![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 19 December 2006
REFERENCE: 0320A-2006
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
26051
|
|
Name of Scheme:
|
Lake Hills
|
|
Address of Scheme:
|
117 - 139 Palm Meadows Drive CARRARA QLD 4211
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
R Staley, a co-owner of lot 38
|
I hereby order that the application for an order
to invalidate all resolutions relating to the installation of bore on common property at Lake Hills until they are considered at a general meeting. Is dismissed. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0320-2006
"Lake Hills" CTS 26051
Application
The applicant lot owner, Mr Staley, is seeking the
following order of an adjudicator:
To invalidate all resolutions
relating to the installation of bore on common property at Lake Hills until they
are considered at a
general meeting.
Scheme
The scheme
is a subdivision of 96 lots and the regulation module applying to the scheme is
the Accommodation Module.
Background
The applicant
advises that at a committee meeting held on 13 April 2006 the body corporate
committee voted to drill for ground water
for the purpose of watering common
property gardens.
The committee resolutions read as follows:
1. that the committee is to obtain a second opinion from a water diviner confirming the advice received from the first water diviner who was engaged by the committee;
2. that subject to the advice received from the water diviner, the committee is to be authorised to approve the quotation received from Drill Power Qld. Pty. Ltd. on 29 March 2006 and the committee is to advise Drill Power Qld. Pty. Ltd. To proceed with the drilling of a test bore in Lake Hills; and
3. That if water is found, the bore is to be capped and the committee is to consider at future committee meetings the viable options available for the distribution of this water onto the common property gardens and lawns and these options are to be submitted for the consideration of the owners at a general meeting.
The applicant submits that :
• The legislation provides that if a series of proposals forms a single project, the cost of carrying out any one of the proposals to be taken to be more than the committee spending limit if the cost of the project as a whole, is more than the relevant limit;
• Expenditure to install a bore must only be authorised by special resolution at a general meeting ;
• Research of all viable options and total cost for each must be accomplished prior to installing a test bore.
Submissions
Under section 243 of the Body
Corporate and Community Management Act 1997 (the Act), a copy of the
application was provided to the respondent body corporate and to all owners,
with an invitation to respond
to the matters raised in the application. Written
submissions were made by two owners and the body corporate.
Two owners
believed that the decision to undertake drilling should be made by resolution of
a general meeting rather than by the committee.
The body corporate
made the following submissions:
• Advice was received from the body corporate manager that it was within the power of the committee to engage a contractor to undertake exploratory work and if water is found the bore could be capped until installation of a bore is approved at a general meeting;
• The committee regard the drilling of a test bore as necessary to determine the feasibility of the water supply available;
• The contractor who has provided the most acceptable quote has sunk productive bores in close proximity to the proposed site. For example a productive bore has been sunk 500 metres away from the test site;
• Quotations for sinking a test hole range from $14 per foot (30cm) to $16.50 per foot (30cm);
• If water was found, the hole would be cased at a total cost of $28 per foot (30cm) to
• Other alternatives were being considered such as lake water and rainwater collection;
• In any case the total expenditure for drilling the bore and installation of an irrigation system could well be within the committee’s expenditure limit i.e. $125 per lot x 96 lots = $12,000;
• under no circumstances would any further work be carried out if water was found until it was considered by the owners at a general meeting; and
• even if the total expenditure for drilling the bore and installation of an irrigation system was within the committee’s expenditure limit, a general meeting would be required as there is no provision in the sinking fund budget and a special levy would be required to raise such monies.
Jurisdiction
Section 276(1) of the Act
provides that an adjudicator may make an order that is just and equitable in the
circumstances (including a declaratory
order) to resolve a dispute, in the
context of a community titles scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
Determination
The committee has engaged a contractor to undertake drilling to determine
the feasibility of supplying an alternative source of water.
The proposed site
of the bore hole is in close proximity to existing productive bores, including a
bore providing situated 500 metres
from the test site, and it is anticipated
that water would be found at less than 100 feet (30 metres).
Quotations
for sinking a test hole range from $14 to $16.50 per foot (30cm) and if water is
found, the hole would be cased at a total
cost of $28 to $33 per foot (30cm).
The hole would then be capped and no further work would be carried out until the
proposal to
install a pump and reticulation system was considered by the owners
at a general meeting.
Section 101 of the Body Corporate and Community
Management (Accommodation Module) Regulation 1997 regulates the expenditure
of body corporate funds. Under that section, the Committee can only approve
expenditure up to the relevant
limit for committee spending.
The term
"relevant limit for committee spending" is defined in the Dictionary
section of the Act as an amount worked out by multiplying the number of lots by
$125. As this scheme
consists of 96 lots, the relevant limit for committee
spending is $12,000 ($125 per lot x 96 lots = $12,000). Where a proposal
involves
expenditure above that amount it must be authorised by ordinary
resolution of the Body Corporate.
In my view, the committee is entitled
to engage a contractor to undertake the proposed work i.e. to
conduct
drilling to determine the feasibility of supplying an alternative source of
water. As pointed out, the committee would be
entitled to incur expenditure of
up to $12,000 although the actual cost of drilling test hole/s would probably be
much less. Further,
given that there are a number of productive groundwater
bores in the area, I do not believe that the proposal is unreasonable,
particularly
when one considers the cost of reticulated water and the future
availability of reticulated water for garden purposes.
Accordingly, I
have decided to dismiss the application.
Although the applicant has
sought interim relief, this order is to have effect as a final
order.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2006/304.html