![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 2 April 2007
REFERENCE: 0313-2006
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
11646
|
|
Name of Scheme:
|
Galen House
|
|
Address of Scheme:
|
142 Queen Street SOUTHPORT QLD 4215
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Janette and John Watson, the owner and occupiers of Lot 1
|
I hereby order that within four weeks of the date of this order,
Amalgamated Megadynamics Pty Ltd, the owner of Lot 2, shall pay to the Body
Corporate
the amount of $2,435.90, being 50% of the cost of the variation to the
building contract with All-Ways Handy Home Maintenance Services.
I further order that the application is otherwise dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0313-2006
"Galen House" CTS 11646
Galen House community titles scheme (Galen House) consists of two
lots and common property. The community management statement for Galen House
indicates that the Body Corporate and Community Management (Standard Module)
Regulation 1997 (Standard Module) applies to the scheme. Department
of Natural Resources Mines and Water records show the scheme is registered as
Building Units
Plan 3518.
APPLICATION
This application
was made by Jeanette Watson, as owner and occupier of Lot 1, and John Watson as
occupier of Lot 1 (applicants) on 28 April 2006 under the Body
Corporate and Community Management Act 1997 (Act). The applicant
sought orders against Rodney Tracey, the director of Amalgamated Megadymanics
Pty Ltd, the owner of Lot 2 (respondent) in the following terms:
Payment of outstanding bills for repairs under the direction of Gold Coast
City Council to repair multiple defects in building including
external staircase
and guttering. During reconstruction further defects were found. Dr Tracey was
notified and did not object to
further repairs. Outstanding accounts amount to
$4,871.79. There are outstanding accounts for previous sewerage repairs which
amount
to $5,914.87
PROCEDURAL MATTERS
In May the
Commissioner’s Office contacted the parties in an attempt to arrange
conciliation to assist in the resolution of
this dispute. Regrettably the
parties could not agree to the terms of a conciliation session.
Under
section 243 of the Act, a copy of the application was provided to the
respondent with an invitation to respond to the matters raised in the
application.
A submission was made on behalf of the respondent. The applicant
did not avail themselves of the opportunity to inspect and respond
to the
submission received (see sections 246 and 244 of the Act
respectively).
A dispute resolution recommendation was made referring the
dispute to departmental adjudication.
JURISDICTION
I am
satisfied that this is a matter which falls within the dispute resolution
provisions of the legislation (see sections 227, 228, 276 and Schedule
5 of the Act).
Section 276(1) of the Act provides that an
adjudicator may make an order that is just and equitable in the circumstances
(including a declaratory
order) to resolve a dispute, in the context of a
community titles scheme, about:
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about -
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
MATTERS IN
DISPUTE
This scheme is a duplex. It appears there is a history of
communication and personality issues between the owners and occupiers.
The
application relates to the cost of repairs to the scheme building. The facts of
the dispute, as outlined in the application
and submission can be summarised as
follows.
The applicants assert that the building was in urgent need of
repair and that the respondent was uncooperative in progressing the
repairs.
The applicants obtained a quote from a registered builder (Frank Cowell of
All-Ways Handy Home Maintenance Services).
The respondent claims the matter was
being discussed and that after obtaining a different quote which he felt was
inappropriate,
he was obtaining other quotes.
The applicants sought
advice from the Gold Coast City Council (GCCC) in mid-February. On 28
February 2006 the GCCC notified the Body Corporate that it was required to
replace or repair the building’s
external balcony and staircase and
replace the gutters and downpipes. The notice required this work to be
completed by 30 March
2005 (presumably intended to be 30 March 2006).
The
quote from Cowell dated 15 February 2006 was for $13,745.60. The respondent
obtained a quote from Dean Marshall dated 20 February
2006 which was
significantly lower. However the deadline imposed by the GCCC was apparently
unable to be met by Dean Marshall and
the Body Corporate accepted the quote from
Cowell. An initial contract was drawn up by Cowell for the quoted $13,745.60.
It seems
respondent apparently requested additional works but rejected the cost
of the revised contract. The second contract reinstated the
original
provisions, and was signed by both owners on 13 March 2006.
The
respondent argues that Cowell was a friend of the applicants and that a letter
from Cowell indicates an agreement between the
applicants and Cowell that he
would deal only with the applicants and not the respondent. An unsolicited
letter from Cowell to this
Office suggests that he requested only one point of
contact. The applicants claim that the respondent was kept informed throughout
the process.
