![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 19 July 2006
|
APPLICANT: GUISEPPE ROBERTIELLO, GLORIA ROBERTIELLO, GILBERTO MAGGIOLO
AND ANTONIO BOSSO
RESPONDENT: BODY CORPORATE FOR NEW FARM VILLAGE COMMUNITY TITLES SCHEME
16207
ORDER OF THE SPECIALIST ADJUDICATOR
|
Made on 4th day of January
2006
|
After reading the application, the submissions made on behalf of the
Applicant, the Respondent, various lot owners and the supporting
materials, I
order as follows:
1. That the Contribution Schedule Lot Entitlements for the Body Corporate for New Farm Village Community Titles Scheme 16207 be adjusted to the recommended schedule as set out in Table 5 of Part B to the report of Leary and Partners Pty Ltd dated 14th November 2005. A copy of the recommended contribution schedule is attached to this order. a) the sum of $4,400.00 to the Adjudicator; |
___________________________
Bernard V McGowan
Specialist
Adjudicator
(a4102)
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
APPLICANTS: GUISEPPE ROBERTIELLO
GLORIA ROBERTIELLO
GILBERTO MAGGIOLO
ANTONIO BOSSO
RESPONDENT: BODY CORPORATE FOR THE NEW FARM VILLAGE COMMUNITY TITLES
SCHEME 16207
REASONS FOR DECISION OF SPECIALIST ADJUDICATOR
Background
The Applicants lodged a Dispute Resolution
Application on 5th May 2004 ("the Application") pursuant to the
provisions of sections 238 and 239 of the Body Corporate and Community
Management Act 1997 ("the Act"). On 24th May 2004 the Application
was amended pursuant to the provisions of section 245 of the Act.
The outcome which is sought in the Application is as follows:
"Adoption of a new contribution lot entitlement scheme as contained in the report of Solutions in Engineering".
I was named as the specialist adjudicator in the Application and this was confirmed by the Commission for Body Corporate and Community Management on 31st August 2004 when the Commissioner referred this Application to me for adjudication.
By interim adjudication dated 12th April 2005 I advised the parties that I was not in a position to make a final adjudication and that before I could make such an adjudication a final report needed to be prepared by Solutions in Engineering Pty Ltd.
I am instructed that the Respondent Body Corporate subsequently engaged Leary and Partners Pty Ltd to prepare a final report and that Solutions in Engineering Pty Ltd was no longer trading. On 13th December 2005 I received a copy of the report of Leary and Partners Pty Ltd dated 14th November 2005.
I have received no further submissions from the Respondent or
Applicants or any of the lot owners subsequent to my interim
adjudication.
Inspection
I have attended at New Farm
Village for an onsite inspection on 16th May 2005 and in the course
have interviewed the body corporate secretary and the cleaning contractor. My
particular concern was
to ascertain the extent to which the following costs
should be weighted towards the commercial lots:
• Cleaning costs
• Waste removal costs
I also wished to ascertain how
certain costs involving the car parks and intercom system should be dealt with
as far as studio unit
owners where concerned as those lots did not have car park
usage and no need to access the commercial entrance.
Report of Leary
and Partners Pty Ltd
The report of Leary and Partners Pty Ltd is
comprehensive. In my opinion it addresses the central issue, namely, that the
legislation
- section 48(5) of the Act - provides that the respective lot
entitlements for the contribution schedule should be equal except to the extent
to which it is
just and equitable in the circumstances for them not to be
equal.
It also addresses the issues which concerned me on inspection
relating to cleaning costs, waste removal and Lots 8 to 12.
I note that
Leary and Partners Pty Ltd have excluded Lots 9 to 12 from any basement related
expenditure and Lots 8, 16 and 17 have
been excluded from costs associated with
the security shutter and the security enclosure fence.
With respect to
waste removal it is obvious to me that the commercial lots produce more rubbish
than the residential lots. It appears
though that things have been sorted out
with Brisbane City Council so that a standard waste collection occurs three
times per week.
