![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 30 September 2005
REFERENCE: 0434-2004
ORDER OF AN ADJUDICATOR
MADE UNDER
PART 9 OF CHAPTER 6
BODY CORPORATE AND COMMUNITY MANAGEMENT ACT
1997
|
Number of Scheme:
|
17108
|
|
Name of Scheme:
|
Herston Place
|
|
Address of Scheme:
|
60 Herston Road Kelvin Grove Q 4059
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Peter Wayne Freak and Christine Patricia Freak, the Owners of Lot 6
|
I hereby order that the application for a declaration that the body
corporate is responsible for repair work to the patio of lot 6, is dismissed
as
it is the owners of lot 6 who are responsible for the cost of these
repairs.
|
STATEMENT OF ADJUDICATOR’S REASONS FOR DECISION - REF
0434-2004
"Herston Place" CTS 17108
The Scheme
"Herston Place" Community Titles Scheme was
registered as a building units plan (now known as a building format plan) on 1
June 1995.
The scheme comprises six residential lots and is operating under the
Body Corporate and Community Management (Standard Module) Regulation 1997
(the Standard Module).
The Application
This application is
brought by the Owners of Lot 6, Peter Wayne Freak and Christine Patricia Freak
(the Applicants) seeking an order that the body corporate be held
responsible for the cost of repair of structural damage to the patio of Lot
6.
Submissions
Submissions in response to the application
were sought from all owners and the body corporate committee, however, no
submissions were
made.
Background
As previously
mentioned, "Herston Place" was registered as a building units plan of
subdivision on 1 June 1995. Lot 6 was purchased
by Samuel David Vickers and
Sandra Louise Earea (hereinafter referred to as the previous owners) from the
developers, Conhill Pty
Ltd, with the transfer being recorded on 28 August 1996.
The previous owners became aware of several defects with Lot 6, including
water
leaking from the verandah into the garage and a crack in the garage roof with
water bubbles evident. A Dispute Notification
Form was lodged with the Building
Services Authority (BSA) in relation to these and other defects, on 2 June 1997.
As part of my investigation in relation to this matter, I perused the
BSA files in relation to Lot 6, "Herston Place", pursuant to
my investigative
powers under section 271(1)(a)(i) of the Act. A detailed perusal of these files
revealed the following information.
After an investigation by the BSA,
the builder of the scheme was issued with a Direction to Rectify and/or Complete
on 27 August 1997.
The required rectification work was eventually carried out
and the previous owners notified the BSA that the work had been completed
to
their satisfaction on 17 December 1997.
The rectification work failed
some time later and again, water penetration was occurring from the patio to the
garage below. The
previous owners notified the BSA of this on 9 March 1998 and
requested the BSA to re-open their investigation.
As a result of further
investigation by the BSA, a further two Directions to Rectify and/or Complete
were issued to the builder, on
23 March 1998 and 3 September 1998. After the
builder failed to comply with either of those Directions, the BSA approved the
amount
of $2,282.50 as an insurance payment to have the required work carried
out by a contractor, Mr Pitkin. The BSA was notified that
the required work had
been completed satisfactorily 4 May 2000.
In addition to the
information I obtained from the BSA, this Office also obtained information from
the previous owners, particularly
in relation to any correspondence they had had
with the body corporate regarding this issue. The information supplied reveals
that
failing waterproofing membranes on balconies had also been an issue for
Lots 2 and 4 for some years. After lengthy discussion concerning
this issue at
the Annual General Meeting held on 22 August 2000, the Body Corporate Managers,
Premier Body Corporate Management,
notified all Owners via a circular dated 10
October 2000 that owners were individually responsible for membrane repairs,
either by
going through the Queensland Building Services Authority or arranging
for payment for the repairs themselves. Also at this AGM, permission
was granted
to allow the previous owners to extend the patio area to ensure proper
waterproofing of the patio. The material on file
indicates that the previous
owners arranged to have the entire patio area waterproofed and retiled and to
have the hand rail moved
to the edge of the patio.
