![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Queensland Body Corporate and Community Management Commissioner - Adjudicators Orders |
Last Updated: 5 July 2005
REFERENCE: 0694-2003
ORDER OF A REFEREE
MADE UNDER PART
V
BUILDING UNITS AND GROUP TITLES ACT 1980
|
Number of Scheme:
|
GTP 1701
|
|
Name of Scheme:
|
Bauhinia
|
|
Address of Scheme:
|
Sanctuary Cove HOPE ISLAND QLD 4212
|
TAKE NOTICE that pursuant to an application made under the abovementioned Act by
Riitta Anneli MELLISH, the owner of Lot 74,
|
I hereby order that the application for the following orders
–
"1. The new structure is demolished.
is dismissed. |
||
|
|
STATEMENT OF REASONS FOR REFEREE’S DECISION - REF
0694-2003
"Bauhinia" GTP 1701
The applicant, Riitta Mellish of Lot 74, has sought the following orders
of a Referee under the Building Units and Group Titles Act 1980 -
"1. The new structure is demolished.
2. (a) If a class 10 building is to be built on the site then all by-laws are to be complied with. The points are already detailed in our letter to PBC dated 19-10-03.
(b) PBC and ARC are not allowed to give exemption to clauses of the by-laws which impact on our lot.
(c) The final approval of drawings occurs only after we are consulted and that our views are taken into account.
(d) Clause 3.12.2. The structure does not adversely affect our amenity. Aesthetics of the building are in keeping with the character of our lot.
(e) Clause 2.10.2. The details of finish as detailed in this clause area is given to us for approval.
4. Clause 3.10.1(b). That the conduct of PBC and ARC being considered as wilful misconduct or bad faith due to their failure to uphold the by-laws as well as their failure to investigate what has occurred on the site and accepting the new structure (cabana) as existing when it is new"
The applicant also sought an interim
order for the works to cease until such time as the dispute was investigated,
however at the
time the amended application was in a form to proceed, the work
had been largely completed and the application for an interim order
was to no
purpose.
JURISDICTION:
This is a dispute between an owner
(the applicant Mellish) and both the Principal Body Corporate ("PBC"), and
another owner, Mediterranean
Consulting Limited of Lot 75, as first and second
respondents respectively, concerning an alleged breach of by-laws by the second
respondent in the construction of structures on or near the eastern boundary of
its lot, and by the first respondent in not properly
monitoring and halting the
construction.
Jurisdiction for a Referee under the Building Units and
Group Titles Act 1980 ("the BUGT Act") to determine matters arising under
the Sanctuary Cove Resort Act 1985 ("the SCR Act") was provided for by
the following amendment to the SCR Act commencing from 4 March 2003 –
104A Dealing with disputes
Unless otherwise provided in this Act, a dispute about the operation of this Act or the rights and obligations of persons under this Act may be dealt with under the Building Units and Group Titles Act 1980, part 5.
In my Statement of Reasons to other applications I
have commented on the inadequacy and inappropriateness of the above and similar
amendments purporting to give jurisdiction to deal with disputes arising under
the SCR Act and other specified Acts (see sections 5A and 325
of the Body Corporate and Community Management Act 1980). I refer,
for example, to the statement of reasons to Interim Order 209-2003 for
"Bauhinia" of 25 February 2004, and also to Order 377-2004 for
"Roystonia and Colvillia" of 12 January 2005 where jurisdiction to
deal with certain matters under the SCR Act was found not to exist. Both of
these orders
relate to residential bodies corporate within the Sanctuary Cove
Resort complex, being
residential subsidiary bodies corporate to
the PBC. The
reasons to both of those orders, in particular the comments concerning
jurisdiction,
are not determinative of this
application, but may be of
assistance in a general understanding of the reasons to this order and any
other
for a specified Act – the orders and reasons are readily available
by linkages given in the departmental website.
Despite the flaws outlined
in those statements of reason, I intend to assume jurisdiction exists in respect
of this dispute at least
so far as it concerns the application of by-laws of a
PBC.
APPLICATION AND SUBMISSIONS:
Under section
73(1)(c) of the BUGT Act, a copy of the application was supplied to
Mediterranean Consulting Limited (director John Baines), through its solicitors
Summerton
De Vere (Michael De Vere) and to the PBC through its secretary David
Wall of Body Corporate Services, the Body Corporate
Manager
to the resort
complex. Both respondents made written submissions to the application, opposing
the application. The applicant
Mellish
inspected the submissions and
subsequently made a written response.
The applicant contends that the
respondents have not only breached the PBC Development Control by-laws but
commenced the construction
without the proper prior approvals. The common
boundary (eastern boundary of applicant’s lot) comprises the controlled
aspect
wall of the applicant’s lot.
The applicant has supplied a
comprehensive list as to how the construction breaches various by-laws,
including as to the height, the
projection of guttering, the composition of the
material used, distances to the boundary line, the soundness of the
construction,
and other technical matters. She is also concerned that the PBC
and the ARC have allowed improper structures to be built, has allowed
the
respondent to avoid the correct process for having structures approved (plans,
timing etc), and, also, there has not been true
independence in the approval
process and, at the least, there has been wilful misconduct or bad faith by PBC
and ARC.
The applicant claims the result is that, "The amenity and
aesthetic of the new structure are impacting on our lot" and "Our view
along the waterway and access to breeze will be significantly reduced as well as
the visual aspect of the facing to our lot
is not in keeping with details of the
existing structures."