During construction, further defects were identified. This
apparently meant that the gutter brackets needed to be repositioned and
the
barge tiles needed to be refixed and painted. This increased the cost of the
work. A Building Services Authority contract variation
detailed this change and
was signed by the builder but not by anyone representing the Body Corporate.
The applicants state that
Cowell rang them to discuss the problems and to
explain that the work could not proceed without the variation. Janette Watson
says
she gave Cowell her approval but said she would need to discuss it with the
respondent. She says she rang the respondent and he
said he would discuss it
with the builders. Apparently they explained the problem and took him onto the
roof to look at it. As
the respondent did not contact the applicants again or
make any attempt to contact Cowell or to delay or defer the work Janette Watson
says she assumed he was happy for the work to proceed.
The original
contract sum was paid by the Body Corporate on 3 and 24 April 2006. The work
was completed on 10 April 2006. The variation
amount of $4,718.79 was paid by
John Watson in early July. The applicants have sought reimbursement from the
respondent of 50% of
these works.
The application alleges that the
respondent has an attitude of ‘if you want it, you pay for it’.
They assert that John
Watson has previously paid for a number of items which it
appears they believe were the responsibility of the Body Corporate but
which the
respondent had refused to act in respect of. This includes:
- sewerage works undertaken at a cost of $5,914.87;
- security lighting;
- repairs to the external wall of the applicant’s unit caused when a patient backed their car into it; and
- construction of a protective fence to prevent patients backing their cars into the building.
The respondent argues that the builder has been paid in full for the contracted price, and that his own financial obligations to the Body Corporate have been paid fully and on time. He also states:
- The dispute is between the Body Corporate and the builder. - He agreed that the barge tiles needed to be repointed and rescrewed but that was the only work beyond the contracted work that he agreed to. He has apparently obtained estimates for this work from other builders which are in the region of $600-700. - He asked Cowell for a detailed invoice for the additional work but it has not been received. - A council inspector looked at the work and told him the rear downpipe does not meet council requirements. - He was informed by the Building Services Authority that the written variation only applied if it was accepted by the Body Corporate and signed by all parties. Because the variation was not seen by the Committee the original contract stands. - The purported variation was signed by Cowell on 11 April 2006 but no mentioned was made of it at the Body Corporate meeting on 24 April 2006. - Janette Watson has refused to countersign any Body Corporate cheques necessary for the day to day running of the Body Corporate and as a result the respondent has had to pay the handyman gardener from his own funds at a cost of $50 per week. - The sewerage and security lighting issues were resolved in a previous adjudication and this is the first time he has seen mention of the figure of $5,914.87.
DETERMINATION
This
dispute centres on the obligations of the respondent to contribute to the cost
of building repairs that were undertaken subject
to a variation to the building
contract.
Responsibility for and approval for
maintenance
It is important that both owners are clearly aware of the
maintenance responsibilities of owners and the Body Corporate.
Section 120 provides that the owner of a lot included in
the scheme must maintain the lot in good condition. Section 109 of the
Standard Module (as follows) requires a body corporate to maintain common
property. In the case of a building format plan
(which this scheme is), the
boundary of a lot with common property or another lot is the centre of the wall,
floor or ceiling.
109 Duties of body corporate about common property--Act, s 152
(1) The body corporate must maintain common property in good condition, including, to the extent that common property is structural in nature, in a structurally sound condition.
(2) To the extent that lots included in the scheme are created under a building format plan of subdivision, the body corporate must--
(a) maintain in good condition--
(i) railings, parapets and balustrades on (whether precisely, or for all practical purposes) the boundary of a lot and common property; and
(ii) doors, windows and associated fittings situated in a boundary wall separating a lot from common property; and
(iii) roofing membranes that are not common property but that provide protection for lots or common property; and
(b) maintain the following elements of scheme land that are not common property in a structurally sound condition--
(i) foundation structures;
(ii) roofing or other covering structures providing protection;
(iii) essential supporting framework, including load-bearing walls.
(3) Despite anything in subsections (1) and (2)--
(a) the body corporate is not responsible for maintaining fixtures or fittings installed by the occupier of a lot if they were installed for the occupier’s own benefit; and
(b) the owner of the lot is responsible for maintaining utility infrastructure in good order and condition, to the extent that the utility infrastructure--
(i) relates only to supplying utility services to a particular lot; and
(ii) is 1 of the following types--
• hot-water systems
• washing machines
• clothes dryers
• another device providing a utility service of a domestic nature to a lot.