The Applicants
purchased Lot 6 in March 2002. In February 2003 the applicants noted that water
was entering and damaging the ceiling
of the garage of Lot 6 and the body
corporate manager arranged for tiles to be lifted and replaced and also for
silicone sealant
to be applied between the patio and "step down" section.
However in November 2003 it became evident that the work done in February
had
failed as water was again entering and damaging the ceiling to the garage of Lot
6. At an extraordinary general meeting held
on 22 April 2004 the body corporate
accepted a quote from Blake’s Waterproofing in the amount of $5,417.50 to
carry out necessary
rectification work to Lot 6. The body corporate has since
paid this invoice. Blake’s Waterproofing engaged Acacia Tiling
to lift
the existing tiles and prepare the surface for waterproofing. The Applicants
state that it was at this stage that the problem
in dispute came to light. They
state that it became apparent that materials used at the end of the patio were
found to be rotted
and constructed of an inappropriate softwood small gauge
material. The area is referred to by tradesmen as the "add-on section of
the
patio" and is approximately one metre wide and runs the full width of the patio.
The Applicants state that despite the reference
to the area in question by
tradesmen as the "add-on section of the patio", the area has always formed part
of the roof of the garage
to Lot 6.
A report prepared by J & D
Contracting on 22 June 2004 states that "the extended section of the patio is
unsafe and has been unsafe
since the date of construction". The Applicants
again state that the extended section referred to has always been the roof of
their
garage. They suspect the term is used because of the two different
materials that have been used in the construction of the patio.
The
Applicants paid the invoice supplied by Acacia Tiling in the amount of $6,479 on
9 August 2004 for the necessary repair work,
which included removal and
reconstruction of the portion of the patio consisting of the step down section,
re-sheeting and painting
of the damaged garage ceiling. The Applicants seek
that they be reimbursed the total amount of this invoice by the body corporate
on the basis that the work required was structural in nature.
In
February of this year an adjudicator from this Office held a teleconference with
the applicants and the Body Corporate Manager.
At that teleconference the
applicant advised he would pursue a further claim with the BSA. However in a
letter received by this Office
on 2 August 2005, the applicant advised that
attempts to seek compensation through the BSA were unsuccessful and attached a
letter
from the BSA which advised as follows:
" The BSA replaced the
waterproofing membrane in 2000; sometime after, the previous owner tiled this
area and moved the balustrade
to its current position. It would be reasonable to
assume that the original framing was not designed for the increased loading.
Unfortunately
in this instance, the Authority is unable to provide any further
assistance."
Decision
"Herston Place" was registered as a building units plan under the relevant piece of legislation then in place, the Building Units and Group Titles Act 1980 (hereafter the "BUGT Act") on 1 June 1995. The current Act replaced the BUGT Act on 13 July 1997 in respect of existing plans such as "Herston Place". Under the transitional provisions of the Act, a building unit plan becomes a "building format plan" under the Land Title Act 1994 (see section 330 of the Act). Section 49C(4) of the Land Title Act 1994 states that :
(4) Except to the extent permitted under directions of the registrar about
the required format for a building format plan of subdivision, the boundary
of a lot created under the plan, and separated from another lot or common
property by a floor, wall or ceiling, must be located at the centre of the
floor, wall or ceiling.
There is nothing recorded on
the scheme’s plan to show that the boundaries between lots and the common
property exterior land
is other than the general provision set out above, that
is, the centre point of the boundary walls, floors and ceilings.
An
examination of the building units plan reveals that the balcony of Lot 6 is on
the middle level of a three story construction and
as such, the balcony floor
and garage roof in question are entirely within the boundaries of Lot 6 and do
not form part of the common
property. In accordance with section 120(2) of the
Standard Module, the necessary repairs are therefore the responsibility of the
owner of the lot.
Section 109(2) of the Standard Module obliges the
body corporate to maintain in good condition or in a structurally sound
condition certain elements
of schemes registered as building format plans of
subdivision that are not common property. However, I do not consider the area
in question falls into any of those elements mentioned in section 109(2).
Accordingly, I am of the view that it is the owners of lot 6 rather than
the body corporate, who are responsible for the cost of repairs
to the
patio.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2005/443.html