The solicitor for the respondent has
submitted that its client had consulted the applicant on 16 October 2003 when
she stated being
satisfied with the proposed structure. The respondent also
states that the views enjoyed by the applicant were only available because
the
boundary structure was only ever 1.25m though under the PBC Development Control
By-law 2.11.1(c) it can be 2.00m (the constructed
wall is reportedly 1.54m).
Further, it claims that all approvals were obtained and has submitted a copy of
the recommendation for
approval by ARC dated 13 June 2003 and the subsequent
approval by the PBC of the respondent’s plan (with 2 minor conditions)
by
letter to Baines dated 24 October 2003 and his architect (MPS Architects) dated
11 November 2003.
The PBC submitted copies of a large number of relevant
documents relating to decisions and actions by ARC and PBC, and correspondence
with Mellish and MPS Architects for the respondent. It acknowledges that
Mellish brought to its notice aspects of the proposed work
that did not comply
with the Development Control by-laws, resulting in the respondent having to
submit an amended plan which was
subsequently approved. An independent
architect, Design Imagery, was engaged by PBC which reviewed the plans and
recommended approval
in its report of 20 October 2003.
I have all of the
submissions of the parties though do not propose to reiterate all of the points
here, for example, all of the breaches
alleged by the applicant against the
respondent’s
structures.
DETERMINATION:
"Bauhinia" was registered
as a group titles plan under the BUGT Act on 18 August 1987 and comprises 91
residential lots. It is one of the
residential bodies corporate subsidiary to
the principal body
corporate-residential precinct (PBC) which is itself, along
with non-residential
precincts, subsidiary to the primary thoroughfare
body
corporate (PTBC). It comprises mostly "harbour front" and "river front" villas
such as the applicant’s and respondent’s
respective Lots 74 and 75
situated on Anchorage Terrace facing the Coomera River.
At the outset I
must apologise to all parties concerned with this dispute for the delay in the
issue of this order.
The simple reason is that after my visit to
Sanctuary Cove to inspect the physical aspects of the dispute, the body
corporate secretary
Wall (who was present at the inspection) offered to attempt
to mediate what was essentially a simple dispute between the parties.
Having
placed the dispute into abeyance, I was unaware that Wall had subsequently
written to this office on 21 April 2004 advising
that the attempt was
unsuccessful. I would point out that had the applicant (or the respondent)
inquired as to the progress of the
application then this would have brought the
file and the oversight to my attention.
My visit to the resort on 7 April
2004 was to view the construction complained of by the applicant Mellish. The
inspection took place
in the presence of Mellish and Mr Mellish, and as
previously stated, David Wall. Following the inspection of the structures on or
near the eastern boundary of the respondent’s Lot 75, Mr Mellish reviewed
the relevant by-laws and the conduct of the PBC and
the Architectural Review
Committee ("ARC") which both the applicant and he believed was improper in
allowing the structures to be
built.
There is no doubt that Mellish (in
particular Mr Mellish) has sieved the development control by-laws to determine
what aspects of
the construction are or may be in breach – I have
mentioned the major ones and do not intend to revisit them or deal with them
in
detail.
While the applicant states "The core of our dispute is that ... the construction is not in accordance with the Sanctuary Cove Principal Body Corporate by-laws", the real concern of the applicant is not that the respondent has breached development/construction by-laws, but that their river view has been limited and, they claim, the breeze to their lot also.
At the inspection I asked both the applicant and Mr Mellish what in
particular was their major objection to the structure. The response
was that
their view of the river towards the east was now reduced by the increased height
of the stepped wall constructed on the
respondent’s lot. An example of
that given was that while previously they enjoyed a view of the eastern reach of
the river
while breakfasting on the elevated area of their lot, that view was no
longer available.
I did point out to them that if the river end of the
stepped wall was reduced in height then while it is true that they may recover
some of that view, the privacy now afforded by that raised wall of persons using
the adjoining (pool) area of the respondent’s
lot, would be lost. Without
the wall the upper part of persons’ torsos would be visible. I suggested
that the loss of the
river-reach view (though retaining a much more significant
view of the river immediately adjoining their lot) was more than compensated
for
by the screening off of persons using the pool/recreation area in Lot 75.
Neither Mr nor Mrs Mellish agreed with that view and
of course that is a
personal matter.
However, it was and still is my opinion that this matter
is not a dispute of substance that warrants adjudication – it simply
largely concerns, in the end, views of a large part of the river as opposed to a
view of an even larger part of a river, and is a
matter that should be resolved
between the parties themselves, if necessary with the assistance of a trained
mediator. If that assistance
is necessary I would refer the parties to the
Dispute Resolution Centre of the Department of Justice and Attorney-General. I
have
read the submissions of the applicant in respect to the breaches of by-laws
and am of the opinion that the breaches, where they exist,
are minor in that
they have not led to any damage or adverse affect on the applicant’s use
and enjoyment of her lot. As to
the allegations against the PBC and ARC, a
Referee does not have a policing role and even if they did act as the applicant
maintains,
which I do not say, there is no sanction I can order of the kind
sought by the applicant.
Under the power available to me under section
75(4) of the BUGT Act, I dismiss the application.
Having made that
decision, it might be that the silence of the applicant in not pursuing the
progress of the application is because
an accommodation of the differences has
been reached with the respondent, or the applicant has accepted the structures
in preference
to a continuing point of contention with a neighbour, in which
case any order is of no service or value. However, in the absence
of a
withdrawal I have had to formally deal with it.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QBCCMCmr/2005/44.html