Examples for subsection (3)(b)--
1. An airconditioning plant is installed on the common property, but relates only to supplying utility services to a particular lot. The owner of the lot would be responsible for maintaining the airconditioning equipment.
2. A hot-water system is installed on the common property, but supplies water only to a particular lot. The owner of the lot would be responsible for maintaining the hot-water system and the associated pipes and wiring.
(4) To avoid doubt, it is declared that, despite an
obligation the body corporate may have under subsection (2) to maintain a part
of
a lot in good condition or in a structurally sound condition, the body
corporate is not prevented from recovering an amount of damages
from a person
(whether or not the owner of the lot) whose actions cause or contribute to
damage or deterioration of the part of the
lot.
The parties do not
appear to dispute that the repairs were to common property. Accordingly, to the
extent that the work was necessary,
it was a Body Corporate
responsibility.
A Body Corporate may have a range of competing demands on
its expenditure and owners may have different views on the priority of various
maintenance tasks. However the Body Corporate’s legislative
responsibility to maintain common property in good condition is
a duty that
cannot be avoided or deferred. Where maintenance is required the Body Corporate
must raise sufficient funds (by contributions
from its members) to ensure that
all necessary work is undertaken.
Any time that an owner considers an
item of maintenance is required, the appropriate course of action is to obtain
one or more quotes
(depending on the value of the work) and submit them to a
committee or general meeting (depending on the type and value of the work)
for
approval along with a motion for a special levy if the cost of the work has not
been budgeted for[1]. It is not
evident that the applicants took this step when they first sought to pursue
their concerns.
For the information of the parties I have outlined the
relevant provisions regarding the authorisation needed by the Committee or
the
Body Corporate to spend Body Corporate funds:
103 Spending by committee
(1) The committee may only carry out a proposal involving spending above the relevant limit for committee spending for the scheme if--
(a) the spending is specifically authorised by ordinary resolution of the body corporate; or
(b) the owners of all lots included in the scheme have given written consent; or
(c) an adjudicator is satisfied that the spending is required to meet an emergency and authorises it under an order made under the dispute resolution provisions; or
(d) the spending is necessary to comply with--
(i) a statutory order or notice given to the body corporate; or
(ii) the order of an adjudicator; or
(iii) the judgment or order of a court.
(2) For this section, if a series of proposals forms a single project, the cost of carrying out any 1 of the proposals is taken to be more than the relevant limit for committee spending if the cost of the project, as a whole, is more than the relevant limit.
(3) Section 104 applies to the proposal in addition to this section if--
(a) subsection (1)(a) or (b) applies in relation to the proposal; and
(b) the proposal involves spending above the relevant limit for major spending; and
(c) the proposal does not involve spending mentioned in subsection (1)(c) or (d).
104 Quotes for major spending
(1) This section applies if--
(a) a motion to be moved at a general meeting of the body corporate proposes the carrying out of work or the acquisition of personal property or services, including the engagement of a body corporate manager or service contractor, but not including the engagement of a service contractor who also is, or is to be, a letting agent; and
(b) the cost of carrying the proposal into effect is more than the relevant limit for major spending for the scheme.
(2) The lot owners must be given copies of at least 2 quotations for carrying out the work or supplying the personal property or services.
(3) If the motion is proposed by the committee, the committee must obtain the quotations.
(4) If the motion is not proposed by the committee, the person proposing the motion must obtain the quotations and give them to the secretary.
(5) Copies of the quotations or, if voluminous, summaries of the quotations and advice about where the complete documents may be inspected, must accompany the notice of the meeting at which the motion is to be considered.
(6) If, for exceptional reasons, it is not practicable to obtain 2 quotations, a single quotation must be obtained and must\ accompany the notice of meeting.
Example--
If goods to be acquired by the body corporate are obtainable from only 1 source, a quotation for supplying the goods must be obtained from the source and circulated with the notice of meeting. The fact that goods with the necessary characteristics are only obtainable from a single source would be an exceptional reason for not obtaining 2 quotations for the supply of the goods.
(7) Unless subsection (6) applies, the motion must be stated as a motion with alternatives in the agenda and on a voting paper for the meeting.
(8) Each quotation obtained under this section must be retained as an attachment to the minutes of the meeting at which the quotation is considered.
(9) For this section--
(a) the cost of engaging a body corporate manager or a service contractor includes any payment for the body corporate manager’s or the service contractor’s services, provided for under the engagement, for the term of any right or option of extension or renewal of the engagement; and
(b) if a series of proposals forms a single project, the cost of carrying
out any 1 of the proposals is taken to be more than the
relevant limit for major
spending for the scheme if the cost of the project, as a whole, is more than the
relevant limit.
