in contacting
Remedial," since the leaks have been going on since the work was done by
Remedial and 16 months has elapsed.
With regard to the water penetrating
between the membrane and the door and window frames, the Applicants say that
seal between the
doors and glazing components and frames should be the lot
owner’s responsibility, but the membrane should extend to the inside
face
of window and door frame and the seal between membrane and frame should be
responsibility of body corporate.
Further
information
By letters dated 1st December 2006, I sought
further information from both the Applicants and the body corporate, and in
particular from the body corporate,
the finalised report from Opat. I also
asked Mr and Mrs McDonald, the neighbours of the Applicants in Lot 51 for
further information.
The information was to be provided by 18th
December 2006. All parties sought an extension of time in which to respond,
which was given until 8th January 2007.
The Applicants
responded on 6th January 2007. Mr and Mrs McDonald responded on
6th December 2006 but their fax did not reach this Office until
6th February 2007.
On 20th December 2006, the body
corporate advised by fax that since the body corporate had elected a new
chairman at its November AGM, the
information requested had not been collated
and that it would be dealt with as a priority early in the new year. On
5th January 2007, a further fax was received by this Office from the
body corporate manager saying that Opat’s office was closed
over the
holiday season until 15th January 2007 and that Opat were carrying
out further tests which would start after 15th January 2007, subject
to weather conditions and access to Unit 52. This further report would then be
sent to this Office.
Following a response from this Office that I
required existing reports, this Office was advised by fax on 11th
January 2007, that " the committee is still endeavouring to collate all of
the information requested." On 30th January 2007, this Office
again chased a response from the body corporate, repeating the content of the
letter of 1st December 2006. A response was received on
2nd February 2007, and forwarded to the Applicants to make any
further comment.
From the response from the body corporate, which came
from Burchills, it appears that as at the date of this order, there has been
no
final report from Opat carried out. The Opat tests of 16th October
2006 therefore remain inconclusive. The body corporate says that Lot 52 has not
been accessible as it has been rented out,
but that Opat are awaiting the next
dry period to undertake further tests before 23rd February 2007 and
the next letting. The Applicants deny that their lot has been inaccessible or
that they have been contacted about
finalising the Opat report.
The body
corporate provided a memo dated 19th July 2006 from Rendell Digby,
(Mr Digby) manager of Strata, to Mr Simes and Ian Coldwell headed
"Building Defects- Unit 52" saying that the Deluca report may be "theoretical
(sic) correct but not a practical solution to the condition that existed."
He finds that comments about the height of the membrane are incorrect, "as
was proven when the subsill was replaced." Mr Digby refers to hearsay
statements from the tenant about the smell of chlorine in the kitchen and states
that the "salts evident on the kitchen ceiling were sodium based (crystals),
whilst salts emitted from concrete are usually calcium based (coating
as formed
on balcony outlet.)" Mr Digby says there is no proof that the waterproof
membrane has failed.
The Applicants on 6th January 2007
provided an update on the leaks as at 27th December 2006. They say
there has been very little rain since 11th April 2006, but that after
light rain on 26th and 27th December 2006 all leaks were
dry except leak no.10 which was dripping. However, internal damage had
increased at leaks 1,2,6 and
9. The repairs done at the pool stairs wall seems
to be working because there is no damp below. There is no water going down
behind
the new membrane upturn. The pool remains full of water and number 6
leak below the pool is dry. This leads the Applicants to believe
that the
ongoing leaks are caused by "a capilliary action under the membrane ...
occurring during rain events from a point unknown." Further that damage at
Leak no. 2 indicated that leak was from above rather than from around the
window. This leak is directly below the expansion joint installed by Remedial.
Leaking appears to have ceased at Leak 8 since
the new sill doors were fitted.
Where the original sill to the windows exist ( leak no, 9), there is still
leakage evident.
With regard to Strata’s letter of 18th
August 2005, they say that they believe from observation that Opat "
continued a liquid membrane from the bituminous membrane installed by
Remedial... to the inside face " in accordance with the detail required by
the BCA figure 3.3.4.8 for window installation. However, they do not know
whether the
liquid coating is compatible with the bituminous membrane and that
separation will not occur at this joint and whether the sealant
was installed
either side of the sill in case of any leaking of sill anchors.