I agree that the cost of waste collection can be apportioned
equally so long as the commercial lots are paying for a separate service
and are
not generating a level of waste for the rest of the complex that results in a
need for additional collections at additional
cost. This will need to be kept
under review.
The report analizes in depth the administrative costs and
the sinking fund costs. The analysis is far more detailed than that in
the
original Solutions in Engineering report. There has been a focus on the areas
of concern raised in the submissions by residential
owners and this has produced
a recommended entitlement schedule which is weighted marginally more towards the
commercial lots than
the recommended schedule of Solutions in
Engineering.
Leary and Partners Pty Ltd conclude that it is just and
equitable that the respective lot entitlements not be equal. Further the
report
concludes that the current contribution schedule for New Farm Village cannot be
justified. A recommended contribution schedule
is put forward in Part B: Table
5.
In my opinion the report has been prepared consistently with the
principles laid down in the case of Fisher and Others v Body Corporate for
Centrepoint Community Title Scheme 7779 which is the leading case authority
in Queensland. In my opinion the recommendations of Leary and Partners Pty Ltd
should be adopted
by the Body Corporate.
This will result in an increase
in contributions by residential lot owners above present contribution. However
the methodology of
Leary and Partners Pty Ltd cannot be seriously challenged and
the legislature has intended such results by virtue of the clear wording
of
section 48(5) of the Act.
Submissions based on amenity and valuation
A number of submissions were made by lot owners relating to the
impact that any variation of the contribution lot entitlement schedule
may have
on the value of properties owned by lot owners and the financial impact that may
be imposed on lot owners by the change.
Unfortunately, the decision in Fishers
case makes it clear that these issues are to be
disregarded.
Adjudication
I am in agreement with the
approach of Leary and Partners Pty Ltd. I find that the extent to which it is
just and equitable for the
lot entitlements not to be equal is the extent
detailed in the report of Leary and Partners Pty Ltd.
In terms of costs
of this Application, section 280(2) provides that unless I otherwise order the
Applicant is to be responsible for the costs of the adjudication. I see no
reason to
make any order otherwise and so the Applicant is to meet the costs of
my adjudication which will be $4,400.00. I acknowledge receipt
of the sum of
$4,400.00 from the Applicant as security for these costs.
In my letter of
5th May 2005 to the Body Corporate Manager I ordered that the cost of
obtaining the report of Leary and Partners Pty Ltd should be to
the account of
the Body Corporate at that point in time. I also left it open for either party
to make submissions to me as to whether
the Body Corporate should be reimbursed
for this cost. I did not receive any submissions on this point.
Notwithstanding this I
see no reason why the Applicant should not reimburse the
Body Corporate for the cost of obtaining the report of Leary and Partners
Pty
Ltd as this is a cost of the adjudication.
For the reasons expressed
above, I make the following orders:
a) That the contribution schedule lot entitlements for the Body Corporate for New Farm Village Community Title Scheme 16207 be adjusted to the recommended schedule set out in the report of Leary and Partners Pty Ltd dated 14th November 2005. A copy of the schedule is attached to this order. b) That the Respondent shall within three months from the date of receipt of a copy of this order prepare and register with the Queensland Land Registry of the Department of Natural Resources and Mines a new community management statement to give effect to the adjusted contribution lot entitlements. c) That the Applicant pay the costs of the Application and this order as follows:
i) the sum of $4,400.00 to the Adjudicator; and
ii) reimbursement of the Respondent Body Corporate for the cost of obtaining the report of Leary and Partners Pty Ltd dated 14th November 2005.
Dated this day of
January 2006
___________________
Bernard
McGowan
Specialist Adjudicator
To: Body Corporate for New Farm
Village Community Title Scheme 16207 C/- Premier Body Corporate Management, PO
Box 184, Kedron Q 4031
And To: Guiseppe Robertiello, Gloria Robertiello,
Gilberto Maggiolo and Antonio Bosso C/- Café dell Ugo, 693 Brunswick
Street,
New Farm Q 4005
(new040725:a4101)
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2006/5.html