The relevant major spending limit for this Body
Corporate is $500 (two lots x $250). This means that in most cases if the Body
Corporate
wishes to spend more than $500 on anything, two or more quotes are
required and the spending must normally be approved by a resolution
at general
meeting, unless both owners have given written consent.
Notwithstanding
these usual requirements, the committee may approve spending that is above the
major spending limit and without the
need for multiple quotes, in certain narrow
circumstances. One of these circumstances is if the spending is necessary to
comply
with a statutory order or notice given to the body
corporate.
Need for and approval of the original contract
Given the GCCC notice, there is no doubt that the work which was the
subject of the original contract was necessary. Two quotes were
obtained but
the cheaper quote was not acceptable because of the time constraints. Pursuant
to section 103(1)(d)(i) of the Standard Module, as the expenditure was
necessary to comply with a statutory enforcement notice from GCCC, it could be
carried
out by the Committee and so in fact multiple quotes were not required.
The respondent has raised issues about the selection of the builder but
the fact remains that both owners agreed to accept the quote
and sign the
original contract. There is no indication that the respondent sought to contact
the GCCC to seek an extension of time
to enable alternatives quotes to be sought
or that he asked the applicants to consider waiting while alternative quotes
were sought.
Regardless, he chose to agree to the builder and the quote.
The
respondent also complains the builder would only communicate with the
applicants. Nothing prevents a body corporate engaging
a friend to do work and
I consider it reasonable for a contractor to want only one point of contact. It
is not the builder’s
role to negotiate between the owners. However the
onus is on the applicants to communicate fully with the respondents. Even as
a
committee member, Janette Watson has no independent decision-making authority
for the Body Corporate. She can only carry out formal
decisions of the
Committee or Body Corporate.
Unfortunately it does not appear that the
parties have formally minuted their decision to accept this quote. However as
both owners
have signed the contract I accept it was a clear decision. While
the onus is on the secretary, both committee members should ensure that
in future all meetings are appropriately minuted. This will assist in avoiding
disputes of
this type. I bring the parties’ attention to section
36 of the Standard Module[2] which
provides:
36 Minutes and other records of committee
(1) The committee must ensure--
(a) full and accurate minutes of its meetings are taken; and
(b) a full and accurate record is kept of each motion voted on other than at a meeting.
(2) The secretary must give a copy of the minutes of each meeting and of any resolution voted on other than at a meeting to the following persons--
(a) each member of the committee;
(b) each lot owner who is not a member of the committee.
(3) Subsection (2)(b) does not apply to a lot owner who--
(a) has given the secretary a written notice instructing the secretary that the lot owner does not wish to be given copies of the minutes of committee meetings and resolutions voted on other than at meetings; and
(b) has not withdrawn the instruction.
(4) The copy must be given to the person--
(a) within 21 days after--
(i) for a copy of minutes of a meeting--the holding of the meeting; or
(ii) for a copy of a resolution voted on other than at a meeting--the passing of the resolution; and
(b) in 1 of the following ways--
(i) by handing it to the person;
(ii) by sending it by mail;
(iii) by sending it by facsimile;
(iv) by sending it electronically.
(5) In this section--
full and accurate minutes, of a meeting, means minutes including each of the following--
(a) the date, time and place of the meeting;
(b) the names of persons present and details of the capacity in which they attended the meeting;
(c) details of proxies tabled;
(d) the words of each question decided;
(e) the number of votes for and against each question decided;
(f) details of correspondence, reports, notices or other documents tabled;
(g) the time the meeting closed;
(h) details of the next scheduled meeting;
(i) the secretary’s name and contact address.
full and accurate record, of a motion voted on other than at a meeting, means a record including each of the following--
(a) the date notice of the motion was given;
(b) the names of the committee members to whom notice was given;
(c) the words of the motion voted on;
(d) the names of the committee members who voted on the motion;
(e) the number of votes for and against the motion.
Need for and
approval of the contract variation
There were two components to the
building contract variation – the gutters and the barge tiles. The
respondent claims that
he agreed that the work on the barge tiles was necessary,
but he says this was the only work required beyond the contracted work.
He does
not comment on why he considers the variation for guttering was not necessary.