With
regard to Strata’s letter of 29th August 2005, they comment on
the five photographs provided by the body corporate. Photo 2 shows the membrane
taken to the top of
the hob but not continued to the inside face of the
building. This allowed water to go over the top of the turn-up during the rain
of June 2005. With regard to photos 4 and 5, they say at no stage have they ever
sealed or opened up the slots in the windowsill
flashings. That was done under
instruction to contractors by the body corporate. With regard to the remark
about the smell of chlorine
in the unit, the Applicants say that the pool is a
salt pool and gives off no smell of chlorine at all. The commentators might
have
smelt Exit Mould and liquid bleach which they use to clean down the mould.
They do continually have to top up the spa, but this
occurs through normal
evaporation and use. The Applicants cannot emphasise enough that leaking only
occurs after rain.
The Applicants have no knowledge of any chemical tests
done on the salts apparent on the kitchen ceiling. The Applicants say that
their own tests indicate that the salt from the drips in bedroom 2 contained
"double the salt content of either the pool or the spa."
They agree
that they cannot provide proof of failure of the membrane, because they
can’t tamper with it. They continue to ask
the body corporate for
documentation to show what works were done, or whether they were done to
specification and the body corporate
has not provided these. They presume that
the information requested does not exist.
I also sought further
information from Mr and Mrs McDonald as to why they thought they would shortly
suffer the same fate as the Applicants.
They say that they purchased Lot
51 in September 1995, and that shortly after acquiring it, they "began to
experience water penetration to the bedroom area, which in turn, caused damage
to the ceilings and cornices." They approached the body corporate manager
and the body corporate contractor " simply painted a large area of the
ceramic tiles with white waterproofing compound, which prevented the leaking but
which was visually
unsightly." This was a stop-gap solution, because
the McDonalds intended to modernise the roof. They think that the membrane
under the tiles
"had failed" at the time. Later there was further leaking around
the internal chimney. They cannot recall suffering any damage on
30th
June 2005. They think they will have to ask the BC to replace the membrane "in
the not too distant future," but they do not elaborate
on why this should
be.
DETERMINATION
In this matter it is not disputed
that there are, or have been, 11 specified areas of water ingress into the
Applicant’s unit
at Lot 52. Clearly, these leaks are not acceptable to the
Applicants and interfere with the quality of their enjoyment of their property.
The matters in dispute concern the cause of the various leaks, and the
responsibility for repairing or preventing those leaks, and
this is complicated
by the fact that the same leaks have been occurring to a greater or lesser
degree since the time the Applicants
purchased Lot 52, and possibly before that
time.
It is accepted by the parties to the dispute that there were
"on-going problems with the penthouse roofs" at least from 2000, and
the
Applicants noticed damp patches inside the kitchen of Lot 52 at the time of
purchasing it in 1996.
In February 2004, Mark Anttilla (Mr
Anttilla) of BSW Pty Ltd engaged by the body corporate carried out 6 tests
on the roof of the Applicants’ lot. Mr Anttilla found that
by flooding
areas of the roof, he could make water appear on the interior of the
Appellant’s lot at the lounge window, inside
the tile joints inside the
slider door by the pool, in the kitchen from the stink pipe, and in the bedroom
from the BBQ area. He
was unable to confirm penetration in other areas,
although there were visual signs of water ingress. He also noted that the
external
deck was higher than the internal finished floor in both units 51 and
52, and that the primary source of water ingress appears to
be through the hob.
He believed that the upstand details were defective.
By April 2004,
Burchills had been involved, and a contract drafted between a contractor,
Burchills as superintendent and the body
corporate as principal. Remedial
tendered for the contract in August 2004. At some time between August and the
end of November 2004, the body corporate made extensive repairs to the
roof of Lot 52, following meetings with the Applicants and listing their
complaints
about water ingress.
The body corporate replaced the
roofing membrane of the eastern part of the patio, but it was agreed with the
Applicants that it would
cost the body corporate too much to redo the whole roof
which would require the removal of the Applicants’ swimming pool and
replacement of the membrane under the pool. The Applicant William Butler is a
builder and was aware that the join between the two
membranes could be an area
of future susceptibility. In a letter dated 8th November 2004 to
Burchill, he said :
"As the existing membrane extends under the pool
(Pool built on top of membrane) we accept that the cost to remove and replace
the
Pool to allow membrane under to be replaced would be prohibitive. However,
attention should be given to sealing new membrane under
pool before any turn up
around pool is undertaken."
