![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 19 July 2006
REFERENCE: 0112-2006
INTERIM ORDER OF AN
ADJUDICATOR
MADE UNDER PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
1540
|
|
Name of Scheme:
|
Cairns Holiday Lodge
|
|
Address of Scheme:
|
259 Sheridan Street, CAIRNS Q 4870
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Crestvilla Pty Ltd, the owner of lots 5, 6 and 7
|
I hereby order, by consent, as follows:
1. That the body corporate shall not alter the present method of payment for electricity consumption within the scheme until the administrative fund budget has been amended to remove from the budget the total cost of electricity consumption, and, further until a resultant amendment has been made to the administrative fund contributions I further order that the body corporate shall within one month of the date of the order forward a copy of the order and the accompanying statement of reasons to all owners. |
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0112-2006
"Cairns Holiday Lodge" CTS 1540
ORDER SOUGHT
The applicant has sought an order of an
adjudicator under the Body Corporate and Community Management Act 1997
(the Act) as follows:
That the motion passed by the committee under section 33 of the
Accommodation Module that the body corporate supply and install an
electricity
meter for the restaurant (lots 5, 6 and 7) and undertake ancillary works be
declared void.
The applicant has also sought an interim order of an
adjudicator under the Act that the motion not be permitted to have effect until
the outcome of the final order is known particularly in view of the cost of the
proposed works and the cost of reversing such
work.
JURISDICTION
The application evidences a dispute
between an owner of a lot included in a community titles scheme and the body
corporate for the
scheme (section 227(1)(b) of the
Act).
Section 276(1) of the Act provides that an adjudicator may
make an order that is just and equitable in the circumstances (including a
declaratory
order) to resolve a dispute, in the context of a community titles
scheme, about-
(a) a claimed or anticipated contravention of the Act or the community management statement; or
(b) the exercise of rights or powers, or the performance of duties, under the Act or the community management statement; or
(c) a claimed or anticipated contractual matter about-
(i) the engagement of a person as a body corporate manager or service contractor for a community titles scheme; or
(ii) the authorisation of a person as a letting agent for a community titles
scheme.
An order may require a person to act, or prohibit a person from
acting, in a way stated in the order (section 276(2)). An adjudicator's
order may contain ancillary and consequential provisions the adjudicator
considers necessary or appropriate (section 284(1)).
Section
279(1) of the Act allows an adjudicator to make an interim order if
satisfied, on reasonable grounds, that an interim order is necessary
because of
the nature or urgency of the circumstances of the application.
SCHEME
DETAILS
Cairns Holiday Lodge is a community titles scheme comprising
39 lots and common property. The building units plan (now described
as a
building format plan) registered on 19 December 1977. The scheme is regulated
by the Body Corporate and Community Management (Accommodation Module)
Regulation 1997 (Accommodation Module).
BACKGROUND
The
applicant stated in its supporting grounds that the body corporate has purchased
bulk electricity for the scheme since its inception.
The cost of supply has
been included in the annual administrative fund budget, and has been recovered
from owners through their
administrative fund levies. The applicant stated the
scheme comprises various levels of electricity usage, but expressed the view
that the high cost of installing separate meters to each lot is the reason that
the current method of recovering the cost of supply
continues.
However,
the applicant pointed out that by-law 30 deals with bulk electricity supply,
and, in particular, by-law 30.5 provides that
the body corporate must arrange
for the installation of a separate energy meter for each
lot.
Notwithstanding this provision, the body corporate committee has
recently resolved to install an energy meter to lots 5, 6 and 7,
which are owned
by the applicant, and operated as a restaurant.
The applicant stated that
the committee’s decision was contrary to the by-laws.
The Dispute
Resolution Application was received by facsimile transmission in the
Commissioner’s office on 17 February 2006.
The application was referred
to me by the Commissioner on 20 February 2006. A teleconference with the
parties’ solicitors
was arranged for 22 February 2006, but did not proceed
on that date due to the unavailability of one of the solicitors. The
teleconference
was rescheduled for 24 February 2006.
On that date I spoke
with Mr Robert Grealy, solicitor for the body corporate, and Mr Phil
Shakespeare, solicitor for the applicant.
Mr Grealy stated that the
body corporate did not concede that by-law 30.5 required the installation of a
separate energy meter for
each lot. He also pointed out that there are a large
number of lots owned by one entity, and the significant cost of installing
separate meters to each lot in this situation would not be warranted.
Mr
Shakespeare stated that his client’s objection to the installation of an
energy meter (flow meter) in its lots and not in
all other lots was that the
body corporate would effectively be "double dipping" in relation to the
reimbursement for electricity
consumption.