The original contract clearly intended to
replace the guttering and the
respondent agreed to that. It may be that the respondent is of the view that if
the original contract
provided for the replacement of guttering, the contractor
should replace the guttering for the original price even if it became apparent
after the job commenced that the work involved in replacing the gutters would be
significantly greater than first estimated. Unfortunately
this is not
necessarily the way building quotes and contracts work.
The GCCC clearly
required the gutters to be replaced and I have received no evidence to suggest
that the reposition of the gutter
brackets and strengthening and/or packing out
of the gutter fixing points was not necessary to complete the replacement of the
gutters.
Accordingly, I am satisfied in general terms that the work which was
the subject of the contract variation was necessary in respect
of the Body
Corporate’s maintenance responsibilities.
The contract variation
would in itself normally be subject to the major spending provision requirements
with a prima facie requirement for two quotes. However, because of the
GCCC statutory enforcement notice, the Committee was empowered to approve the
variation to the extent that it is for work required by the notice. Even
without the statutory notice, it could also be argued that
only one quote was
required because it would not be reasonable or practical to get another
contractor to quote when the job had already
been contracted to and started by
Cowell.
The respondent disputes the validity of the variation because
it was not signed by the Body Corporate. That issue is beyond the jurisdiction
of this Office, although I note that section 82 of the Domestic Building Contracts Act 2000 provides that as soon
as practicable after a variation document is made, the building contractor must
sign the document and "take all reasonable steps to try to ensure the
document is signed by the building owner." Accordingly it may not
automatically be the case that a variation that is not signed by the owners is
not valid.
The fundamental issue here is whether Janette Watson had the
authority to verbally authorise Cowell to proceed with the variation
work.
Clearly Janette Watson has no legislative authority in her own right or as a
committee member to authorise expenditure of
Body Corporate funds to the tune of
almost $4,900 (or even $1 for that matter). The minimum requirement for the
expenditure of Body
Corporate funds is a committee decision. I accept that
Janette Watson may have believed that the respondent did not object to the
variation and that the respondent may not have contacted her to say he objected
to part of the variation works. However that is
entirely insufficient for the
additional expenditure to have been approved by the Body Corporate. A decision
must be a positive
decision rather than an absence of objection and, moreover,
it should be minuted. There was no committee meeting, no apparent attempt
to
call a committee meeting, no attempt to decide the issue by flying minute or to
confirm the purported decision at the next face-to-face
meeting. It is clear
there was no valid decision by the Body Corporate agreeing to the contract
variation.
Building contract dispute
The respondent argues
that this is really a dispute between the Body Corporate and the builder, and to
a large extent I agree. However,
I do not consider it is appropriate for the
respondent to simply refuse to contribute to the cost of the contract variation
and at
the same time to take no specific action to pursue his concerns about the
contract.
It is not the role of this Office to determine disputes under
the Domestic Building Contracts Act 2000. The Body Corporate
must pursue a dispute with the Building Services Authority or the Commercial and
Consumer Tribunal (depending
on the specific nature of the complaint) if they
consider that there are defects in the work, that the variation was not properly
signed, that the variation guttering work was covered by the original contract
price, or any other area of concern.
Pursuant to section 312 of the
Act a special resolution is required for a Body Corporate to commence legal
proceedings. The proper course of action for
the respondent, if he has concerns
about the building contract, is to put a motion to a general meeting seeking
authority for legal
proceedings to be commenced in the appropriate forum,
accompanied by quotes for the cost of the action. The respondent would be
prudent to seek further information and legal advice on the basis of any claim
and the likelihood of success before proceeding with
this course of action.
If the motion is not passed and the proponent considers this to be
unreasonable, he may lodge a dispute resolution application in
this Office
seeking to overturn the decision. The applicants should bear in mind that they
have a responsibility to vote on any
such motion with the interests of the Body
Corporate, rather than their builder friend, in mind. If the respondent is able
to present
cogent evidence of some irregularity in Cowell’s contract or
workmanship it may well be determined that the Body Corporate
is acting
unreasonably if it does not agree to pursue legal action, unless the cost of the
action would outweigh any benefit the
Body Corporate could win.
Other
claims
In addition to the sums sought for the contract variation, the
application appears to seek nearly $6,000 for sewerage work and claims
other
unspecified amounts have not been paid for. I invited the applicants to provide
full details of their claim if they were seeking
to recover for previous works,
noting that I am not able to reconsider issues previously determined by an
adjudicator.
Aside from an assortment of unexplained and unreferenced
documentation, including letters and invoices, scant information has been
provided by the applicants to substantiate any other claims. They have not
outlined even basic grounds to justify these claims.