Mr Symes, mentions this letter and says
that "during the repairs" it was found that the pool was leaking, and that the
Applicants
acknowledged that there were defects in the pool walls and said they
intended to repair them. This information was apparently in
a letter dated
19th November 2004 from the Applicants to the body corporate with
which I have not been provided. Remedial refers to this incident in
its
warranty dated 12th May 2005, which carries the rather ambiguous note
-
"Prior to installation of the membrane we informed the body corporate
that the existing pool structure was leaking and was still
leaking prior
to our completion of the project." (my underlining)
The Applicants,
however, deny that there was ever any evidence of any water penetration through
the membrane under the pool, even
though with the removal of the substructure, a
number of minor leaks were evident in the pool wall which were subsequently
repaired
and tested satisfactorily by them.
The body corporate also
tackled the "primary source of water ingress" being the leaks around or through
the fitting of the large glazed
windows and the sliding door onto the roof. (
leaks 8 and 9).
The Applicants say Burchills certified that the work was
"complete and free from defect" on 1st December 2004. I have
not seen those words in any document produced to me. In fact, the body
corporate received a Practical Completion Certificate on 1st December
2004 certified by the same Mr Bell who is a director of Strata. Mr Bell is a
registered professional engineer and managing
director of "belleng Pty Ltd" and
certified the work as being " generally in accordance with our approved
documentation and therefore acceptable to be classed as practically
completed" with a defects liability period of 26 weeks ending on
1st June 2005.
Strata is a division of Burchills, and on
1st February 2007 in responding to my letter to the body corporate,
Mr Bell signed as "Principal, Body Corporate Services" for Strata.
Clearly, the
Certificate of Practical Completion is not a document produced by an independent
inspector, but is merely a formal
note of the finalisation of the
contract.
However, the Applicants fax to the body corporate manager on
9th December 2004 make it clear that the contract had not in fact
been competed. In addition, the membrane had not been tested, before
tiles had
been laid on top of it. The Applicants noticed a new leak below the pool
area, appearing in the kitchen ceiling (leak
6) at Easter 2005, and then on
30th June 2005, a torrential rainstorm caused leaks as detailed.
Their complaints resulted in further remedial work being undertaken by
the body
corporate to the fitting and sealing of the sliding door and window in July and
August 2005, and the Applicants engaging
the Leak Detective and Deluca in
respect of the cause of the leaks.
The outsiders brought into this matter
by the Applicants to prepare reports have concluded that the water was "leaking
past the waterproof
membrane" and that that the waterproof membrane in this area
had failed; (Leak Detective – November 2006); that the pool itself
was not
leaking ( Leak Detective – November 2006); that the outlets for water
escaping from the roof were inadequate and blocked,
and the design of the roof
provided insufficient freeboard for floodwater (Deluca – February 2006).
Following the lodging of this application, the body corporate asked Opat
to report in October 2006. Opat detected no leaks from their
water testing on
the roof but "it would appear that the leaks manifest after wind
driven and continuous rain." Perhaps Opat is simply stating here what it
had been told. However their testing and report was incomplete, and they were
unable
to test the theory that the leak in the kitchen ceiling was caused by
poolwater.
The body corporate does not deny that the leaks continue to
occur but says that those that occur within the Applicants’ lot
must be
addressed by the Applicants, and that the Applicants have not demonstrated that
the body corporate has failed in its duties.
I understand that talks between
the body corporate and the Applicants, and other lot owners, continue as to the
best way to resolve
the problem. I also understand that Leak 8 has now possibly
been fixed by remedial works done by the body corporate and the new
flashing
being affixed to the sill.
The Applicants have various theories as to why
the leaks occur: that the new membrane was defective or not installed properly,
in
which case the parties can turn to the guarantees from Remedial; that the new
membrane was never or incorrectly or insufficiently
joined to the remaining
membrane under the pool; or that rain and wind-driven water is overtopping the
membrane which has an insufficient
seal to door and window subsills.