Mr Shakespeare explained
that at the moment the body corporate includes the estimated annual cost of
electricity for the whole scheme
in the annual budget for the administrative
fund. The contributions to the administrative fund are then determined by
reference
to the budget, which means that all owners make a contribution to the
cost of the electricity based on their contribution schedule
lot
entitlement.
Mr Shakespeare pointed out that if the applicant’s
lots were separately metered, the applicant would pay for the actual amount
of
electricity used in its lots on top of its contribution to the cost of
electricity through payment of its levies. Mr Shakespeare
stated that the
applicant would have no objection to paying for the electricity used in its lots
as determined by a flow meter, provided
that there is a reduction in its levies
to reflect that portion of its levies which would otherwise have been applied to
the cost
of electricity under the system which has been operating to
date.
Mr Shakespeare further stated that a flow meter should also be
installed to measure the electricity used on common property, as this
area
involved quite high levels of usage.
It was then discussed that the
cost of electricity could be recovered in the following manner:
• The electricity used in lots 5, 6 and 7 from the applicant, based on its metered usage
• The electricity used in the common property from all owners including the owner of lots 5, 6 and 7, based on the metered usage, and billed according to contribution schedule lot entitlements
• The balance of the electricity used for the scheme would be billed to the owners of all lots excluding the owner of lots 5, 6 and 7 according to contribution schedule lot entitlements.
Mr Grealy stated
that he would need to obtain instructions from the body corporate committee on
this proposal.
The teleconference was adjourned to 28 February 2006 to
allow Mr Grealy to obtain instructions.
Upon its resumption, Mr Grealy
stated that the body corporate committee had agreed to implement the proposal
outlined above. He stated
that the committee had further agreed that until such
time as the levies had been adjusted to reflect the new method of paying for
electricity, there would be no change to the present system of paying for
electricity.
Mr Grealy advised that the estimated cost of installing a
flow meter to the common property is $2,200.00 and to lots 5, 6 and 7 is
$3,000.00. Mr Grealy further advised that he thinks the body corporate has
increased the level of committee spending but is unsure
to what level. (The
limit, if it has not been increased, is $4,875.00). Mr Grealy noted that if
committee spending has been increased
the committee would be able to approve the
installation of flow meters to the applicant’s lots, and to the common
property.
Mr Grealy and Mr Shakespeare agreed that the budget and the
administrative fund levies could only be altered to reflect the deletion
of the
line item relating to total electricity usage at a general meeting. They also
both agreed that the appropriate orders to
facilitate the matters discussed
would be made by consent.
Following the teleconference, a member of the
Commissioner’s staff telephoned the body corporate manager who advised
that as
far as she can ascertain from the minutes going back to 1994, the body
corporate has not increased the level of committee
spending.
DETERMINATION
By-law 30.5 states, in part,
"the body corporate must arrange for the installation of a separate energy
meter for each lot." In my view this is an unequivocal statement. Whilst I
accept that the body corporate might not wish to go to the expense of installing
separate meters to each lot where there are multiple lots in the one ownership
(one company, for example, owns 19 lots), if that
owner, and indeed all other
owners, insisted that separate meters be installed then I consider that the body
corporate would be required
to do so.
In this matter however, the
applicant’s specific concerns about paying twice for electricity usage can
be addressed by the consent
orders discussed during the teleconference.
The first issue to be considered is the cost of installation of the flow
meters.
Under the Accommodation Module the level of committee spending
can be increased by the body corporate in general meeting to a maximum
limit of
$450.00 per lot. As the body corporate manager has checked the minutes going
back to 1994 (prior to the commencement of
the Body Corporate and Community
Management Act 1997) and has not been able to locate any record of the body
corporate having increased the limit, the committee appears therefore to
be
restricted to the present statutory limit of $125.00 per lot, and will not be
able to install the flow meters to the applicant’s
lots and to the common
property, if the cost exceeds $4,875.00. In these circumstances, the committee
will also not be able to install
one of the meters without the other, because,
on the basis of the discussion during the teleconference, the installation of
both
meters forms a single project (section 101(2) of the Accommodation
Module), and must be approved by owners at a general meeting.
In any
event, the body corporate cannot implement the new method of billing for
electricity usage until a general meeting is held
at which appropriate
amendments are made to the budget and the administrative fund contributions,
otherwise the applicant will be
paying twice for its electricity usage.
I
have made consent orders in accordance with the agreed outcomes from the
teleconference, and these orders finally dispose of the
application.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2006/107.html