Moreover, it is
apparent that an adjudicator has previously made a determination on issues
relating to a security light and sewerage
work[3]. The applicants have provided
no information to indicate they are making a claim beyond that which has already
been determined.
As the applicants have been advised, there is no jurisdiction
for an adjudicator to revisit issues that have been finally determined
in a
previous adjudication. If the applicants dispute the earlier decision, the next
step is for them to appeal that previous decision
to the District Court on a
question of law.
Accordingly, I find that there is no basis to consider
any further claims by the applicants and it is not apparent that I have any
jurisdiction to consider claims relating to security lightening and sewerage
work.
Day-to-day financial management
The respondent claims
Janette Watson has removed the cheque book from the Body Corporate and refused
to sign cheques necessary for
the day to day management of the scheme. He
claims he has had to personally pay for the handyman-gardener. As these issues
were
not the subject of the original application and the applicants have not
responded to them, it is not appropriate for me to make any
orders on these
issues. However I will make the following comments.
Committee members
must act reasonably, responsibly and in accordance with the legislation at all
times. It is entirely inappropriate
for a committee member to refuse to
counter-sign payments for Body Corporate obligations because of a dispute over
an allegedly unpaid
bill. That sort of ‘tit-for-tat’ activity (if
this is in fact what is occurring) would be childish and unprofessional.
However it does not particularly assist the situation for the respondent
to pay outstanding bills himself and just assume they will
be repaid. If the
gardener is not paid they will cease working which will provide a much greater
incentive for cheques to be counter-signed.
A more appropriate course
of action would be for the respondent to put forward motions to a body corporate
meeting that (a) the gardener
be paid and (b) that he be reimbursed for any
amounts paid in the interim. If the motions are not passed or acted on, and the
respondent
considers that the Body Corporate has been unreasonable in failing to
do so, the respondent can lodge an application in this Office.
Conclusion
I am satisfied on the evidence before me that
the work that was the subject of the original contract with Cowell, and the
contract
variation, was necessary and the responsibility of the Body Corporate.
However, it is clear that Janette Watson failed to obtain
proper Body Corporate
approval before authorising Cowell to proceed with the contract variation
work.
Notwithstanding that, I am required by section 276 to make a
decision that is just and equitable in the circumstances. The primary concern
of the Body Corporate in this matter was
to ensure that necessary repairs were
undertaken in accordance with the Body Corporate’s legislative
responsibilities and the
directive of the GCCC. The work that was the subject
of the contract variation has been completed and I have not received any
convincing
evidence that the work were not necessary, or was faulty or
unprofessional. Moreover, I have not received any evidence that the
cost of the
variation work (comprising both the barge tile and guttering component of the
work) was manifestly excessive.
While inappropriate and incorrect, the
actions of the applicants have nonetheless resulted in the fulfilment of the
Body Corporate’s
maintenance obligations. Moreover, I am not satisfied
that the Body Corporate has suffered any particular detriment as a result
of
these actions. Accordingly, I do not believe that it would be just and
equitable for the Body Corporate to avoid paying the cost
of work which is its
responsibility because of irregularities in the process for approving the work.
As John Watson has paid the variation amount, I have ordered the
respondent pay 50% of the cost to the Body Corporate. The Body Corporate
can
then reimburse the applicants in this amount.
Both parties are now
clearly on notice as to their legislative responsibilities regarding maintenance
and spending. They should ensure
that in future no money is spent by the Body
Corporate without a clear and minuted decision agreeing to the expenditure.
This will
assist in minimising future disputes.
I would also encourage
both owners to make every effort to inform themselves about their rights and
responsibilities under the body
corporate legislation. As the parties have been
previously informed, the Information Service of the Commissioners’ Office
can be contacted on 1800 060 119 with a range of information online. A new fact
sheet targeted at owners in a duplex is available
at: www.dtftwid.qld.gov.au/Dispute+Resolution/BCCM/Fact+Sheets.
I would also encourage the parties to utilise mediation and conciliation
services to assist in any future disagreements over the
operation of their
scheme. If the owners find the administrative responsibilities of the scheme
they may wish to consider engaging
a body corporate manager to assist with tasks
such as meetings, minutes taking and financial management.
[1] See section 95(2) of the Standard Module
[2] Section 59 of the
Standard Module similarly requires that ‘full and accurate minutes’
be recorded for each general
meeting.
[3] Galen House
[2005] QBCCMCmr 535 (29 September 2005)
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2006/751.html