The body corporate suspects that at least leak 6 is caused by the pool
leaking and that therefore the leak is the responsibility of
the Applicant
owners. Its theories are that that the membrane under the pool is now leaking
and allowing passage of rainwater; or
that the membrane under the pool is
leaking spilled poolwater from leaks in the walls of the pool or spa. It gives
no explanation
for the leaks at 8 and 9 (although I asked it to do so) but has
detailed instead a history of the repairs undertaken. It has re-sealed
the
window and sliding door, painted a liquid membrane up to the edge of the
bituminous one installed by Remedial in 2004 from the
top of the hob into the
inside face, and unsealed drain holes in the sill
All these theories
concern the new or existing membrane.
I am of the view that even if the
Applicants’ pool is leaking, I cannot see why the responsibility should be
that of the Applicants’.
Spilled pool water should not pass through
either the existing membrane or the new membrane. Unless it can be shown that
the Applicants
have damaged the under-pool membrane or the new membrane, or
tampered with the join between the two in some way, the responsibility
for a
roofing membrane does not shift from the body corporate.
Section
109 Standard Module states in full ( with my underlining) –
109 Duties of body corporate about common
property--Act,
s 152
(1) The body corporate must maintain common property in good condition, including, to the extent that common property is structural in nature, in a structurally sound condition.
(2) To the extent that lots included in the scheme are created under a building format plan of subdivision, the body corporate must--
(a) maintain in good condition--
(i) railings, parapets and balustrades on (whether precisely, or for all practical purposes) the boundary of a lot and common property; and
(ii) doors, windows and associated fittings situated in a boundary wall separating a lot from common property; and
(iii) roofing membranes that are not common property but that provide protection for lots or common property; and
(b) maintain the following elements of scheme land that are not common property in a structurally sound condition--
(i) foundation structures;
(ii) roofing structures providing protection;
(iii) essential supporting framework, including load-bearing walls.
(3) Despite anything in subsections (1) and (2)--
(a) the body corporate is not responsible for maintaining fixtures or fittings installed by the occupier of a lot if they were installed for the occupier’s own benefit; and
(b) the owner of the lot is responsible for maintaining utility infrastructure, including utility infrastructure situated on common property, in good order and condition, to the extent that the utility infrastructure--
(i) relates only to supplying utility services to a particular lot; and
(ii) is 1 of the following types--
• hot-water systems
• washing machines
• clothes dryers
• another device providing a utility service to a lot;
and
Examples for subsection (3)(b)--
1 An airconditioning
plant is installed on the common property, but relates only to supplying utility
services to a particular lot.
The owner of the lot would be responsible for
maintaining the airconditioning equipment.
2 A hot-water system is
installed on the common property, but supplies water only to a particular lot.
The owner of the lot would
be responsible for maintaining the hot-water system
and the associated pipes and wiring.
(c) the owner of the lot is responsible for maintaining the tray of a
shower that services the lot, whether or not the tray forms
part of the
lot.
(4) To avoid doubt, it is declared that, despite an obligation
the body corporate may have under subsection (2) to maintain a part
of a lot in
good condition or in a structurally sound condition, the body corporate may
recover the prescribed costs, as a debt,
from a person (whether or not the owner
of the lot) whose actions cause or contribute to damage or deterioration of the
part of the
lot.
(5) In this section--
prescribed costs
means the proportion of the reasonable cost to the body corporate of
carrying out the maintenance that can, in the body corporate’s
reasonable
opinion, be fairly attributed to the person’s actions.
The
roofing membrane is not common property. It is within the Applicants’ lot
as has been pointed out, but it is a roofing membrane
that provides protection
to lots, ultimately to all lots, as submitters Mr and Mrs Toomey point out, and
comes squarely within section 109(2)(a)(iii) Standard Module.
I do not think that the body corporate denies that it is responsible for the
maintenance and good condition of the membrane. This
is why the repairs in 2004
were undertaken by the body corporate. However, there is some concern as to
whether the membrane remains
the responsibility of the body corporate when it
joins seals around windows and doors within the owner’s lot, or passes
over
hobs within the owner’s lot. In my view it would be a nonsence if
the body corporate was not responsible for the correct
joining of the membrane
to such point in the interior of a lot where sufficient protection is provided
to lots or common property.
The fact that water comes through a roofing
membrane, at whatever point, so that lots receive ingress of water, will always
be
the responsibility of the body corporate ( in a building format plan) barring
damage by another person. In that case, the body corporate
must still repair the
damage, but may recover costs from the person who has caused the damage.
(Section 109(4) Standard Module.)
However, it is not agreed that
the membrane is faulty. Water ingress may be caused by overtopping of the
membrane, because the design
of the roof is insufficient to cope with severe
rain, or the design of the roof coupled with the height of the sills, the
blocking
of the overflow outlets, or the drilling of holes under the sub sill
may all play a part. Section 109(2)(b)(ii) provides that the body
corporate is responsible for maintaining roofing structures providing protection
in good condition. As such,
the overflow channels should be kept clear and
serviceable, and any holes drilled by the original builders where they allow
water
to enter, should be sealed properly.
It may be that the body
corporate is stuck with poor roof-top design from the original owner, or with a
badly constructed building.
I have no jurisdiction over this, and believe that
civil action to remedy poor workmanship or design would now not be successful
after 19 years. The body corporate remains responsible unfortunately, to
maintain a poorly constructed or badly designed building,
and the burden does
not shift to the nearest or most affected lot owner.
It has not been
suggested by the body corporate (or the Applicants) that any of the leaks occur
because rainwater is simply blowing
into a shaft or under an ill fitting door or
window. All the theories and exploratory repairs have looked at the integrity
of the
membrane and the sealing of the edge of the membrane over the hob into
the interior of the lot.
In respect of the leaks occurring near
ventilator shafts ( leaks 4 and 7) I would add that if these shafts are "utility
infrastructure"
as defined at section 20 Act and the definition of
"utility infrastructure" in Schedule 6 Act , that is, if they serve more
than one lot, then they are common property even if they are within the boundary
of an owner’s
lot and therefore the responsibility of the body corporate
to maintain by virtue of section 109 (1) as set out above. If however,
they fall within the exception to section 20 Act, that is, they service
only one lot (and are within an owner’s lot, and not within a boundary
structure of an owner’s
lot) then maintenance of such ventilator shafts
would be the responsibility of the lot owner.
I am assuming that if the
leaks at 4 and 7 were caused simply by rain blowing into a vent ( as opposed to
rain seeping between a vent
fitting and the roof which is a description given by
the Applicants) then this matter would not have gone on for such a long time.
The same applies to the leaks at 8 and 9. Where section 109 Standard
Module does not apply, the lot owner would be responsible for maintenance within
his own lot.
I cannot say what is causing the leaks any more than those
involved seem to be able to do. However, in the scenarios which have been
proposed, all of which concern the integrity of roof membranes or the structure
of the building albeit within the Applicants’
lot, I cannot find a way in
which the Applicants would be responsible for the leaks as described, bar
deliberate damage.
Deliberate damage
Deluca found that a
small overflow channel on the roof had been plugged. There is no evidence as to
who may have done this, although
the Applicants say that the body corporate
sealed up slots in the parapet to stop water running down the outside of the
building.
I do not have information about when that was. There was also some
evidence given by Strata that slots for the drainage of water
in the subsill of
the sliding door had been filled with silicone after being re-opened at the time
the new membrane was laid in 2004.
The Applicants deny that they have ever
sealed or unsealed these slots. In any event, there is no evidence that this
filling contributed
to the ingress of water. Additional holes found under the
subsill were also put forward as suspects for the ingress of water by
Mr Simes,
but Burchills say that these holes occurred during the original building in
1988, although they do not say how they know
this.
Compliance with
the BCA
Equally, there is no proof that the building was not
constructed in accordance with building codes relevant in 1988, or that the BCA
was breached in 2004 by Remedial. The Building Code of Australia states general
objectives and makes functional statements which
are to be used as an aid to
interpretation of the BCA and not for determining
compliance.[1] The Applicants
propose various Australian Standards which have been compromised or not complied
with, but there is no independent
evidence of such failures, and the Applicants
acknowledge that they are surmising why their roof leaks as they have not been
able
to investigate fully.
The Applicants say that the Deluca report
shows that the roof does not comply with certain Australian Standards as
required by the
BCA, (although they do not identify which Australian Standard or
Standards those are). In my view, Deluca does not quite say this.
It just says
that the BCA requires that any roof design be able safely to convey discharge
from a storm of ARI 100 magnitude and
should have a freeboard of 30mm above the
water design level, but that in the case of this roof, because of exposure to
"extreme
wind conditions" that a freeboard of 50mm be
adopted.
Ongoing repairs
Leaks at points 8 and 9 have
been occurring since at least 2003, and were part of the reason for the new
membrane being fitted in
2004. These leaks have never been fixed ( although
there is some hope for Leak 8 now apparently.) Leaks 2,4,5 and 7 were also
"original
leaks" and remain unresolved by the body corporate’s efforts in
2004. Leaks 1,6,10 and 11 are new leaks since the storm on
30th June
2005 when the new membrane was already in place. There is insufficient
information about Leak 3.
There is certainly room in my view for the body
corporate to return to the terms of the contract with Remedial concerning the
testing
of the membrane prior to being covered up which the Applicants noted at
the time was not done. The body corporate (and Remedial)
also might like to
explore the terms of the warranties for product and installation. These
warranties were provided to the body
corporate in May 2005. At that time the
original leaks had still not been rectified and new leaks had appeared. The body
corporate
should immediately have notified Remedial that it was not satisfied
with the work, and/or that further work was required. Burchills
organised
further repairs in August 2005, but told the body corporate they were not
responsible for the new leaks appearing, and
started to suggest other reason for
the leaks. At this point, I find that the body corporate, having spent a lot of
money on a disappointing
outcome, failed to get a satisfactory response out of
its contractor. It misguidedly looked instead at the fact that all the leaks
were occurring within the Applicants’ lot, and were deflected by the idea
that the Applicants’ pool or spa might be leaking,
even though such leaks,
if they existed, should not be able to penetrate a waterproof roof membrane for
which the body corporate
is responsible.
I also find that the body
corporate has dragged its feet in this application and that the Applicants have
not been provided with documents
which they have
requested.
Order
The body corporate is responsible for
making sure that water from any source does not penetrate the Applicants’
lot through
the roof membrane, or over the top of an existing roof membrane, or
through the fabric of the roof structure. To this end it should
immediately go
through the terms of the contract with Burchills and Remedial. Points to be
explored in the contract should include
the allegation of the failure to
watertest the membrane before it was covered; and whether the
manufacturer’s recommendations
were followed. I understand that the
Building Services Authority may have a role in a complaint laid against
Remedial, as suggested
by Mr Simes.
If Remedial is not willing to act
under the warranty, or cannot rectify the remaining leaks under the cover if the
warranty, or cannot
rectify the remaining leaks without changes being made to
the design of the roof, the body corporate must within 3 months of the
date of
this order instruct an engineer, who is not part of the
Burchills/Strata/Remedial group and who is properly qualified in
the
rectification of water ingress into buildings, and whose qualifications are
acceptable to the Applicants, to report on the reasons
for water ingress, and
the method in which those defects should be rectified. Without casting any
aspersions on the persons who
have made reports which have been discussed in
this application, none of them have given ( or I have not been provided with)
their
qualifications or their expertise variously in leak detection, salts
analysis, hydraulic design, or construction detailing.
Within one month
from the receipt of the report, the body corporate is to seek at least two
quotations for the rectification work
recommended by the engineer and put the
quotations as a motion to a general meeting of the body corporate as a motion in
the alternative.
The body corporate has an obligation to maintain the
membrane(s) and roofing structures in sound condition.
The chosen
engineer may also report on Lot 51 at the same time if the body corporate so
wishes, but I do not make that part of the
order.
I have not been
provided with any quotations but there is some suggestion by the submitters,
that something of this nature has already
been proposed. The figure of $50,000
has been mentioned but I do not know where this has come from. I find that all
the submitters,
and the Applicants have been honest and helpful in their
presentation of a difficult problem, and trust that progress can now be
made
since the body corporate knows where its responsibilities lie.
The body
corporate should also recall the relevant contractors to replace the damaged
floor tile in the Applicants’ unit which
was damaged during the repairs in
August 2005, and to match the grout with the existing tile grout. In my view
that repair should
be done free of charge, but that is a matter for the body
corporate to orchestrate. Meanwhile, the Applicants, on payment of the
requisite fee for photocopying, and in accordance with Section 205 Act
and Section 151 Standard Module, should be provided with all documents
relating to the contract, and any correspondence on the body corporate records
which they may wish to see.
[1] BCA 2004 Vol 1
"Introduction."
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2007/171.html